1、乌干达HIMA 850t/d水泥生产线 目 录Content一、编制依据Basis of edit1二、筒体结构滑模施工技术方案cylinder slip forming construction technical plan1三、生料库滑模施工RAW MILL SILO SLIP FORMING CONSTRUCTION3(一) 滑模工艺设计design of slip forming technics3(二) 外筒滑模平台设计design of out cylinder slip forming platform3(三) 内筒滑模平台设计design of inner cylinder s
2、lip forming platform7(四) 油路布置disposal of oil route10四、库壁结构滑升施工工艺SILO WALL STRUCTURE ELEVATING CONSTRUCTION TECHNICAL11(一) 滑升区段的划分elevation section division11(二) 滑模平台组装slip forming platform installation11(三) 组装顺序installation sequence错误!未定义书签。(四) 组装注意重点installation attention point12(五) 一个浇灌层滑模施工工艺流程on
3、e pouring layers slip forming construction technical flow13(六) 始滑first slip14(七) 钢筋和钢绞线绑扎reinforcing steel bars and bars tendon colligation14(八) 预留洞reserved holes16(九) 混凝土振捣concrete vibration17(十) 滑升sliding up18(十一) 平台的偏移及扭转的测量与控制flat form excursion & deviation measure and control19(十二) 操作平台的拆除和改装fl
4、at form back out and refit21五、滑模模板shuttering 21六、垂直运输VERTICAL TRANSPORTATION22七、应急措施及注意事项EMERGENCY METHOD AND NOTICED PROCEEDING22(一) 应急措施emergency method22(二) 施工注意事项construction attention items23八、安全技术措施SAFETY REGULATION ON SITE24- 2 -乌干达HIMA 850t/d水泥生产线 一、编制依据Basis of edit1)工程施工图;Project construct
5、ion drawings 2)工程招标文件;Project public bidding document3)工程相关的施工规范、规程及相关的质量评定标准;Project related construction criterion, regulation and related quality assess standard4)液压滑动模板施工技术规范(GBJ11387);Hydraulic slip shuttering construction technology regulation5)液压滑动模板施工安全技术规程(JGJ6589);Hydraulic slip shuttering
6、 construction technology and safety regulation6)建筑机械使用安全技术规程(JGJ332001)。Safety and technology regulation of using construction machines二、筒体结构滑模施工技术方案 Cylinder slip forming construction technical plan筒仓结构系按滑升模板工艺设计,滑升模板工艺系一次组装模板,连续浇灌成形,确保高质量地完成本工程的筒仓施工,做到内外壁圆滑无模板接痕,外壁做到清水滑模效果。Cylinder silo structure
7、is designed according to sliding up shuttering technology. Sliding up shuttering technology is that once install the shuttering and continue pouring to form to insure the accomplishment of high quality cylinder silo construction. It can make the inner and outer wall smooth without any shuttering con
8、nection mark and make the outer wall get the effect of rinsing slip forming. 1) 全部用GYD60大吨位千斤顶、482.75钢管作滑模支承杆。All slip forming support poles will use large tonnage jack and 482.75steel tube.2) 简化滑模平台,实际只设人行通道,即减轻平台荷载又方便施工。It should simplified slip forming platform. Actually just set up a walking pas
9、sage, which will reduce platform load as well as keep facility of construction 3) 柔性模板接缝之间夹一条海棉条,可以有效地防止板缝漏浆,同时使板缝拼接平整、圆滑,提高筒仓结构滑模的外观质量There is one piece sponge in the joint of flexible shuttering, which can effectively prevent leakage from the joint and at same time keep the joint flat, smooth to i
10、mprove the appearance of the cylinder silo structure slip forming 4) 滑模工程外观不好的另一主要原因是水泥浆沿筒壁流淌,为防止操作平台上水泥的流淌,在模板下口和模板间用6夹海绵条吸附水泥浆,操作人员在每层及时清理海绵内的水泥浆。Another reason for slip forming appearance drawback is that grout flow along cylinder wall. In order to stop the grout from control platform, use 6 spon
11、ge between shuttering below gob and shuttering to absorb grout. Controllers should clear up the group from sponge in each layer in time 5) 出模混凝土的处理措施:对出模混凝土及时进行原浆压光和对流淌水泥浆进行铲除,在吊架上环绕筒壁设一圈20铸铁管,在管上靠筒壁一侧均匀钻孔,用管道泵将水压入铸铁管,随滑模施工对筒壁混凝土进行喷淋。并派专人用清水均匀涂刷筒壁,最终达到表面圆滑、光洁、色泽基本一致的效果,同时在内外筒壁刷混凝土养护液养生。Disposal meas
12、ure of out shuttering concrete: press the out shuttering concrete to smooth in time and remove the flowing grout. On the scaffolding set a 20 cast iron tube around cylinder wall, drill equal holes on the tube next to cylinder wall, use tube pump compress water into cast iron tube, and then water can
