资源描述
新鹏·盛世临港
冬季专项施工方案
编 制:
审 核:
批 准:
五洋建设集团股份有限公司
新鹏·盛世临港项目部
二○一二年十一月
目 录
1、 编制依据··························································3
2、 工程概况··························································3
3、 施工安排··························································4
3.1时间安排·······················································4
3.2冬施组织安排···················································4
4、施工准备···························································5
4.1技术准备·······················································5
4.2生产准备·······················································6
4.3材料准备·······················································6
4.4临设准备·······················································7
5、施工方法及技术措施·················································7
5.1防水工程·······················································7
5.2钢筋工程·······················································7
5.3模板工程·······················································8
5.4混凝土工程·····················································9
5.5二次结构施工···················································14
5.6装饰工程·······················································15
5.7安装工程·······················································16
5.8土方回填·······················································16
6、施工管理措施·······················································18
6.1质量保证措施···················································18
6.2安全措施·······················································18
6.3文明环保措施···················································19
6.4消防措施·······················································20
7、应急预案及相应措施·················································20
1 编制依据
序号
名 称
编 号
备 注
1
盛世临港施工图纸
建施、结施全套
核工业西南勘察设计研究院有限责任公司
2
盛世临港施工组织设计
2023年7月
3
混凝土结构工程施工质量验收规范
