收藏 分销(赏)

PPR管综合项目施工专项方案.docx

上传人:精**** 文档编号:2728271 上传时间:2024-06-05 格式:DOCX 页数:8 大小:3.04MB
下载 相关 举报
PPR管综合项目施工专项方案.docx_第1页
第1页 / 共8页
PPR管综合项目施工专项方案.docx_第2页
第2页 / 共8页
PPR管综合项目施工专项方案.docx_第3页
第3页 / 共8页
PPR管综合项目施工专项方案.docx_第4页
第4页 / 共8页
PPR管综合项目施工专项方案.docx_第5页
第5页 / 共8页
点击查看更多>>
资源描述

1、1.1.1. PPR管道施工工艺 PPR pipe installation method1.1.1.1. 编制依据Basis of drawing up1.1给水排水管道工程施工及验收规范GB50268-97。Construction and acceptance norm of Water supply and drains piping engineering。1.2室内管道支架及吊架03S402Piping support indoor。1.1.1.2. 施工工艺:Construction technique: 依据现场多种管线部署情况和步骤次序确定工艺步骤,本工程采取以下工艺步骤:施

2、工准备材料进货检验PPR管预制加工支吊架制作安装PPR管安装PPR管试验According to the arrangement and flow order of field all kinds of pipelines, confirm the process flow. This engineering adopts the following process flow: construction preparationmaterial stocking testPPR pipe pre-processingmanufacture and installation of support

3、and hangerinstallation of PPR pipePPR pipe test 1). 施工准备:Construction preparation 施工工作及技术人员认真熟悉原图纸,领会设计意图,对图纸中和实际管道部署清楚后,才能施工。 Construction work and technicians are strictly familiar with the original drawing, comprehend design purpose, and carry out the construction after the clarity to drawing and

4、 actual pipeline arrangement. 施工人员须熟悉PPR管通常性能,掌握必需操作关键点。在各项预制加工项目开始前,依据实际编制材料计划,将需要材料、设备等按规格、型号准备好,运至现场。Constructer must know well the general performance of PPR, master necessary operation points,Before each precast processing project, according to the plan of practical scheduling material, well pr

5、epare the needed material and equipment according to specification and model and transport to the field. 材料设备要求:到现场管材、管件等提供管材和管件应符合设计要求,并附有产品说明书和质量合格证书,须认真检验并经业主验明材质,查对质保书,规格、型号等,合格后方能入库,并分别作好标识。Material equipment requirements: The offered field pipe and pipe fittings should accord with design presc

6、ription, adding with product stipulation and quality certification. Strictly examine and identify material by owner, check quality guarantee, specification and models etc, warehouse after qualification, and mark separately. 管材和管件内外壁应光滑平整,无气泡、裂纹、脱皮和显著痕纹、凹陷,色泽应基础一致。不得使用有损坏迹象材料。如发觉管道质量有异常,应在使用前进行复检。The

7、 internal and external surface of pipe and pipe fittings should be smooth and flat, without air bladder, crack, desquamate, obvious trace and hollow, and the color and luster should be consistent. The material with damaged mark should be forbidden. If it is discovered that there is problem in the pi

8、peline quality, recheck it before using. 管材端面应垂直于管材轴线。管件应完整、无缺损、无变形。End face of pipe should be upright to the axes of pipe. The pipe fittings should be intact, without lack and distortion. 管件和管材不应长久置于阳光下照射,为避免管子在储运时弯曲,堆放应平整。搬运管材和管件时,应小心轻放,避免油污,严禁猛烈撞击,和尖锐物触碰和抛、摔、拖。管材开口处应立即封堵,以免管道堵塞造成无须要浪费。Pipe fittin

9、g and pipe should not be placed in the sunshine for a long time to avoid the pipe curve in storage and transportation, and piling up them should be level. When conveying pipe and pipe fittings, they should handled with care and avoid oil stain. Strong bump, cast, throw and draw is forbidden. Pipe ha

10、tch should be immediately plugged to avoid pipe jam and unnecessary waste. 施工现场和材料存放处温差较大时,应于安装前将管件和管材在现场放置一定时间,使其温度靠近施工现场环境温度。When there is large difference in construction field and storage temperature, should place pipe fitting and pipe at the field before installation for certain time and make i

11、ts temperature closure to environment temperature of construction field. 本项目PPR管道采取热熔连接,施工前应仔细检验所使用热熔机具、割刀是否符合要求和正常使用,使用电源及电线是否正常和安全。以下图:This project pipe-PPR pipe adopts heat fusion. Before construction, should carefully examine whether the using hot melt equipment and cutter knife accord with requ

