资源描述
主变压器本体安装
main transformer proper installation
表号table number:DL/T5161.3-1.0.3-1
工序procedure
检查项目inspection items
质量原则quality standard
检查成果inspection results
基础
安装foundation
预埋件embedded parts
按设计规定对照设计图纸检查meet the designs
基础水平误差foundation level error
<5mm
轨道间距误差space error between tracks
<5mm
油绝缘性能oil insulation
原则规定值standardized reading
本
体
就
位proper position
套管与封闭母线中心线the centerline of bushing and sealed busbar
一致identical
支墩与变压器及预埋件连接connection of rest pier to the transformer and embedded parts
牢固firm
本体接地proper grounding
牢固,导通良好firm, conductivity
冲击值和次数impact value and frequency
按制造厂规定值according to the manufacturer’s data
其他
others
油箱顶部定位装置orientation device on the top of the oil tank
无变形,无开裂no deformation, no crack
验收结论:
质检机构
Quality inspection organization
验收意见Comments
签名Signature
NEPC施工班组
Construction teamSigned confirmation
符合 comply
NEPC工地技术员
Site Technician Signed confirmation
符合 comply
NEPC(专业工程师)
Professional engineer Signed confirmation
符合 comply
CNEEC(专业工程师)
Professional engineer Signed confirmation
符合 comply
HPC/OE(专业工程师)
Professional engineer Signed confirmation
符合 comply
变压器检查
inspection of the transformer
表号form number:DL/T5161.3- 1.0.3-2
主变压器检查inspection of the transformer
检查状态inspection
工序procedure
检查项目inspection items
质量原则quality standard
检查成果result
器
身
外
观
Appearance
器身各部位each location
无移动no movement
各部件外观appearance of each part
无烧伤、损坏及变形no burned or damaged deformation
各部件绑扎措施each part binding
齐全、紧固complete and firm
绝缘螺栓及垫块insulation bolt and sizing block
齐全,无损坏,且防松措施可靠complete, no damage, not loose
绕组及引出线绝缘层insulation layer of widing and leads i
完整、包缠牢固紧密complete, wrapped tightly
铁
芯transformer core
铁芯接地the core grounding
1点,连接可靠 one point, connection steady
铁芯绝缘the core insulation
用2500V兆欧表测试,不不不小于200兆欧。By 2500V megaohm meter not less than 200megaohm
绕
组
winding
裸导体exposed conductor
外观appearance
无毛刺、尖角、断股、断片、拧弯 no burr, no sharp horn, no break wire, no break piece, not bent
焊接welding
满焊,无脱焊fully welded, no loose weld
高压应力锥high voltage stress cone
完好function
油路(有围屏者除外)oilline, ( the one with screen not included)
无异物,畅通smooth
均压屏蔽罩(500kV高压侧)average voltage shield(500kV side)
完好,无损伤complete, no damage
线圈固定检查winding fix inspection
固定牢固firm
绕组绝缘winding insulation
不低于出厂值旳70% not lower than 70% of manufacturer’s requirement
电
压
切
换
装
置
voltage switch
连接connection
可靠steady
开关
触头switch head
清洁度、弹力cleanness, bounce
无锈蚀、油污、且弹性良好no rust, no grease, bounced well
接触touch
可靠,塞尺塞不进steady, by feeler
对应位置relative positions
对旳、一致correct, identical
部件装配parts equipped
齐全、对旳complete, correct
无励磁分接开关non-excitation tap
操作杆长度handle length
三相一致 identical three phase
转动器rotator
动作灵活,密封良好responsive, sealed well
有载调压分接开关load tap changing
开关动作次序sequence of switches
对旳,切换时无开路correct, circuit closed when switched
切z换开关密封seal of switch
良好function
强油循环管与下轭绝缘接口密封insulation interface seal between forced circulation tube and lower yoke
良好functiion
其他others
各部位清理clearing of each part
无杂物、污迹、屑末no dirt, no grease, no scraps
阀门动作vavle response
验收结论:
质检机构
Quality inspection organization
验收意见Comments
签名Signature
NEPC施工班组
Construction teamSigned confirmation
符合 comply
NEPC工地技术员
Site Technician Signed confirmation
符合 comply
NEPC(专业工程师)
Professional engineer Signed confirmation
符合 comply
CNEEC(专业工程师)
Professional engineer Signed confirmation
符合 comply
HPC/OE(专业工程师)
Professional engineer Signed confirmation
符合 comply
主变压器附件安装
the main transformer accessories installed
表号form number:DL/T5161.3- 1.0.3-3
主变压器附件安装 the main transformer accessories installed
检查状态inspection
工序procedure
检查项目inspection item
质量原则quality standard
检查成果inspection result
高
压
套
管
安
装
high voltage bushing installed
套管及电流互感器试验bushing and current mutual inductance test
合格acceptable