GB50204-2023
国家
4
混凝土强度检查评估标准
GBJ107-87
国家
5
地下防水工程质量验收规范
GB50208-2023
国家
6
钢筋焊接及验收规程
JGJ18-2023
行业
7
混凝土泵送施工技术规程
JGJ/T10-2023
行业
8
建筑工程冬期施工规程
JGJ104-2023
行业
9
建设工程安全生产管理条例
国务院令
第393号
10
建筑工程冬期施工手册
/
/
2 工程概况
本工程位于宜宾市临港开发区,总建筑面积353726.58㎡,地下建筑面积160466.7㎡;地上6幢33层(高99.3M)的高层住宅、1幢25层(高99.75M)的五星级酒店、1幢24层(高99.95M)的办公楼、3幢4层(高19.65M)的商业建筑及一个下沉式地下室广场,地下室为三层地下室。
3 施工安排
3.1 时间安排
冬期施工的依据为:根据本地数年气温资料记录,当室外日平均气温连续5天稳定低于5℃即进入冬期施工,当室外日平均气温连续5天稳定高于5℃时解除冬期施工。
施工项目安排
1)本项目在冬施期间将进行地下室的施工、主体结构施工、装饰工程的施工。
2)地下室外墙防水。
3)与主体结构工程同步的安装预埋。
3.2 冬施组织安排
3.2.1 组织机构
组 长:贾以仓
副组长:赵文华
组 员:臧兆强、胡云法、王晓波、杨征、王静、顾初渭、何巨丰。
气象员:阮思蓉、何茂兰。
3.2.2 职责分工
贾以仓:负责冬施现场的全面管理工作。
赵文华:负责冬施现场的施工生产工作。
臧兆强:负责冬施技术指导及方案的审批工作。
杨征:负责冬施技术交底工作。
胡云法:负责冬施质量监督管理及质量验收工作。
王晓波:全面负责冬施安全监督管理工作(涉及防火、防毒、安全防护、保卫、环境)。
顾初渭:全面负责冬施物资采购、备用管理。
阮思蓉:负责冬施技术资料收集、整理、归档及气象预报工作。
何茂兰:负责冬施实验、测温、各项记录。
何巨丰:负责冬施生活、后勤等工作。
4 施工准备
4.1 技术准备
1.提前编制冬期施工方案,进行冬期施工技术交底工作,掌握冬期施工控制要点。对本工程冬期施工的项目进行拟定,工程技术人员和项目管理人员必须认真复核图纸,核对施工项目是否能适应冬期施工的规定,不宜在冬期施工的工序(如抹灰、塞缝工程)坚决不施工。加强对工人的冬施技术交底,明确冬施中要进行的分项工程及所采用的人、机、料、施工工艺、安全质量施工注意点等,做到冬施重点突出、心中有数。
2.冬施前应对测温员、实验员、安全员、技术管理员,进行冬期施工技术培训后上岗,保证测温记录的真实性、完整、准确性。
3.各单位工程的测温应在冬施方案中考虑,测温孔的布置应根据规定按顺序进行编号,施工现场应设立测温箱, 安排专人测量施工期间的室外气温、混凝土的入模、养护温度,并认真做好记录。
4.及时与本地气象台站保持联系,及时接听天气预报,撑握天气变化情况,防止寒流的忽然袭击。
5. 开始测温前要准备好工具、用品、文具等,为正常测温发明有利条件。重要工具、用品有:①测温百叶箱:规格不小于是300mm×300mm×400mm,宜安装于建筑物10米以外,距地面高度1.5米通风条件较好的地方。外表刷白色油漆。②测温计:测量大气温度和环境温度,采用最高最低温度计,测量混凝土温度采用玻璃液体测温计。各种测温计在使用前均应进行校验。③三角旗:为表达测温孔的位置和编号,需准备与测温孔数量相应的金属制的小三角旗,并在旗上编号。④闹钟、手电筒、文献夹、测温登记表、记录大气温度的小黑板等,均应事先准备齐全。
4.2 生产准备
1.混凝土输送泵搭设围护结构,围护棚墙、顶棚内挂50厚保温板,板缝封严,
出入口挂棉被保温,门口挂防火棉被保温。砌筑砂浆搅拌棚,搭设电热水箱及备用燃煤加温水箱。
2. 混凝土泵管用防火草帘缠裹保温,外缠厚塑料布防水浸湿,泵管保温严密,不得露出泵管,以保证混凝土入模温度。
3.施工迎风工作面用彩条编织布挡风,彩条布绑扎于外围脚手架上,随架子提高,围护架间封严。
4.施工工作面下一楼层外墙洞口用塑料布封闭,楼层洞口用胶合板封闭。
5.对现场火源、电源、水源要加强管理,全面检查一次防止意外事故的发生。
4.3 材料准备