12、irements and normal service, the using power supply and wire are normal and security. as the following drawings. 材料进货检验: Material-stocking test 为确保安装质量,材料进货时应严格检验,其管径椭圆率应10%,管材同一截面壁厚偏差应14%,内外壁应光滑、平整,无气泡、裂口、裂纹、凹陷、脱皮和严重冷斑及显著痕迹。For insuring the installation quality, should strictly test the material wh

13、en it is stocked. The ellipticity of pipe diameter should be less than 10%. The wall thickness deviation in the same pipe section should be less than 14%. The internal and external surface should be smooth, flat, without air bladder, crack, hollowing desquamate, severe cold appearance and obvious tr

14、ace.2). PPR管道预制加工: Precast processing of inner pipe PEpipelinePE管连接:采取热熔连接方法。热熔连接最为可靠,操作方便,气密性好,接口强度高。本方案中热熔焊接为关键工序,具体方案以下:PPR pipe connection: adopt hot melt connection method. Hot melt method is the most reliable, with convenient operation and good air tightness and high joint strength. In this pr

15、oject, sweating soldering is the key working procedure; the detail project is as the followings. (1)PPR管道接触式焊接安装PE pipe touch welding installation其施工方法及技术方法以下:Method of execution of works and actions to be taken管道连接采取热熔焊接。热熔焊接为关键工序,必需严格控制。The piping conjunction adopts hot melt to weld. The hot melt

16、weld is the key work , have to control strictly. 管道焊接关键程序:The piping welds main procedure:A:设置焊机初始值(液压值、温度);Establish the initial value of the welding machine(the liquid presses value, temperature)液压值设置:The constitution of the liquid presses value管径DN100MM以下,液压值设定为 0.2 MPa; Diameter of pipe is DN100

17、 MM the following, the liquid presses value to set for 0.2 MPa;管径DN100-350MM时,液压值设定为0.4-0.5MPa;Diameter of pipe is DN100-DN350 MM, the liquid presses value to set for 0.4-0.5 MPa;温度设置: The constitution of the temperature 加热板预热时,温度设定为210;Heat plank prepare hot, the temperature sets to 210 ;加热焊口时,温度设定

18、为190-210.While heating the welding , the temperature sets to 190-210 .B:固定焊管,确保待焊接管及管件中心在一条直线上,错口应在2毫米以内;Fix the welding pipe, assurance treats to welding pipe and fittings center is on a straight line, Distance of shunt should at 2mm in;C:抛磨管端口,确保端口平整,再用医用酒精清洗管端口,确保端口内外壁清洁;Throw to whet pipes head,

19、 promise pipes head neat, use again to cure to clean pipes head with the alcohol, promise the inside and outside wall of pipes head to clean;D:室外温度为20C时加热管及管件端口焊接参数以下表 Outdoor temperature is at 20 C heating pipe and tube port welding parameters following tableE:取出焊接好管段,检验焊口,焊口宽度、高度、形状、均匀度等均符合焊接标准即为合

20、格,方可安装。Take out to welding pipe, check the welding sew , the welding sew width, height, shape, even degree.etc. all matching to weld standard is qualified, then be able to install. 3). 管道试压及冲洗Pipeline Pressure Testing and Flushinga). 管道试压:Pipeline Pressure Testing管道安装完成,应按设计要求对管道系统进行强度、严密性等试验,以检验管道系

21、统及各连接部位工程质量。 After installation, pipeline should be taken strength testing and hermetic testing according to design as well as the quality test of pipeline system and connections.管道用水作介质进行强度及严密性试验;应根据设计具体要求采取。如设计无要求时,工作压力不低于0.07MPa管道通常采取水压试验,工作压力低于0.07MPa管道通常采取气压试验。Media of strength testing and herm

22、etic testing is water and the water used for test should meet the relative standards. If no request in design, it usually goes like below: pipeline with work pressure more than 0.07MPa should be taken water pressure testing; pipeline with work pressure less than 0.07MPa should be taken air pressure

23、test.1)管道系统试验前应含有以下条件:Following conditions should be met before testing:A.管路系统施工安装完成,且符合设计和规范要求。Finish the pipeline system installation and meet the design and specification request.B.全部支、吊架安装完成且合格。 Supports installation should be finished and qualified. C.管道位置、标高、坡度、坡向等经复查合格;试验用临时加固方法经检验确定安全可靠。Pipe