13、 be sprayed to the concrete on cylinder wall during slip forming construction. Also special man should be arranged to brush the cylinder wall smoothly with clean water. Finally consistent effect of surface smooth, color and lustre will achieve. At the same time brush concrete maintenance liquid on i
14、nside and outside cylinder wall to maintain三、生料库滑模施工Raw meal silo slip forming construction1滑模工艺设计Design of slip forming technics根据图纸设计,生料库为预应力钢筋砼结构,外筒高 m,内径为 m,壁厚 m以下为 mm,以上为 mm,内筒高 m,内径为 m,壁厚为 mm,外筒每米砼量约为 m3,内筒每米砼量约为 m3,为保证砼的输送,在库外设一台塔吊和两台布料车进行施工。According to drawing design, raw mill silo is pre-s
15、tress bar concrete structure. Out cylinder is m high, inner diameter is m, wall is m thick, above is mm and below is mm, inner cylinder is m high, inner diameter is m, wall is mm thick. Concrete quantity per meter of out cylinder is m3, Concrete quantity per meter of inner cylinder is m3 In order to
16、 keep concrete transport, 1 tower crane and 2 material trucks prepared out of the silo for construction. 外筒筒壁从基础顶标高开始采用滑模施工,滑至标高10.8m处,空滑至13.6m标高,施工内筒及减压锥底板。待减压锥底板施工完毕后改装滑模平台滑至77.2m。Out cylinder wall begins slip forming construction from foundation top elevation. After slide to 10.8m elevation, slid
17、e with empty concrete to 13.6m elevation where reach the construction inner cylinder and decompress cone bottom board. After decompress cone bottom board construction finish, refit the slip forming platform and slide to 77.2m 2.外筒滑模平台设计design of out cylinder slip forming platform1)筒壁布置提升架和千斤顶,平台构件布置
18、见平面布置图。Set hoist frame and jack beside cylinder wall. Platform components disposal see plane disposal drawing2)筒体平台荷载计算:Cylinder platform load calculation根据设计滑模装置的荷载参考值,模板、围圈及提升架等自重、摩阻力按模板面积计算,操作平台及吊架自重、施工荷载按平台面积计算。According to designed reference number of slip forming equipment load, deadweight, ru
19、b resistance of shuttering, pen and hoist frame, etc are calculated on shuttering acreage, while control platform, tower crane deadweight and construction load is calculated on platform acreage.S模板shuttering214.78,S平台platform420.60序号No.荷载名称load name荷载值(KN)load number1内外平台及吊架自重inside and outside plat
20、form and tower crane deadweight1.0420.6=420.62模板、围圈及提升架自重shuttering, pen and hoist frame deadweight0.8214.78=171.8243摩阻力rub resistance1.8214.78=386.6044施工荷载construction load1.0420.6=420.65总荷载total load1399.6283)千斤顶需用量计算Calculation of needed jack 千斤顶最少需用量计算calculation of jacks minimum number needed:n
21、=N/P=1399.628/30=47台综合考虑抗风要求和构造、稳定性等因素实际布置千斤顶76台,提升架76榀,千斤顶和提升架的布置详见滑模平面结构布置图。Well think of the factors about anti-wind requirement and structure, stability, etc 76 jacks and 76 hoist frames are actually disposed. Detailed disposal of Jack and hoist frame see slip forming plane disposal drawing千斤顶实际
22、承载能力计算:The actual load capacity calculation: P=N/n=1399.628/76=18.5KN30KN 故安全。So it is safe4)支承杆计算supporting pole calculation千斤顶爬升用支承杆采用483.5脚手架钢管,每根支承杆的实际承受荷载18.5KN。jack rising supporting pole will use483.5 scaffolding steel tube. And each n supporting poles actual load is 18.5KN 支承杆容许荷载计算supportin
23、g pole admitting load calculation :P0=afAn式中formula:P0-支承杆允许承载力(KN);Supporting pole admitting load weightf-支承杆钢材强度设计值,取20KN/cm2;Supporting pole steel intensity designing figureAn-支承杆截面积为4.89 cm2;Supporting pole section area is 4.89 cm2a-工作条件系数,取0.7;Working condition modulus-轴心受压杆件的稳定系数,计算出杆的长细比值,查现行
24、钢结构设计规范得值。=(0.75L1)/1.58 Stability modulus of pressed poles in axes. Calculate the length and thinness ratio checked attachment from present “steel structure design regulation” will get L1-支承杆计算长度。按提空时最不利的状态计算,模板下口至千斤顶下卡头距离195cm。Supporting pole length calculation. Suppose the worst condition calcula