提前做好冬期施工保温材料的准备工作,提前与商品混凝土厂家取得联系,做好冬期施工混凝土的试配工作,并提出施工配合比。保温材料计划见下表。
保温材料计划表
序号
材料名称
型号规格
单位
数量
进场时间
1
阻燃草帘
宽1m×长2m
条
4500
根据现场需要
2
塑料布
/
M2
4000
根据现场需要
3
彩条布
/
M2
2023
根据现场需要
4
铁丝
16#-18#
kg
1000
根据现场需要
5
温度计
-20~100℃
支
30
根据现场需要
10
火炉、电热器
/
个
40
根据现场需要
11
聚苯板(50厚)
/
M2
2500
根据现场需要
4.4 临设准备
1.对生活用水和施工用水、消火栓等外露水管,冬施前用岩棉或阻燃草帘保温,非外露水管均埋入自然地面以下0.8m。水池搭设围护棚,顶棚用石棉瓦,内挂50厚保温板。
2.生活区、办公区采用电暖器,配置专用电缆线路,漏电开关,触电保护器。
3.工人宿舍增长被褥,现场夜间值班人员增长御寒大衣。
4.所有临时管沟(涉及临时排水沟、化粪池等)均用盖板盖严,并经常检查保证排水通畅。
5 施工方法及技术措施
5.1 防水工程
地下室防水施工期间应注意以下问题:
1.地下卷材防水在冬期施工阶段,采用通常的满铺法进行施工,规定防水卷材要紧贴防水层底部基层,不得留有任何空隙。
2.对施工前的防水卷材做好保温防护工作,保证卷材自身的温度不低于+50C的情况铺设作业。
3.防水卷材施工前应清扫掉在基层的冰雪、杂物。遇有雨、雪天及大风天气应停止卷材防水施工。
4. 热熔法施工环境温度不应低于-5℃,涂刷基层解决剂宜使用快挥发的溶剂配制,涂刷后应干燥10小时以上,干燥后应及时铺贴。热熔法防水层应采用满粘法施工,铺贴时应采用喷灯均匀加热基层和卷材,喷灯距卷材的距离宜为0.5m,不得过度加热或烧穿,应待卷材表面熔化后缓缓地滚铺铺贴。
5.防水材料的堆放场地要满足防火规定,配全防火器材。
5.2 钢筋工程
1.钢筋在运送和加工过程中,必须注意防止刻痕和碰伤,这些缺陷的存在易产生应力集中而导致钢筋脆断。
2.冬期钢筋的焊接,其最低温度不得低于-20℃,且应有防雪挡风措施,焊后的接头,严禁碰到冰雪。电渣压力焊应尽也许在中午进行,并适当延长拆除焊剂盒的时间,防止温差过大。
3.加工成型的钢筋,应下垫木方,防止钢筋接触冰冻地面,粘上泥土。
4.注意雪后要及时清理施工完毕钢筋表面上的积雪,防止钢筋锈蚀,要搭设人行马道,不得在钢筋骨架上行走,防止钢筋变形、人员摔伤。遇下雪天气绑扎钢筋时,应将绑扎好的钢筋加盖塑料布,减少积雪清理难度。
5.3 模板工程
1.工地上的大模板,应垫上木方,排放整齐,碰到下雪时,应用苫布、编织布遮盖。
2.支模时,应将模板上的冰雪和泥土清除干净,方可使用。
3.支墙体模板前必须将模板内杂物、冰雪清扫干净,模板不准浇水。
4.冬期施工,对于模板的拆除,结构混凝土应留置同条件养护试块,模板拆除应申请,经技术负责人批准后方可进行模板拆除。梁板底模拆除必须达成规范规定的结构强度(参见模板方案)。对于墙体模板拆除,结合冬施规范的规定,及本工程冬施混凝土的外加剂性能,明确如下:
u、在正温环境下,墙体混凝土养护达成一定强度,不因墙体拆模而损坏混凝土的棱角、面层时,可以拆模,拆模后的混凝土与外界环境温度差不大于20℃。假如温差大于20℃,则将已拆模的混凝土表面挂盖保温被。
v、在负温环境情况下,拆模原则是保证混凝土在达成临界强度4Mpa(通过试块进行实验,得出结论)前不得受冻。墙体模板作为混凝土养护保温层(同时在墙体模板顶部覆盖保温被)必须控制拆除时间,只有当拆模试块抗压强度达成4MPa,方可拆离墙体大模板。否则,墙体大模应在混凝土终凝后,在模板可以剥离而混凝土不粘模情况下,先松开墙体支模的大螺杆,让模板剥离混凝土墙面,然后重新支合模板覆盖住混凝土墙体表面,延缓混凝土降温散热。
6.顶板模及其支撑的配置量满足冬期施工需要,顶板支模材料、周转用品不落地,拆下后及时倒运到作业层。
7.模板堆放区配置清理积雪用品,模板组装零配件防止雨雪泥污染,集中堆放管理,设立遮挡工具棚。
5.4 混凝土工程
5.4.1 冬施混凝土施工总则
