资源描述

1、接管和法兰Nozzle and the flange将坡口加工好接口和相对应法兰进行组装,要求:间隙34mm,错边在1.5mm以下,氩弧焊打底,全熔透结构。焊接完成后送无损检测,检验标准RT( )%,级合格。Assemble the groove machined nozzle with the corresponding flange, requirements: the gap is 3 4mm, the staggered side is less than 1.5mm, argon arc bottoming, full penetration structure. After wel

2、ding,having a non-destructive testing, the inspection standards is RT () class, III qualified.支座点焊Supportswelding1.按图对支座底板、筋板、立板进行组装前检验。In accordance with drawings, inspect the supports backplane, ribs, riser before assembling.2.组装各部件,点固,加支撑件等,焊接。Assemble every component, solid point, support pieces

3、, and welding.接管支座和壳体组装Nozzle supports and shell assembling1.按先前标出0、90、180、270方位点,延长在壳体上。Base on the previously marked 0 , 90 , 180 , 270 compass points, extending to the hcase.2.画出接管、支座,预开孔,安装位置,即坐标点。Draw the nozzle, supports, pre-openings, the installation location, that is, the coordinates of poi

4、nts3.检验合格后,开孔,然后打上坡口,角度为外坡口30After Inspection, opening, then grooving,the angle of the outer groove is30 4.组对接管和壳体,组装前,接管必需将补强圈带上固定好,一起装配。Connect nozzle to shell, before assembling,the nozzle must fix the reinforcement ring,along with the equipment.5.接管和壳体组对间隙为23mm,且间隙均匀。The gap of the nozzle and sh

5、ell is 2 3mm, and the gap is uniform6.焊接完成后,内接管须清根封底,焊缝打磨和母材齐,并倒245圆角。After welding, to nozzle requires to clear the root of the back cover, weld and polise to ensure the base metal level, and the fillet is 2 45 .管箱Tube box1.封头:材质确定,标识移植,切割,外协模压,回厂检验,材质为( ),( )。Head: Material confirmation , mark and

6、 transplante, cutting, outsourcing molding, back to the factory inspection, the material is (), ().2.短节:材质确定 a.按排版图尺寸划线下料坡口加工。(见具体工艺文件) Short section: material confirmation a. Drawing, crossed material and groove processing by the size of the layout chart. (See the specific process documents). b.卷板,

7、纵缝焊接,校圆,纵缝RT( )%,级合格,车加工削薄。 b. coil, longitudinal seam welding , regulate round, longitudinal seam RT (), III class qualified ,vehicle processing thinning.3.管箱法兰和短节组装:a.管箱法兰和短节组焊,封头和短节组焊。Flange and short section of the tube box assembly: a. tube box flange and a short section welding,the head and a

8、short section welding。b.对环缝进行射线检测。Ring sewn-ray detection.c.和壳体联接,整体划线,开孔,接管组装,焊接,确保其整体一致性。Connection with the shell, the overall drawing,openings, nozzle assembly, welding, ensure that its overall consistency.d.卸下管箱,对接管法兰清根封底,划出隔板安装线,再按封头实样放样切割,装配隔板和焊接,装配要求:每层隔板端口尺寸必需和固定端管板( )槽一致吻合。(d) Remove the t

9、ube box, clear the root of the nozzle of the flange, draw the bulkhead install line, and then cutting base on the real shape of the head, assembling the bulkhead and welding, assembly requirements:each partition port size must be consistent with the fixed end of the tube plate () notch.e.做好热处理前支撑,预防

10、热处理使隔板变形。Do good support before heat treatment to prevent heat treatment so that bulkhead deformationf.热处理完成冷却后,再加工密封面,确保法兰密封面和隔板端平面一致。After the heat treatment and cooling, reprocessing the sealing surface to ensure the flange sealing surface and the baffle-side plane consistent.外头盖the outsidebonnet

