1、EPC of ABC 330kV D/C TRANSMISSION LINE PROJECTConstruction Management PlanABC Co., LtdApril 5,2010Prepared: Checked: Approved: 50Chapter 1 Project Overview and Features1 Project overview and features1.1 Project overviewLot 1 330kV A - B DC Line ( that is 286m in length ) ( hereinafter referred to as

2、 “AB Project”) is a project invested by NDPHC.1.1.1 Length, voltage grade and erection type of the lineABProject is located in the central area of N NATIONAL starting from A Substation in the south and ending in B substation in the north with the length of 279.449km. The project is located above sea

3、 level between 100m and 1300m with the voltage grade of 330kV. The double-circuit line will be erected on the same tower and self-supporting angle steel towers will be employed for the line. 1.1.2 Conductor, ground wire, OPGW and insulator The conductor will be twin bundled and horizontally arranged

4、 with the model of BISON. The ground wires will be GJ-60 galvanized stranded wire and OPGW respectively. Glass insulators will be employed for the line. Twenty FC120/146 glass insulators will be employed in the tangent tower and 2X22 FC160/146 glass insulators in the strain tower. 1.1.3 Fountation t

5、ype and earthingOblique Angle Inserted Foundation and horizontally radial earthing.1.2 Analysis of construction condition1.2.1 Construction condition at the site Medium sand, crushed stone resources are available along the line. Appropriate sand, stones may be provided. Influenced by climatic condit

6、ions, it is difficult to construct in rainy season at location of this project. Rainy season should be evaded as far as possible. However, since part of construction period for this project is arranged in rainy season. Preparations should be made for the construction proposal in rainy season. Constr

7、uction period of the procedures should be arranged reasonably. Adverse factors should be considered sufficiently to ensure construction period progress target. To make sufficient preparation for construction in rainy season and to provide effective drainage equipment and excavation retain equipment.

8、 Since infrastructure is backward in N NATIONAL, local health care conditions are poor, there are many mosquitoes, malaria morbidity is high, necessary medical equipment should be provided and necessary medical training should be provided for employees during construction. Common medications, antima

9、larials and injection should also be provided. Since tap water treatment condition is unavailable locally, water permeability in the soil is high. Almost all ground water cannot be drunk directly. Domestic water should adopt purified water as far as possible, or water treated. material resources con

10、ditions Construction material resources in A City, C and B City are basically abundant, but relative quality is poor. Chapter 2 Organizational Framework of Project Construction Management2.1 Organizational structure of project management and responsibility division 2.1.1 Organizational structure of

11、project management In order to complete this project successfully, our company organized N NATIONALn Project Management Department. Main management personnel of the Project Management Department are dispatched from technical management personnel of the company. “330kV D/C TRANSMISSION LINE Project M

12、anagement Department” is organized. On behalf of M COMPANY/CHEMO, the Project Department is responsible for the Client and Consultant and fulfills the contract comprehensively to realize the project objectives. Transmission Line construction Management Department Project manager : Deputy Project Man

13、ager: Chief Project Engineers: Technical Control PrincipalC Material Principal Plan and Finance PrincipalLi Quality Principal SafetyPrincipalC Fig. 2-1 Organization chart of project management and constructionConstruction Team 1ManagerY Construction Team 2Manager Construction Team 3Manager 2.1.2 Res

14、ponsibility and work division Table 2 - 1 Department & postResponsibility and authorityCompany Head Office1. Dispatching project manager and chief project engineer with strong management capability, business skills and rich experience to organize A & B Substation Project Department according to the

15、scale and features of this project; 2. Organizing to prepare Project Construction Organization Measures, Responsibility Documents of Construction Project Management, define obligations, responsibilities and rights of the project manager and functional departments of the company in this project; 3. A

16、llocating construction resources such as labor force, material resources, equipment etc of Project Management Department, guaranteeing to meet project implementation requirements; guaranteeing implementation of the funds required for the project. The company and relevant departments should ensure to

17、 solve requirements of the Project Department timely. Project Manager1. Agent of the companys legal representative in this project, manages the overall construction process of this project on behalf of the company, responsible for comprehensive fulfillment of the contract. Implementing the companys

18、quality, safety and environment management guidelines, Quality Manual, Occupational Safety and Health and Environment Management Manual as well as documents of relevant procedures during project construction, completing project tasks according to provisions of the contract, accepting inspection and

19、supervision by the owner unit, consulting engineer, dealing with and coordinate relationship between the parties concerned, creating good environment and conditions for project construction, achieving project management objectives comprehensively; 2. Fulfilling tasks specified in the Responsibility

20、Documents of Construction Project Management; 3. Organizing to prepare and implement Project Construction Organization Measures; 4. Implementing according to the companys quality, safety and environmental protection management guidelines, quality, safety, environmental protection objectives of this

21、project as well as requirements of the companys quality, safety, environmental protection management system documents. 5. Allocating construction resources rationally, taking full responsibility of safety, quality, construction period objectives for this project; 6. Responsible for construction qual

22、ity monitoring, safety supervision and civilization, organization management of environmental protection construction; 7. Grasping plan, financial and funds situation, instructing Planning and Finance Department to arrange funds reasonably according to the construction schedule and implementation st

23、atus of funds plan; 8. Implementing commands of the owner unit, consulting engineer related with project quality, safety and construction progress etc effectively during construction; 9. Implementing management works of safe, civilized construction and environmental protection. Dealing with follow-u

24、p work after the project is completed. Deputy Project Manager Under the leadership of the project manager, assisting the project manager to complete all works of project manager within his responsibility scope. Responsibility and authorityChief project Engineer1. Chief project engineer is the chief