本工程冬期混凝土施工,在混凝土中掺加适量抗冻早强剂,并将混凝土搅拌原材料预先加热,混凝土经运送、浇筑完毕时,温度保持在8~10℃以上,通过蓄热保温或短期人工加热(通过无烟煤炉或电暖器加热)使混凝土经1~1.5d后才冷却至0℃。
本工程冬期混凝土由商品混凝土供应站提供预搅拌混凝土,混凝土搅拌材料预热,混凝土运送到现场出罐温度15℃,混凝土内掺复合抗冻早强剂,现场混凝土采用保温养护措施:现场混凝土输送泵进入保温防护棚,混凝土输送泵管用保温材料包裹,墙体混凝土借助模板保温,墙体顶部遮盖保温养护。
5.4.2 抗冻临界强度
规范规定:不掺加抗冻外加剂的混凝土,当混凝土搅拌采用硅酸盐水泥或普通硅酸盐水泥配制的混凝土,抗冻临界强度应为设计的混凝土强度标准值的30%。采用矿渣硅酸盐水泥配制的混凝土,应为设计的混凝土强度标准值的40%。掺防冻剂的混凝土,当室外温度不低于-15℃时,混凝土的受冻临界强度不得小于4.0N/mm2,当室外温度低于-15℃时,混凝土的受冻临界强度不得小于5.0N/mm2。
因此,根据本工程冬期混凝土施工总则,抗冻临界强度定为4MPa。
按照我公司以往同类工程施工经验,混凝土入模温度在10℃,浇筑后采用草帘保温养护,一般在40h达成临界强度。
5.4.3 原材料、配合比规定
混凝土冬期施工应优先选用硅酸盐水泥和普通硅酸盐水泥,水泥的强度等级不应低于32.5MPa,最小水泥用量不应小于300Kg/m3,水灰比不大于0.55。砂石材料必须清洁不含冻块。水:水加热应提前4h进行,保证水温达成80℃。
搅拌站的冬施混凝土规定掺加具有早强效果的抗冻剂,保证混凝土在-10℃环境下,混凝土的水分子可以保持液相状态,本工程采用防冻剂,同时,规定混凝土在浇筑后40h内达成抗冻临界强度(4MPa),混凝土养护到48h,强度可以达成7.5MPa,满足外墙挂架提高的墙体强度规定,抗冻早强剂的使用效果和掺量经实验室试配后拟定能否达成规定,防冻剂必须是环保产品,不得具有尿素、氯盐成分。
混凝土的塌落度有严格规定,冬施期间,墙体塌落度:160~180mm,板混凝土坍落度140~160mm。搅拌站按照规定塌落度进行搅拌,混凝土运送到工地后要对塌落度进行检查,发现塌落度不符合规定,混凝土拌合物离析、泌水,立即予以退回。
5.4.4 混凝土搅拌、运送
为保证搅拌温度,必须严格控制水的加热温度。搅拌过程中,随时注意检查砂、石、水的温度情况,当不满足计算规定的温度时,应及时采用措施或暂停搅拌混凝土。
混凝土的搅拌时间不得少于135S,商品混凝土到现场的出罐温度控制在+15℃以上。
混凝土运送车,外缠苫布保温,外缠塑料布防水浸湿。
混凝土运至浇灌部位后,应采用快铺料,快振捣,及时覆盖的快速施工方法。 混凝土经输送泵的传输后的入模温度不应低于10℃,对每一台班车辆的进场混凝土进行入泵前的温度测量,入模温度的测量,混凝土浇筑后覆盖前的温度测量,并做记录。
混凝土的搅拌及运送由混凝土厂家严格按规定进行控制。
5.4.5 混凝土泵送
泵送的输料管要用草帘或其它保温材料包裹,以减小混凝土在输送过程中的温度损失,进行混凝土泵送前要用热水进行润洗输送管。输送到作业层的热水必须用专用料斗存放,不得打入模板内。
混凝土出罐前一定要测量其温度,保证其温度不小于+150C,输送到作业层的混凝土,测量入模温度,规定不低于+100C。每一台班施工完毕后,清洗输送管线及机具,彻底排出其内部的积水,以免其内部受冻,影响施工的正常进行。
罐车必须设立在稳固地点,不得有冰雪冻融物。喂料前,要监督罐车进行倒转,防止混凝土的离析等物理不良变化。施工现场道路注意防滑等措施,水平管的出料方向要低于进料方向,输送管不得直接稳固在钢筋、模板及预埋件上。
5.4.6 混凝土浇筑
1.冬施混凝土浇筑安排每次浇筑的开始时间宜在当天上午9:00开始,尽也许避开夜间作业。
2.冬施混凝土浇筑应尽也许避开雨雪严寒天气施工。
3.浇筑混凝土前及时将模板、钢筋上的冰、雪清理干净。
4.浇筑前充足做好准备工作,提高混凝土的浇筑速度,保证混凝土的入模温度。
5.每次浇筑混凝土前,要检查混凝土泵管上包裹阻燃草帘被、岩棉管是否有破损之处,并及时修补,避免施工冷桥对混凝土温度的影响。
6.现场混凝土随浇随盖,特别是平板混凝土在二次抹光前,不能露天放置,必须临时性的先铺一层塑料薄膜,待二次抹光后,及时加盖一层保温被。