25、tion during empty rise, the distance between shuttering bottom hole and jack bottom clip head is 195cm以上数据代入上式得:put above data into the formula make: =(0.75195)/1.58=93 查表取值check from table =0.6P0=0.7200.64.89 41.084KN18.5KN;即按照整个滑模平台托空时的最不利状态计算,支承杆的承载能力大于实际负荷,故十分安全。That is when calculate on the bas
26、is of the worst condition during the whole slip forming platform empty load, supporting pole s load capacity is larger than actual load. So it is very safe. 5)液压系统设计hydraulic pressure system designa、液压系统计算hydraulic pressure system calculation序号No参数名称reference name参 数 值reference number1滑模装置总荷载slip fo
27、rming equipment total loadN=1399.628KN2千斤顶油缸容积jack oil tank capacityV=0.261n=0.26176=19.84L3千斤顶活塞总面积jack piston total areaA=7457n=745776=566732mm24千斤顶弹簧总压力jack spring total pressurePt=0.3n=0.376=22.8KN5所需工作压力required working pressureP= (N+Pt)/A+P/=(1399.628+22.8)1000/566732+0.1/0.6=4.19MPa6齿轮泵流量gear
28、 pump fluxQ=VK/t=19.841.2/1=23.81L/minb、液压系统选型hydraulic pressure system types selection选用HY56型液压控制台,其技术参数如下:selecting HY56 hydraulic pressure control platform, technology reference will be as follow: HY56型液压控制台HY56 hydraulic pressure control platform参数名称reference name参 数 值reference number参数名称referen
29、ce name参 数 值reference number工作压力working pressure8MPa油箱容积oil tank capacity56L最高压力the highest pressure10MPa电机功率electrical engine power10KW流量flux56L/min3. 内筒滑模平台设计Design of inner cylinder slip forming platform1)筒壁布置提升架和千斤顶,平台构件布置见平面布置图。Set hoist frame and jack beside cylinder wall. Platform components
30、disposal see plane disposal drawing 2)筒体平台荷载计算:Cylinder platform load calculation根据设计滑模装置的荷载参考值,模板、围圈及提升架等自重、摩阻力按模板面积计算,操作平台及吊架自重、施工荷载按平台面积计算。According to designed reference number of slip forming equipment load, deadweight, rub resistance of shuttering, pen and hoist frame, etc are calculated on sh
31、uttering acreage, while control platform, tower crane deadweight and construction load is calculated on platform acreage.S模板149.22,S平台298.43序号No.荷载名称load name荷载值(KN)load number1内外平台及吊架自重inside and outside platform and tower crane deadweight1.0298.43=298.432模板、围圈及提升架自重shuttering, pen and hoist frame
32、deadweight0.8149.22=119.3763摩阻力rub resistance1.8149.22=268.5964施工荷载construction load 1.0298.43=298.435总荷载total load984.8323)千斤顶需用量计算Calculation of needed jacks千斤顶最少需用量计算calculation of jacks minimum number needed:n=N/P=984.832/30=33台综合考虑抗风要求和构造、稳定性等因素实际布置千斤顶40台,提升架40榀,千斤顶和提升架的布置详见滑模平面结构布置图。Well think
33、 of the factors about anti-wind requirement and structure, stability, etc 40 jacks and 40 hoist frames are actually disposed. Detailed disposal of Jack and hoist frame see slip forming plane disposal drawing千斤顶实际承载能力计算:The actual load capacity calculation of the jack:P=N/n=984.832/40=24.62KN30KN 故安全
34、。So it is safe4)支承杆计算supporting pole calculation千斤顶爬升用支承杆采用483.5脚手架钢管,每根支承杆的实际承受荷载24.62KN。Jack rising supporting pole will use483.5 scaffolding steel tube. And each supporting poles actual load is 24.62KN 支承杆容许荷载计算supporting pole admitting load calculation:P0=afAn式中:formulaP0-支承杆允许承载力(KN);Supporting
35、 pole admitting load weightf-支承杆钢材强度设计值,取20KN/cm2;Supporting pole steel intensity designing figure adopt 20KN/cm2An-支承杆截面积为4.89 cm2;Supporting pole section area is 4.89 cm2a-工作条件系数,取0.7;Working condition modulus adopt 0.7-轴心受压杆件的稳定系数,计算出杆的长细比值,查现行钢结构设计规范附表得值。=(0.75L1)/1.58 Stability modulus of press