升高座安装hoist seat installed
外观
检查appearance
接线端子wiring terminal
牢固,无渗漏油firm, no leakage of oil
放气塞air release plug
升高座最高处at the top of hoist seat
安装位置installation position
对旳correct
绝缘筒装配insulation canister equipped
对旳,不影响套管穿人correct, not disturb to the insertion of bushing
法兰连接flange connection
紧密sealed
套管检查bushing inspection
清洁,无损伤,油位正常clean, no damage, regular oil level
法兰连接螺栓flange connection bolt
齐全,紧固complete, firm
引
出
线
安
装wire leads
穿线wire insertion
顺直、不扭曲straight and not twisted
220kV
应力锥stress cone
在均压罩内,深度合适inside the equalizer cover, fair depth
500kV
均压球equalizer ball
在均压屏蔽罩内间距15mm左右15mm space inside the equalizer cover
引线与套管连接connection between leads and bushing
连接螺栓紧固,密封良好connection bolt fastened, sealed
低压
套管
low voltage bushing
套管检查bushing inspection
清洁,无损伤clean, and no damage
法兰连接flange connection
连接螺栓紧固connection bolt fastened
电压
切换
装置
voltage switch
无励磁分
接开关non-excitation tap switch
传动连杆driven rod
回装对旳,转动无卡阻smooth rotatation
指示器indicator
密封良好sealed well
有载调压
开关 load tap-changing
分接头位置与指示器指示tap position and indicator
对应,且联锁、限位对旳, matched, interlocked, limited
油室密封oil chamber sealed
良好function
储
油
柜
安
装
oil tank installed
内部检查inside inspection
清洁、无杂物clean, no dirt
胶囊或隔阂bag or separation film
无变形、损伤,且清洁no deform, no damage, and clean
胶囊或隔阂气密性bag or separation film air-tight
无泄漏no leakage
胶囊口密封bag sealed
无泄漏,呼吸畅通no leakage, wind smoothly
油位计检查oil level inspection
反应真实油位actual response of oil level
吸湿器安装moisture-absorber installed
连通管connection tube
无堵塞、清洁smooth and clean
油封油位oil level of oil seal
在油面线处at oil surface line
吸湿剂moisture-absorbent
颜色正常regular color
安全气道安装及压力释放阀安装safety air duct installed and pressure release valve installed
内部检查inside inspection
无杂物、污迹no dirt, no smear
隔阂separation film
完好function
隔阂与法兰连接connection between separation film and flange
严密,不与大气相通sealed, not connected to atmosphere
隔阂位置触点separation film location head
动作精确,绝缘良好responsive, insulated
释放器压力releaser pressure
位置location
对旳correct
阀盖及弹簧valve cover and spring
无变动no change
电触点检查inspection of power head
动作精确,绝缘良好responsive, and insulated
气体继电器安装
gas relay installed
校验calibration
合格acceptable
继电器安装relay installed
位置对旳,无渗漏location, no leakage
连通管升高坡度the up gradient of connection tube
便于气体排向气体继电器gas discharged to the gas relay
温度计安装thermometer installed
温度计校验themometer calibration
制造厂已校验manufacturer calibration
插座内介质及密封socket medium and seals
与箱内油一致,密封良好identical to the oil inside the oil tank, sealed well
测温包毛细导管capillary of temperature measurement
无压偏、死弯,弯曲半径不小于50mm not flattened, no dead leg, elbow radius greater tan 50mm
冷
却
器
安
装
cooler installed
外观检查appearance
无变形、法兰端面平整no deform, flat ends of flange
密封性试验seal test
按制造厂规定follow manufacturer’s procedure
支座及拉杆调整adjustment of holder and rod
法兰面平行、密封垫居中不偏心受压parallel flange ends, seal pad centering
潜油泵submerged oil pump
结合面严密 joint surface sealed
流速、差压继电器
flow velocity and relay with difference of voltage
按制造厂规定follow manufacturer’s procedure
风扇fan
牢固,叶片无变形firm, blade not deformed
阀门动作valve response
操作灵活,开闭位置对旳responsive, open and close at correct positions
外接管路outlet pipeline,
内壁清洁,流向标志对旳clean inner wall and flow direction label
冷却器安装cooler installed
内部检查inside inspection
清洁,无杂物、污迹clean, no dirt, no smear
滤网检查filter inspection
完好function
吸湿剂absorbent
白色不透明white and not transparent
其他others
耐油绝缘导线oil-proof insulation wire
排列整洁,保护措施齐全arranged in order, protected
接线箱盒junction box
牢固,密封良好firm, sealed well
控制箱安装control box installed
牢固firm
验收结论:
质检机构
Quality inspection organization
验收意见Comments
签名Signature
NEPC施工班组
Construction teamSigned confirmation
符合 comply
NEPC工地技术员
Site Technician Signed confirmation
符合 comply
NEPC(专业工程师)
Professional engineer Signed confirmation
符合 comply
CNEEC(专业工程师)