7.剪力墙混凝土分层浇筑时,已浇筑层的混凝土温度在未被上一层混凝土覆盖前不应低于2℃。较低环境气温作业时,应有专门人员及时抽检各层混凝土浇筑后的温度,严格控制施工间歇时间。
8.混凝土浇筑时要测量其入模温度,保证其温度不得小于+100C,浇筑成型后的混凝土温度不得小于+50C。混凝土浇筑完毕后要及时覆盖保温养护。
其它规定同《混凝土施工方案》。
5.4.7 混凝土养护、测温
本工程混凝土的养护采用综合蓄热养护法进行养护,即在混凝土中掺加适量抗冻早强剂,并将混凝土搅拌原材料预先加热,混凝土经运送、浇筑完毕时,温度保持在8~10℃以上,通过蓄热保温或短期人工加热,使混凝土经1~1.5d后才冷却至0℃。(此时混凝土强度达成抗冻临界强度,然后,混凝土逐渐与环境气温相平衡,由于防冻剂的作用,混凝土在负温中强度继续增长。)
蓄热保温及短期人工加热的具体措施如:板及墙体顶部采用一层塑料薄膜加盖一层阻燃草帘被。草帘被的铺盖要严密,一层压一层,规定相邻草帘应搭结200mm,铺盖过程中应注意混凝土的成品保护,不得随意踩坏混凝土。遇大风天气时,阻燃草帘上应用木方或钢管等重物覆盖,以免大风将保温层吹开。混凝土的边、棱角,应加设2层阻燃草帘覆盖。安排专人负责混凝土的覆盖检查工作,同时对工人加强冬施期间的技术交底,注意混凝土覆盖物的保护。
短期人工加热:顶板混凝土的底部保温为了防止冷空气流动或寒流的袭击,将
本层及下层其周边用彩条布密封(局部不方便遮挡处采用阻燃草帘辅助),严冬时,室内采用加温措施,楼梯间通道和门窗处挂设临时性草帘遮挡,使顶板底部处在正温。
在浇筑混凝土时,要根据测量温度的规定,预埋好温度计的测量位置。预埋孔的尺寸见测温孔的设立,测温次数见温度测量表。
保温完毕,相关人员要认真检查,遇有大风天气,要留专职人员检查覆盖情况,并负责修复被风破坏的保温层。
2.测温孔的设立
a.测温孔应在易于散热的部位设立。
b.现浇混凝土梁、板、的测温孔,应垂直插入留置。梁侧孔每3~6m长设立一个,且每跨至少设1个,孔深1/3~1/2梁高。楼板每15~30m2设立1 个,每间至少设立1 个,孔深1/2板厚。
c.剪力墙结构板墙,横墙、纵墙轴线之间采用梅花形布置。每块板墙单面设测孔1~2个,对角线布置,上、下测孔距模板上下边沿30~50CM,孔深10CM,墙上每位置取上、中、下各一点,呈梅花型布置。
d.楼梯间休息平台及踏步板,每层设测孔不少于2个。
e.现浇阳台结构等每层设测孔2个。
3.测温方法和规定
1)玻璃液体温度计的测温方法。
①测温人员工作前,应检查所需用品是否齐全,夜间测温还应带好手电筒。
②混凝土浇筑时,顶板用φ25园钢筋棍按入测孔位置并能形成深度适宜的测孔,混凝土终凝前拔出钢筋棍。剪力墙用φ25钢管预埋,内侧封严,外侧用保温材料堵塞。插上标志测孔位置的三角旗。
③测温时,按测温孔编号顺序进行。温度计插入测温孔后,堵塞住孔口,留置在孔内3~5分钟。然后从孔中迅速取出,使温度计与视线成水平,仔细读数,并记入测温登记表,同时将测温孔用保温材料按原样堵塞住覆盖好,把三角旗插入测孔内。
2)最高最低温度计的测温方法。
测量大气温度时,应使用最高最低温度计。使用的方法是:U形水银柱左右两侧所指的读数不同,左侧蓝色浮动砝码的下端所指的刻度为上次测温以后至本次测温期间温度变化的最低点,即最低温度。右侧蓝色浮动砝码的下端所指的刻度为上次测温以后至本次测温期间温度变化的最高点,即最高温度。
3)现场测温项目及测温次数见下表:
测温项目
测温次数
测温时间
1.室外气温及环境温度
每昼夜4次,并测量最高最低气温。
1:30、7:30、13:30、19:30
2.工作环境温度(泵棚内)
每工作班2次
上.下午各一次
3.混凝土入模温度
每工作班4次
按车次测
4.混凝土养护温度
混凝土浇筑后,在抗冻临界强度之前
每2h测一次
达成抗冻临界强度之后
每隔6h测一次。
根据规定进入冬季施工后开始进行大气温度测量,进入冬施开始配合混凝土施工进行规定项目的测温,各项测温内容按规定表格填写。
5.4.8 混凝土养护注意事项
1.测量放线掀开保温材料时,放完线要立即覆盖。
2.对墙顶部保温薄弱部位必须重点检查覆盖保温措施到位。