36、ed poles in axes. Calculate the length and thinness ratio check attachment from present “steel structure design regulation” will get L1-支承杆计算长度。按提空时最不利的状态计算,模板下口至千斤顶下卡头距离195cm。Supporting pole length calculation. Suppose the worst condition calculation during empty rise, the distance between shutteri
37、ng bottom hole and jack bottom clip head is 195cm以上数据代入上式得:Put above data into the formula make:=(0.75195)/1.58=93 查表取值check from table=0.6P0=0.7200.64.89 41.084KN24.62KN;即按照整个滑模平台托空时的最不利状态计算,支承杆的承载能力大于实际负荷,故安全。That is when calculate on the basis of the worst condition during the whole slip forming
38、platform empty load, supporting pole s load capacity is larger than actual load. So it is safe. 5)液压系统设计 Hydraulic pressure system designa、液压系统计算 Hydraulic pressure system calculation序号No.参数名称reference name参 数 值reference number1滑模装置总荷载slip forming equipment total loadN=984.832KN2千斤顶油缸容积jack oil tank
39、 capacityV=0.261n=0.26140=10.44L3千斤顶活塞总面积jack piston total areaA=7457n=745740=298280mm24千斤顶弹簧总压力jack spring total pressurePt=0.3n=0.340=12KN5所需工作压力required working pressureP= (N+Pt)/A+P/=(984.832+12)1000/298280+0.1/0.6=5.74MPa6齿轮泵流量gear pump fluxQ=VK/t=10.441.2/1=12.53L/minb、液压系统选型 hydraulic pressur
40、e system types selection选用HY56型液压控制台,其技术参数如下:selecting HY56 hydraulic pressure control platform, technology reference will be as follow: HY56型液压控制台HY56 hydraulic pressure control platform参数名称reference name参 数 值reference number参数名称reference name参 数 值reference number工作压力working pressure8MPa油箱容积oil tan
41、k capacity56L最高压力the highest pressure10MPa电机功率electrical engine power10KW流量flux56L/min4. 油路布置disposal of oil route 千斤顶的油路布置原则,应使千斤顶尽可能地同步工作,达到压力传递均匀,方便控制和纠偏的目的。不同结构类别的滑模工程,其油路布置是不一样的。而千斤顶位置随着提升架的布置而确定。Principle of jack oil route disposal is that taking every means to make jacks work synchronize, so
42、that pressure can be delivered equally and reach the aim of convenient to control and rectify. Different type structure of slip forming project, its oil route disposal is different. While the location of the jack is fixed with the disposal of hoist frame 本工程拟采用三级分组并联油路布置,一级主油管选用19mm高压耐油橡胶管,二级分油管选用13
43、mm高压耐油橡胶软管,支油管选用10mm高压软管伸向各千斤顶;分油器采用无缝钢管制作。一级分油器,一进六出(根据建筑平面每一方各一条分油路);二级分油器一进三出,各主油管长度和直径均取其相等,并作环形布置有利于均衡滑升;三级分油器一进六出通向各千斤顶,每级、每组均设有截流阀加以控制,千斤顶单独设针形阀,这样方便纠编和抽拔支承杆。This project is planning to adopt 3 class groups and parallel connection of oil disposal. The first class main oil pipe will choose 19m
44、m high pressure and oil endurance rubber pipe. The second class separate oil pipe will choose 13mm high pressure and oil endurance rubber pipe. Branch oil pipe will choose 10mm high pressure tube to run out to each jacks. Oil separator will adopt seamless steel pipe for manufacture. The first class
45、oil separator will come out 6 parts after 1 enter (according to construction plane, each side should have one oil route). The second oil separator will come out 3 parts after 1 enter. Length and diameter of each main pipe are all selected the same. And rounding disposal will be used in favor of equi
46、librium sliding up. The third oil separator will come out 6 parts after 1enter to each jack. Every class and every group will dispose a shutting valve to control. Jacks will separately use needle valve, which be convenient to rectify and pull out the supporting pole.四、库壁结构滑升施工工艺Silo wall structure e
47、levating construction technical1. 滑升区段的划分Elevation section division根据经济和可行的原则考虑,从基础顶标高开始的竖向结构采用滑模工艺施工。Think of the economic and feasible principle, from the foundation top the vertical structure adopt slip forming technology to construct2. 滑模平台组装Slip forming platform installation滑模平台结构详见滑模平台布置图。Slip forming platform structure see “slip formin