11、1.封头:材质确定 划线,标识移植,切割,外协模压,回厂检验,贴合格标签。Head: The material confirmation, mark and transplante, cutting, outsourcing molded, back to the factory inspection, paste qualified label.2.短节:材质确定 按图尺寸划线,切割,坡口精加工,卷板,焊接,校园。Short sections: materials confirmation drawing base on the size of the chart, cutting and

12、finishing of the groove, plate bending, welding, regulate round.3.法兰和封头,短节组焊:a.将合格封头和短节及对应法兰组焊,错边量控制在02mm之间。Flange and the head, a short section of welding: (a) welding the qualified head ,a short section and the corresponding flange, the stagger volume is controlled between 0 2mm.b.环缝焊接,无损检测。(b).Th

13、e girth welding, nondestructive testing.c.划线开孔,安装管嘴和吊耳,焊接 (c). Drawing and opening, install the nozzle and lug ,welding.d.和壳体、管箱、浮头盖,一并整体热处理。(d).The shell, tube box, floating cover, together with the overall heat treatment.浮头盖Floating bonnet1.拱盖:材质确定 划线下料,标识移植、切割,外协模压、回厂检验。Ledge: material confirmati

14、on Drawing and cutting, mark transplantation, cutting, outsourcing molding, back to the factory inspection.2.浮头法兰:在材料检验员指定下领取贴有合格标签法兰。 Floating head flange: receive designated qualified label of the flange under the guidiance of the materials inspector .3.将拱盖和浮头法兰组装,装配尺寸图。Assemble ledge and floating

15、 head flange, the assembly size shown in Figure。4.焊接完成后,再按拱盖实形放样、隔板、切割、组装、焊接,确保隔板装配尺寸和浮动管板槽尺寸一致。After welding, the then loft base on the real shape, bulkhead,cutting, assembling, welding, ensure size of the bulkhead, assembly size and floating tube notch groove consistent.5.和前壳体、外头盖及管箱一并进炉热处理。Having

16、 a heat treatment furnace to the front shell, the outside bonnet and the tube box .管束tube bundle换热管1材质确定:( )( ) 规格( )。Material confirmation: ( )( ) Specification().2单管试压,试验压力为设计压力2倍,即( )MPa。Single-tube testing pressure,the pressure is 2 times the design pressure,that is () MPa.管板本锻件应按JB4726制造和验收,进行P

17、T检测,依图数控放样、钻孔、隔板槽铣加工、倒坡口、拉丝孔攻丝。The forgings shall be JB4726 manufacture and acceptance ,PT detection, according to Figure NC loft, drilling, the bulkhead.slot milling, chamfer the groove, wire drawing hole tapping.折流板1.材质确定,Q235B,16,数控放样切割,去渣,整形,打垛点固焊。Material confirmation,Q235, 16, CNC cutting loft

18、, remove the residue, shaping, playing stack point of solid welding.2.数控划线,钻孔,折流板车园,做标识次序号,单块剪切去毛刺。NC drawing, drilling, baffle to car round, mark the order number, a single block of shear deburring.3.次序号移植,管孔倒角,折流板打磨,整形。Sequence number transplantation, pore chamfer, baffle polished, plastic管束其它辅件加工

19、定距管机加工,拉杆端点过丝,滑道旁路挡板剪切下料、整形。Distance tube machining, rod endpoint wire, slide the bypass damper shear cutting, shaping.管束组装1.立架:先将固定管板直于工装平台架上,依次按图安装拉杆、距管、折流板,锁紧拉杆螺姆。Stands: first fixed tube plate straight to the tooling platform rack, followed by the plan to install the rod ,the distance tube, baff

20、le, locking lever screw farm2.处理管板孔和管板面上油污、锈蚀等。Dealing with the tube sheet holes and the tube sheet surface oil, corrosion, etc.3.穿管:穿管完成后再上浮动管板,定尺定位,点焊,再回管。Tube cross: crossing the tube ,then installing the floating tube sheet, length positioning, spot welding and then back to the tube.4.管头焊、切管、打磨、