24、lines position, elevation, gradient and slop direction should be qualified. The temporary facility used for test should be stable and safe. D.试验用压力表经校验合格,并做好标识;精度不低于1.5级,表满刻度值为最大被测压力1.52倍;试验压力表不少于2块。Pressure meter used for test should be ok and marked with precision no less than 1.5-level. The full

25、scale value should be 1.5-2 times as biggest tested-pressure.2)具体试验方法宜采取分区、分层试压和系统试压相结合方法。分区、分层试压时,待系统充满水且放净空气后进行加压,先把管网或管段压力升至试验压力,稳压10分钟,压力不得下降,再将压力降至工作压力,在60分钟内压力不得下降、外观检验无渗漏为合格。系统试压时以最低点压力为准,压力升至试验压力后,稳压10分钟,压力下降不得大于20Kpa,再将系统压力降至工作压力,外观检验无渗漏为合格。通知相关人员验收、办理交接手续,然后把水泄净、拆除试压泵和水源。The test method is

26、 to be chosen the combination of subarea test and delamination test. When doing test, add pressure after pipe is full of water and without air in. First increase the pressure of pipeline net or pipe section to tested pressure and keep it for 10min with no descending of work pressure. Then lower the

27、pressure to work pressure for 60min to check if there are any leakages. No leakages are qualified. When doing test for pipeline system, first increase the pressure from the lowest to tested-pressure and keep it for 10min with pressure decline less than 20Kpa. Then lower the system pressure to work p

28、ressure to check if there are any leakages. No leakages are qualified. Finally notice relative personnel for check and discharge the water in pipe and remove the pressure-testing pump and shut off water supply.3)试验时不得敲击管道。Dont beat the pipe when testing.4)试压完成后,恢复原有设备、表计,并拆除隔断用盲板,试验后填写试压统计并作好验收签证。Re

29、cover the equipment and meter and remove the blind plate for partition after test. Then fill the test record.b). 管道冲洗 Pipeline blowing and flushing管道水系统冲洗:Pipeline Flushing of Water Pipe System:1)调试、运行前必需进行系统冲洗:水系统主、干管必需开式进行冲洗排污,反复数次直至确定清洁,然后才许可转入封闭式循环过滤(管网、机组、设备整体进行),反复清理过滤器,直到整个系统洁净、清洁。It must do

30、flushing after test and commissioning: main pipe and branches should be down flushing repeatedly and then it may be in closed circling filtration (include pipeline net, units, equipment). Clean the filter again and again until the system is clean.2)管道系统在清洗前必需把设备和系统分离开(即关闭设备进出口阀门),开启旁通阀(能够临时设置),向管网最高

31、点灌水,直到系统灌满水为止;接着从系统最低点处把脏水放出,按上述方法反复数次,直至系统无脏物;然后开启冷冻水泵、冷却水泵,使水循环数次,停泵后将系统水放尽,检验水过滤器,确定系统管网清洁时止。Separate the equipment form the system before flushing, that is, to close the valve connecting the equipment. Open the bypass valve (can be installed temporarily), fill water from highest point until it i

32、s full, then discharge the dirty water from the lowest point. Do as above repeatedly until theres no filth in system. Start the condensation water pump, cooling water pump to circle the water for many times. Then stop the pump to check the water filter unitl the system net is clean or not.3)冲洗前还应将管路

33、上安装流量孔板、滤网、温度计、调整阀等拆除,待冲洗合格后再恢复安装。Remove the flow pore plate, filtering net, thermometer and adjust valve before flushing. Install them after it is qualified.4)管道冲洗进水口及排水口应选择合适位置,并能确保将管道系统内杂物冲洗洁净,其截面积大于被冲洗管道截面。 Chose suitable position for enter and exit for flushing and ensure it can clean the filth in pipe. The section area of enter and exit should no less the 60% of pipe section area of pipe flushed.5)冲洗水应排入指定泄水点,避免出现跑水事故。Flushing water should discharge in pointed

展开阅读全文
相似文档                                   自信AI助手自信AI助手
猜你喜欢                                   自信AI导航自信AI导航
搜索标签

当前位置:首页 > 品牌综合 > 施工方案/组织设计

移动网页_全站_页脚广告1

关于我们      便捷服务       自信AI       AI导航        获赠5币

©2010-2024 宁波自信网络信息技术有限公司  版权所有

客服电话:4008-655-100  投诉/维权电话:4009-655-100

gongan.png浙公网安备33021202000488号   

icp.png浙ICP备2021020529号-1  |  浙B2-20240490  

关注我们 :gzh.png    weibo.png    LOFTER.png 

客服