3.墙拆模后混凝土表面必须一方面及时刷抗冻养护液。
4.混凝土初期养护温度,不得低于5℃,不能满足该温度条件时,必须立即增长覆盖保温。
5.若混凝土拆模后,混凝土温度与外界温差大于20℃时,在混凝土表面,必须继续覆盖两层阻燃草帘被。
5.4.9 混凝土试块留置
冬施中混凝土试块为混凝土拆模和拟定热养护期提供依据。在制作试块时应按照《混凝土结构工程施工质量验收规范》(GB50204-2023)中有关规定并结合施工中实际情况,试块组数应留设4组。
序号 号
组 别
应 用
1
第一组
28天标养,检测混凝土强度
2
第二组
混凝土同条件养护,测定拆模时混凝土强度
(平板梁混凝土强度达成规定规定,墙体混凝土强度达成抗冻临界强度)
3
第三组
同条件养护28d,转入标准养护28天测设强度。
4
第四组
同条件等效养护龄期达成600℃d,以检查实体强度(见证)
(注:拆模及撤除保温层规定:模板及保温层应在混凝土达成受冻临界强度并冷却到5℃后方可拆除。当混凝土与外界温差大于20℃时,拆模后的混凝土表面,用防火草帘被临时覆盖,使其缓慢冷却。)
5.4.10 测温管理
1.每层或每施工段停止测温时,由技术员审阅测温记录,签字后交技术负责人审阅签字。
2.对特殊情况需要延长保温时间采用加温措施者,要及时报告项目技术负责人。
3.测温工作由技术负责人统一管理,实验员负责本工程的测温、保温、掺外加剂等工作,将天天测温记录及时上报技术负责人。
4.质量检查人员,天天要检查冬施的测温、保温的情况,对发现的问题要及时告知工长和项目经理。
5.测温员在每层或每段停止测温时要向技术负责人交一次测温记录,平时发现问题及时向工长和技术员报告,以便采用措施。
6.测温人员每24小时都有人上岗,实行严格的交接班制度。测温人员要分楼号分项填写测温记录并妥善保管。
7.测温人员要经常与加温人员、保温人员取得联系,如发现加温、保温措施不妥使温度急剧变化或降温过速等情况,应立即报告栋号工长进行解决。
5.5 二次结构施工
本工程进入冬施后,进行砌体砌筑,砌筑工程采用掺加“外加剂”法,具体施工技术措施如下:
1.将各地下室、各层对外门窗洞口封闭,室内布置充足的照明电灯,使用的砌体提前一天运至地下室或室内储藏、解冻、待用,不得使用遭水浸和受冻后的砌体。
2.砌筑砂浆强度等级M5,内掺砂浆防冻剂,外加剂投放量(用小塑料袋分袋包装,按袋投放)。投料顺序为:砂→热水→水泥和外加剂。严禁水泥与温度≥80℃ 的沸水直接接触。
3.水泥存放在室内温暖环境,保持存放空间温度3℃以上。
4.砂含泥量≤3.0%,砂进入堆场后封闭覆盖保温防潮,减少冻结,不得具有直径大于1cm的冻结块。
5.砂浆搅拌水采用电热炉加温至60℃。
6.砂浆在地下室或室内随拌随用,砌筑时砂浆温度不低于5℃。
7.每日砌筑后,应及时在砌筑表面进行保护性覆盖,砌筑表面不得留有砂浆,在继续砌筑前,应扫净砌筑表面(天天砌筑高度不得超过1.5m,顶部斜砌等沉降均匀后再塞缝)
8.在环境气温低于0℃时,不进行砌筑作业。
9.砂浆试块的留置,除应按常温规定规定外,尚应增设不少于2组与砌体同条件养护的试块,分别用于检查抗冻临界强度和转入常温28d的砂浆强度。
5.6 装饰工程施工
5.6.1一般规定:
1、 安排室内抹灰以前,先做好屋面防水层及室内封闭保温。
2、 室内抹灰的养护温度,不低于5℃,水泥砂浆层应潮湿的条件下养护,并要通风换气。
3、 冬期抹灰所采用的砂浆应采用保温防冻措施,室外抹灰砂浆内掺入能减少冰点的防冻剂,其掺量由实验拟定。
4、 室外装饰工程施工前,要加设挡风措施。
5、 外墙饰面工程,不宜在严寒季节施工。
5.6.2冬期施工有关措施及注意事项:
1、 在进行室内抹灰前,将门窗洞口封好,将脚手架眼、孔洞等均应堵好,施工洞口,楼梯间要作保温封闭解决。
2、 砂浆在搅拌棚中集中拌制,在运送中作保温解决,要随用随拌,防止砂浆冻结。
3、 室内抹灰结束后在7天内,室内温度应保持在5℃以上,并可采用加温措施加速干燥。
4、 含氯盐的防冻剂不得用于高压电源部位和有油漆墙面的水泥砂浆中。
5、 防冻剂的掺量、品种应符合规范规定,并由专人配制和使用。
6、 抹灰层表面当有冻、雪、霜时,可采用与抹灰砂浆同浓度的防冻剂溶液冲刷,并应清除表面的尘土。