25、technical superintendent of this project, responsible for technical management work according to relevant technical standards, regulations, regulations, design drawings as well as related technical management system of this company, responsible for management and application of MS Project software i

26、n this project; 2. Organizing to prepare quality plan, construction organization design, project construction proposal, technology, overall measures planning of safety, civilization and environmental protection construction etc for this project, examining or approving them according to the specified

27、 authority; 3. Organizing the joint checkup of construction drawing, coordinating related work with individual departments and units; 4. Responsible for technical training and evaluation work before commencement of this project, verifying commencement conditions; organizing and implementing construc

28、tion process control according to quality plan as well as related management system procedure document of the company; 5. Taking direct responsibilities for the quality of this project, assuming technical responsibilities for project safety; 6. Responsible for timeliness, accuracy of the final accep

29、tance data. Technique Principal1. Assisting chief engineer to manage the implementation of project technical work, examining construction drawing, reading design documents and construction drawings carefully, understanding design intention, preparing quality plan, construction organization design an

30、d construction technology, safety measures; 2. Preparing Construction Guide Book, safety construction measures and construction technique manual, as well as their release and management; responsible for site design document, management and release of construction drawings; providing construction tec

31、hnology and safety intention explanation for construction personnel, instructing construction according to relevant procedure documents; organizing the sorting and handover of project completion data, supervising and instructing construction team to fill out various construction record forms correct

32、ly; 3. Accepting and executing the commands of consulting engineer related with design change and technical requirements, organizing the implementation; 4. Participating in the purchase inspection of engineering materials, coordinating with the special person for materials to prepare supply plan of

33、machines, tools and materials, coordinating with quality control, safety supervision personnel to supervise and check construction quality and safety; Quality Control Principal1. Assisting chief engineer to manage the implementation of project quality control: supervising works quality in accordance

34、 with Consultants instruction and corresponding quality control standard, organizing and participating quality inspection on construction team and project management, compiling quality scheme, fulfilling quality management to make sure quality management system operate effectively. 2. Applying inter

35、mediate acceptance and final acceptance to the consulting engineer, participating in the acceptance; 3. Participating in the purchase inspection of engineering materials, coordinating with the special person for materials to prepare supply plan of machines, tools and materials, coordinating with qua

36、lity control, safety supervision personnel to supervise and check construction quality and safety;Safety Management Principal1. Responsible for construction safety management; 2. Responsible for safety education and post training of construction personnel; 3. Organizing inspection test of tools, app

37、aratus and mechanical equipment; 4. Organizing to implement project safety health and environment management work to ensure effective operation of project occupational safety and health and environment management system; 5. Supervising and instructing construction team to fill out various safe const

38、ruction record forms correctly; 6. Submitting safety supervision work report to the project manager; 7. Commissioned by the project manager, presiding over safety accident investigation, submitting investigation report, putting forward correction opinions. Plan and Finance Principal 1. According to

39、the project schedule, managing labor force and funds etc resources, project contract management, budget management and cost control, formulating project disbursement plan;2. According to the construction progress, resource utilization and funds utilization, using MS Project management software for c

40、ollection, analysis and sorting of implementation record, preparing adjustment plan at stages; 3. Sorting out and summarizing various reports required by Head Office and consulting engineer, reporting to the owner, consulting engineer and Company Home Office on specified time. Materials Principal1.

41、Establishing and completing management systems of on-site materials, tools and equipment according to requirements of related quality system procedure documents, managing on-site materials, tools and equipment; 2. Formulating configuration plan of tools, apparatus and equipment according to the cons

42、truction schedule and construction proposal, organizing implementation; 3. According to the project schedule of construction organization design and physical supply time provided by general contract unit, formulating engineering goods and materials supply plan and organizing the implementation; 4. R

43、eceiving and sorting out materials quality certification, test report; 5. Organizing purchase, processing of engineering materials; 6. Responsible for receiving, keeping, releasing management of materials. Construction team leader1. The person responsible for management work of this construction tea

44、m, organizing construction of the personnel according to Construction Organization Design and Construction Guide Books, organizing self-check, ensuring construction in controlled state, takes full responsibility of construction quality, safety, progress, cost and civilized construction etc in this t

45、eam; 2. According to construction arrangement of the Project Department, organizing to complete construction task in the designated construction section; 3. Implementing various work instructions, safety, quality and civilized construction provisions issued and forwarded by the Project Department du

46、ring construction. 4. Organizing to implement quality, safety activities during construction, correcting problems in the construction timely, taking preventive measures as required; 5. Achieving engineering management objectives in the construction section. Construction personnel1. Operating accordi

47、ng to requirements of the work instructions under the leadership of construction team leader, abiding by organization disciplines and technical regulations on construction site, ensuring works to meet project construction requirements; 2. Participating in the quality, safety activities, participatin

48、g in democratic management of the team, adjustment rationalization proposal actively. Chapter 3 General Layout Plan of the Construction Site3.1 Construction layout plan3.1.1 Principle1) The location of Project Management DepartmentThe location of Project Management Department is in C and construction teams

展开阅读全文
相似文档                                   自信AI助手自信AI助手
猜你喜欢                                   自信AI导航自信AI导航
搜索标签

当前位置:首页 > 考试专区 > 中考

移动网页_全站_页脚广告1

关于我们      便捷服务       自信AI       AI导航        获赠5币

©2010-2024 宁波自信网络信息技术有限公司  版权所有

客服电话:4008-655-100  投诉/维权电话:4009-655-100

gongan.png浙公网安备33021202000488号   

icp.png浙ICP备2021020529号-1  |  浙B2-20240490  

关注我们 :gzh.png    weibo.png    LOFTER.png 

客服