Professional engineer Signed confirmation
符合 comply
HPC/OE(专业工程师)
Professional engineer Signed confirmation
符合 comply
主变压器注油及密封试验
the transformer oiling and seal test
表号form number:DL/T5161.3- 1.0.3-4
主变压器注油及密封试验the transformer oiling and seal test
检查状态inspection
工序procedure
检查项目inspection items
质量原则quality standard
检查成果result
变
压
器
注
油transformer oiling
绝缘油试验insulation oil test
合格acceptable
检查试验汇报test report
油温(220kV及以上变压器)oil temperature(for 220kV above transformer)
高于器身温度higher than proper temperature
用温度计检查themometer checked
器身温度proper temperature
>20OC
真空度vacuum extent
按制造厂规定follow manufacturer’s data
注油前真空保持时间vacuum time before oiling
按制造厂规定follow manufacturer’s data
注油(循环)速度L/min oiling (circulation) velocity L/min
按制造厂规定follow manufacturer’s data
注油过程检查(220kV及以上变压器)oiling inspection (for 220kV and 220kV above transformer)
按制造厂规定follow manufacturer’s data
变压器注油transformer oiling
注油后真空保持时间vacuum time after oiling
按制造厂规定follow manufacturer’s data
油位检查oil level
油标指示oil indication
对旳correct
油标指示与油枕油面高度oil surface level of oil indication and oil conservator
按制造厂规定follow manufacturer’s data
500kV变热油循环器500kV hot oil circulator
净油设备出口油 oil purifying equipment outlet oil OC
按制造厂规定follow manufacturer’s data
油箱内温 temperature inside oil tank OC
按制造厂规定follow manufacturer’s data
循环时间 circulation time h
按制造厂规定follow manufacturer’s data
热油循环后油质试验oil quality after hot oil circulation
合格acceptable
整体密封试验overall seal test
试验压力pressure test MPa
按制造厂规定follow manufacturer’s data
试验时间 test time h
按制造厂规定follow manufacturer’s data
所有焊缝及结合面密封seal on all welding joints and joint surface
无渗漏no leakage
验收结论:
质检机构
Quality inspection organization
验收意见Comments
签名Signature
NEPC施工班组
Construction teamSigned confirmation
符合 comply
NEPC工地技术员
Site Technician Signed confirmation
符合 comply
NEPC(专业工程师)
Professional engineer Signed confirmation
符合 comply
CNEEC(专业工程师)
Professional engineer Signed confirmation
符合 comply
HPC/OE(专业工程师)
Professional engineer Signed confirmation
符合 comply
主变压器整体检查
the transformer overall inspection
表号form number:DL/T5161.3- 1.0.3-5
主变压器整体检查the transformer overall inspection
检查状态inspection
工序procedure
检查项目inspection item
质量原则quality standard
检查成果result
变
压
器
整
体
检
查
the transformer overall inspection
铭牌及接线图标志nameplate and wiring tags
齐全,清晰complete, clear
所有附件安装all accessories installed
对旳,牢固correct and firm
油系统阀门oil system valve
打开,且指示对旳opened, and correct indication
变压器外观appearance of the transformer
清洁,顶盖无遗留物clean and no residual on the top cover
分接开关位置及指示tap switch position indication
符合支行规定位置指示对旳meet the requirement for position indication
油位oil level
正常regular
测温装置temperature measurement device
指标对旳 correct indication
气体继电器gas relay
模拟试验良好simulation test
冷却装置cooler
试运良好,联动可靠operation and linkage
事故排油消防设施fire fight facilities for emergency oil drainage
完好,投运可靠function
试验项目test item
合格,无漏项acceptable not leave out
整体密封 overall seal
无渗油no leakage of oil
相色标志phase label
齐全,对旳complete and correct
接地grounding
铁芯和夹件接地引出套管bushing from core and clamp grounding
牢固,导通良好firm and conduction
高压套管末屏high voltage bushing end-screen
电流互感器备用二次端子secondary terminal for current mutual inductor
短路后可靠接地grounding when short circuit
本体及基础proper and base
牢固,导通良好firm and conduction
引线与主线地网连接grounding grid for leading wire and master wire
牢固,导通良好firm and conduction
孔洞封堵opening closed
严密sealed
验收结论:
质检机构
Quality inspection organization
验收意见Comments
签名Signature
NEPC施工班组
Construction teamSigned confirmation
符合 comply
NEPC工地技术员
Site Technician Signed confirmation
符合 comply
NEPC(专业工程师)
Professional engineer Signed confirmation
符合 comply
CNEEC(专业工程师)
Professional engineer Signed confirmation
符合 comply
HPC/OE(专业工程师)
Professional engineer Signed confirmation
符合 comply
展开阅读全文