7、 施工规定分层抹灰时,底层抹灰不得受冻应做好防冻保温措施。
8、 冬期施工外墙饰面材料应根据本地气温条件及吸水率规定选用。
外墙门窗、大扇玻璃不宜在冬期安装。
5.7 安装工程
1.下雨、下雪进入施工现场时,脚手板上的积雪先清理干净,严禁穿硬胶底鞋,
2.塑料PVC 管冬期施工进行粘接时,凝固时间为2~3min,粘接场合应通风良好远离明火,插入粘接时将插口稍作转动,以利粘接剂分布均匀,约30~60秒即可粘接牢固,粘牢后立即将溢出的粘接剂擦拭干净. 粘接剂易挥发,使用后应随时封盖。
3.施工现场临时水进入冬期后,明露管应做好保温,防止管道及设备冻坏。所有室内明露管道均做保温,保温采用岩棉管壳,厚度为止50mm,外缠玻璃丝布两道。
5.8 土方回填
5.8.1回填土规定
采用素土回填(甲方指定),回填土不得具有有机杂质,回填土的颗粒直径不应大于50mm,含水量应符合压实规定。
5.8.2回填规定
a) 冬期回填土每层虚铺土厚度为250~300mm;
b) 回填土前,应清除基底上的冰雪和保温材料;填土的上层应用未冻土填铺,其厚度应符合设计规定;
c) 基坑回填不得使用品有冻土块的土进行回填;
d) 回填土施工应连续进行,尽快完毕,防止基土或已填土层受冻,应及时采用防冻措施。
e) 回填好的土层要加盖保温材料保温,且应注意取土场土的保温。
5.8.3施工技术措施及质量规定
1)在冬期土回填时,应采用以下措施:
A、在土方回填以前,将回填土堆上面约30cm左右的表层冻土挖掉。
B、在使用的回填土中,将不冻土堆在一起加以覆盖,防止冻结。
C、用人工夯实时,每层铺土厚度不超过30 cm,夯实厚度为20~25 cm。
D、回填土的压实系数为0.94。
E、土方回填时,不得在受冻结实,或上层有有机质(如加盖草帘的草叶等)层面上回填第二层。
6、冬期回填土方应连续进行并逐层夯实。
2)对其冬期施工质量的保证作如下规定:
A、保证项目
(1)基底解决,必须符合设计规定和施工规范规定。
(2)回填土的土料,必须符合设计规定和施工规范规定。
(3)回填土必须按规定分层夯实,压实后的干容重,应有90%以上符合设计规定。
(4)回填土使用非冻土,在使用回填的土中不能含冻土块。
B、允许偏差
项目
允许偏差(mm)
标高
人工
±30
表面平整
人工
20
C、填土方前清除基底上的冰雪和保温材料,填方时,不得采用品有冻土块的土填筑。
D、当气温低于-100C度时,不宜回填作业。
E、回填宜连续进行并应夯实,以免地基土或已填的土受冻,大面积填方时,要组织平行流水作业或采用其他有效的保温防冻措施。对当天回填土面层采用覆盖阻燃草纤被保温。防止过夜面层冻胀,第二日回填前如有冻结部位必须挖除后重新回填。
F、部分死角,用机械夯实不到位的采用人工夯实,人工夯实时,每层铺土厚度不超过20cm,夯实厚度为10~15cm。
6 施工管理措施
6.1 质量保证措施
6.1.1冬期施工混凝土质量检查除应符合国家现行标准《混凝土结构工程施工质量验收规范》(GB50204-2023)及其他国家有关标准规定外,尚应符合下列规定:
1.检查外加剂质量与掺量,进行抽样检查合格后方可使用。
2.检查混凝土原材料和混凝土出罐及浇筑时温度。
3.检查混凝土从入模到拆除保温层或模板期间的温度。
4.冬期施工测温的项目与次数应符合规定规定。
5.混凝土养护期间温度测量符合规定。
6.1.2防水层严禁有破损和渗漏现象,在浇筑细石混凝土保护层时,如发现防水层有损坏,必须及时修复,方可浇筑。
6.1.3回填土压实系数>0.90,合格率大于90%以上,夯实后的干密度≥1.45g/cm3。
6.2 安全措施
冬施生产,安全第一。根据冬施生产的特点,现场会有较多的保温防寒材料,施工用电总负荷增长,并且冬季多大风,多雨雪冰,安全生产重点狠抓以下“五防”工作:
l 防火灾
l 防触电
l 防中毒
l 防人员滑跌
l 防大风
具体工作内容如下:
1.应遵守本工程创文明、安全工地措施,并针对冬期施工特点而制定冬期施工安全措施。
2.应编写各分部分项工程施工安全措施,在施工前向工人进行冬期文明、安全施工交底。
3.冬期施工应要严格遵守建筑工作施工安全操作规程和安全管理各项制度。