21、浮动端管头焊,支耳调试,安装焊接,管头两端热处理。Tube head welding, tube cutting, polishing, floating side tube head welding, lugs debugging, install the welding, the tube head at both ends of heat treatment5.胀管(见胀管工艺卡),胀管器按编号到仓库领用,规格为( )( )( )。Expander (see the expanding technology card), the expander by number to the war

22、ehouse recipients, specifications are ( )( )( ).6.安装滑道并焊接。Installation of slide and welding管束试压管头试压,试验压力( )MPa(见试压工艺)水压试验时下列情况为合格:无渗漏,无可见变形,过程中无异常响声。Tube head pressure test, the test pressure is () MPa (see Pressure Test) .hydrostatic test, the following conditions are eligible: no leakage, no visib

23、le distortion, no abnormal noise in the process.整体试 压overall pressure test1.将管束试压合格后,装入壳体中After passing the pressure test,put the bundle into the shell.2.安装两端管箱,浮头盖,装配时注意垫片保护,均匀将几件螺栓紧固。安装管箱,浮头盖时,一定做好隔板槽和隔板衔接口标识,稳合统一。Install both ends of tube box, floating bonnet ,pay attention to the protection of t

24、he gasket assembly, bolt a few pieces evenly. When installing the pipe box, floating head cover, be sure to do the partition groove and clapboard convergence mouth mark, stable co-unified.3.螺栓拧紧时,要分步骤,先预紧等分四颗,即0、90、180、270,再逐步对称紧固。用力要均匀,最终对螺栓进行全方面紧固。When tightening the bolts, step by step, decile fo

25、ur first , namely, 0 , 90 , 180 , 270 , and then gradually tighten the symmetry. Forced evenly, at last full tightening the bolts.4.将管箱上( )孔,即下端接管用盲板封住,紧螺栓,( )注水,用行车配合作业,上下往返起落,将管程中空气排净为止,状态为不显现汽泡静止面,再封住( )口,紧固螺栓。Tube box () hole, seal the bottom nozzle by the blind plate,bolt, () inject, operate wi

26、th a driving car, up and down, until draining the process air of the tube , the state does not show bubble stationary surface, and then sealed () and tighten the bolts.5.按试压工艺卡,分步骤循序淅升。According to the pressure test card, step-by-step sequential Hsi-l.6.检验易池漏区、面和焊道,无泄漏,无异常响动为合格。Test the leak area, s

27、urface and weld, no leaks and no unusual ring for qualified. 7.组装外头盖,同上紧固螺母,封堵壳程( )口和外头盖下方管嘴。Assemble the bonnet, ditto fastening the nut and sealing the shell ()outlet and the nozzle below the outside bonnet.8.( )和( )注水,同上方法排净空气,封住( )和( )口,紧固螺栓。()and () injection, ditto drain the air, seal () and()

28、 port and tighten the bolts.9.稳步升压至试验区域线,检验,无漏点和异样响声为合格。Steady boost to the test area line, check no leak point and strange sound for qualified.10.排净体内积水,用压缩空气吹干。Drain the body of water, dry with compressed air.11.喷砂,外观处理,喷砂时对螺栓要做好保护方法,油漆(见工艺卡)包装。Sandblasting, processing the appearance,when blasting the bolts ,taking protective measures, painting (see process card) packaging.

展开阅读全文
相似文档                                   自信AI助手自信AI助手
猜你喜欢                                   自信AI导航自信AI导航
搜索标签

当前位置:首页 > 品牌综合 > 技术交底/工艺/施工标准

移动网页_全站_页脚广告1

关于我们      便捷服务       自信AI       AI导航        获赠5币

©2010-2024 宁波自信网络信息技术有限公司  版权所有

客服电话:4008-655-100  投诉/维权电话:4009-655-100

gongan.png浙公网安备33021202000488号   

icp.png浙ICP备2021020529号-1  |  浙B2-20240490  

关注我们 :gzh.png    weibo.png    LOFTER.png 

客服