4.冬期施工中,遇有五级以上大风天气时,应停止吊车运营。冬施人员上下行走通道,必须在冬施来临前做一次检查,防滑木板条必须用8#铅丝绑扎牢固,雨雪天气要及时清扫积雪和冰冻。
5.遇有下雪天气时,应及时清除工地上、跳板上的冰雪,防止滑倒伤人。
6.遇有大风雪天气时,不要在楼边堆放木板等物,防止高空落物伤人。
7.冬期施工使用电动机具,应由专人负责使用和保管,不准带线手套触模电钻等机具转动部分,以防伤手。冬期施工用电要统一管理,统一分派,严禁私拉乱接。对用电接地和所有现场使用的漏电保护装置要进行一次检查,并作好检查记录。
8.冬期施工用水严禁常流水,工地施工操作面不得积水,防止结冰后滑倒伤人。
9.火炉子加热时,应制定严格的防火、防煤气中毒措施,如留排气窗、通风口、设排烟道等,防止发生火灾、煤气中毒事故。做好冬期施工人身保暖工作,防止工人冻伤手脚。施工人员增长御寒棉衣,防止冻伤。未经安全保卫部门认可,不得在生产区和生活区使用电炉。
6.3 文明、环保措施
1.冬期施工用的保温被等材料,使用完后,应及时回收、码放整齐。
2.施工现场的各种材料,脚手板、钢管、模板等料具应分类码放整齐。
3.雪后应清扫积雪,有泥浆处应清除,防止运送车辆将泥浆带上市政道路。
4.运送袋装水泥、白灰和砂、石等其它易飞扬的细颗粒散体材料及建筑渣土均需用彩条布或苫布遮盖严实,以防止扬尘。
5.建筑物内的施工垃圾采用容器吊运,严禁用电梯井或在楼层上向地面抛洒施工垃圾,施工垃圾应及时清运。
6.施工现场火灶一律烧液化气,茶炉采用电热水器,严禁使用煤做饭、取暖等。
6.4 消防措施
1.冬期天气干燥,保温材料多,是火灾易发生时期,为保证冬期施工的正常进行,应做好消防工作。
2.冬期施工的消防,应认真贯彻“防止为主,消防为辅”的消防工作方针,组织有关人员学习消防有关知识,纯熟掌握各种消防器材的使用。
3.严格执行工地动火申请制度,电气焊在施工区内施工时,必须先申请,经批准后施工,并设专人看管,防止发生火灾事故。
4.易燃材料要远离火源堆放,码放整齐,并用塑料布、编织布遮盖,必要时,应设立隔火墙。
5.防火器材,严禁挪用。违反者,应给予处罚,以保证消防器材到位,作到有备无患。
6.工地应设专人负责防火工作,做好火灾预控工作,并能组织义务消防队,作到有备无患。
7.火警电话“119”,在消防器材和消火栓及工地电话室,挂牌明示。
七、冬季施工应急预案及相应措施
(一)应急解决机构和责任分工
1、项目部成立由项目经理任组长,分管安全生产副经理任副组长,有关班组负责人为成员的项目部“三防”工作应急解决领导小组。
组长:贾以仓
副组长:赵文华
成员:胡云法 王晓波 王静 杨征及各分包单位项目负责人、管理人员
2、分工职责:
(1)施工场合、加工场合防冻及应急保障:★胡云法 王晓波及各分包单位项目负责人、管理人员
天天早上上班前及下班前对施工场地例行检查,看有隐患等。发现隐患及时解决,自己无法解决,立即向领导报告。
(2)项目部安全及防滑应急保障:★王晓波、王静及及各分包单位项目负责人、管理人员
天天早上上班及下班前对责任区例行检查,项目部队部是否有积水、冰冻,人人要知道防滑地毯、警示牌存放地,发现隐患及时解决,自己无法解决,立即向领导报告。还需重点关注的要害部位:加工平台。
(3)用电安全及防火应急保障:★王晓波、杨征
冬季用电高峰,天天检查总配箱电压、电流是否正常使用;检查分派箱有无跳闸现象;检查各设备闸箱有无跳闸现象;检查电表箱外壳和电线、缆外皮有无破损;检查各工地、加工场合用电是否正常,如遇故障及时排除。提出用电建议,保证用电高峰不跳闸。天天填写项目部用电安检巡查记录。还需重点关注各室空调使用情况、灯罩是否松动;办公室有无违章用电器,下班前查办公室等空调有无关闭。保安定期检查消防设施是否完好。
(二)、事故责任追究
1、坚持谁主管谁负责,谁主办谁负责的原则,在查明因素、认定性质、分清责任的基础上,根据国家、省、市有关法律、法规,按照“四不放过”的原则,对安全事故有关负责人严厉追究行政和法律责任。
2、严格实行安全事故报告制度,发生安全事故,有关领导和当事人,在及时处置险情的同时,第一时间上报项目部有关领导,因不及时上报,延误抢救时机、导致重
展开阅读全文