资源描述
陕西省商州区高级中学建设项目
高 压 线 围 护
施
工
方
案
编制人:
审核人:
批准人:
编制单位:
编制时间:
目 录
一、 编制说明························································································2
二、 编制依据·······································································································2
三、 工程概况及现场概况·····················································································2
四、 防护方法·······································································································2
五、 施工技术要求································································································3
六、 搭设方法·······································································································3
七、 施工安全措施································································································4
八、 安全技术措施································································································5
九、 防护架体检查·······························································································5
十、 防护架拆除···································································································6
十一、 安全、文明施工························································································7
十二、劳动力安排································································································7
高压电线围护专项施工方案
一、 编制说明
本工程为陕西省商州区高级中学建设项目,4#图书馆南侧现正使用学校围墙边,有高压电线一路在塔吊回转半径范围之内。根据《施工现场临时用电安全技术规范》JGJ46-2005要求,防止塔吊钢丝绳碰撞高压电线,因此需要高压电线进行防护。
二、 编制依据
1、 施工现场实地勘察。
2、 《施工现场临时用电安全技术规范》(JCJ46-2005)
3、 《建筑施工高处作业安全技术规范》(JGJ80-91)
4、 《建筑施工扣件式钢管脚手架安全技术规程》(JGJ130-2011)
5、 国家相关规范规定。
三、 工程概况及现场概况
1、 工程概况
工程名称:陕西省商州区高级中学建设项目
工程地址:陕西省商州区大赵峪办事处东龙山
业主单位:陕西省商州区高级中学项目建设管理处
建设单位:商洛明城基础设施开发有限公司
勘察设计单位:商洛市建筑勘察设计院
监理单位:陕西远大工程项目管理有限公司
2、 现场概况
在本建设项目4#图书馆南侧,现正使用学校围墙边,有架空高压电线一路在塔吊回转半径范围之内。根据《施工现场临时用电安全技术规范》JGJ46-2005要求,为防止塔吊钢丝绳碰撞高压电线,必须采取安全防护措施。
四、 防护方法
因施工所用的塔吊需要360°回转,所以现场南侧搭设防护架体。架体采用两种材料搭设,6m以下采用扣件式钢管脚手架,6m及其以上采用竹木搭设,高度超出高压线2米,水平距离离高压线1.5米,顶层铺设毛竹片做保护。详见附图。
底部采用扣件式钢管脚手架搭设,上部采用绝缘材料毛竹搭设防护栏杆,搭设参数为:步高1.8米,搭设高度为超过高压线2米。同时在高压线保护栏上设警示牌,警示牌上书写:“高压危险”。或者每隔6米,在立杆上固定一面红旗,以示警戒。
五、 施工技术要求
1、 搭设材料
1.1钢管采用Φ48×3.5mm的钢管,有严重锈蚀、弯曲、压扁、损伤和裂纹的均不得使用。扣件应有合格证明,要光洁灵活,发现有脆裂、变形、清丝等现象禁止使用。
1.2根据现场实际情况,用钢管搭设架体底下6m,6m以上的架体采用毛竹搭设,毛竹有效部分小头直径不得小于75mm。
1.3绑扎铁丝用12#脚手架专用铁丝,镀锌铁丝使用时不允许用火烧,次品和锈蚀严重的镀锌铁丝严禁使用。
1.4围护材料采用:高压线下2米往上靠工地一侧处采用毛竹片,其他部分采用密目安全网。
1.5厚木垫板,木板厚度不得小于50宽度不得小于300,木板不得腐蚀,变形、破裂等质量缺陷。
2、 搭设尺寸及要求
2.1防护架总长度按照塔吊辐射范围确定(约110米),立杆间距为1.5米,水平杆步距为1.8米,第一步扫地杆距地0.15米。防护距离离围墙0.5米。
2.2防护栏杆每隔5米设抛撑一根,抛撑必须与地面牢固连接。同时防护栏与外架进行连接,以保证防护架体的稳定。
2.3所有立杆和抛撑基础必须回填夯实密实,确保基底平整、坚实、不下沉。
2.4防护架应牢固稳定具有抗风能力,围护竹片绑扎牢固保证不掉落。
2.5利用学校围墙,采用Φ9.3钢丝绳与围墙拉结,拉结部位同时用毛竹与围墙斜撑防止反向倾覆。
3、 参照标准:《施工现场临时用电安全技术规范》(JGJ46-2005)第4.1.4条、4.1.6条。
六、 搭设方法
1、 准备工作
1.1清除施工现场的障碍物。
1.2夯实搭设防护栏杆范围内的基土,并排好立杆位置,用厚木板垫与立杆之下,木板必须垫实、垫平。
1.3根据毛竹粗细、材质、外形等进行合理挑选分类,决定其用途及使用的部位。
2、 施工工艺流程及要求
场地平整夯实→确定立杆位置→铺垫垫板→竖立杆→绑扫地杆→绑大横杆→固定杆件与防护架体的连接→竹笆的铺挂→警示标志安装→红旗的绑扎。
2.1场地平整:因本架体属于防护架且架体较高,能拉结的地方很少,只能靠架体本身相互拉结,形成整体而稳定。因此对架体地基密实度和平整度要求极高,必须按照施工规范要求施工。
2.2垫板:垫板铺设必须平整,板底必须与基土接触实在,不得有空虚出现。
2.3扫地杆:防护栏杆高度较高,在立杆底部加扫地杆绑扎牢固。
2.4竖立杆:先竖两端头立杆,再竖中间立杆。立杆竖好后,应纵成行横成方,杆身垂直。立杆弯曲时,其弯曲面应顺纵向方向,既不能朝高压线面也不能背高压线面,以保证大横杆能与立杆接触良好。
2.5绑大横杆:防护栏两端大横杆的大头应朝外。绑扎第一步架的大横杆时,应检查立杆是否埋正、埋牢。同一步架的大横杆大头朝向应一致,上下相邻两步架的大横杆大头朝向应相反,以增强防护架的稳定。
2.6绑扎水平和竖向防护毛竹片,应与防护架立杆、横杆绑扎牢固,绑扎间距不得大于500mm,每张毛竹片应有支撑点,防止坠落。
2.7安装警示标志,在围护竹笆外安装警示标志,所有警示标志必须安装牢固。每3~4根立杆上绑扎一面红旗也起警示作用。
3、 搭设标准
3.1钢管架部分必须严格按照《建筑式钢管脚手架安全技术规程》要求施工。
3.2毛竹架部分必须满足下列要求:
⑴立杆:立杆应大头朝下,上下垂直,立杆杆身垂直偏差不得超过架高的1/1000,且不得大于100mm。不得向外偏斜。最后一根立杆应大头朝上,为使立杆顶端齐平,可将高出的立杆向下错动。
⑵立杆必须按规定进行接长,相邻立杆的接头至少错开一步架,接头的搭接长度不得小于1.5米。为使接长后的立杆位于同一平面内,上下立杆的接头应沿纵向错开。
⑶横杆:大横按绑在立杆内侧,沿纵向平放。大横杆必须按规定进行接长,接头应置于立杆处,大头伸出立杆200~300mm,并使小头压在大头上,搭接长度不小于1.5米。接头位置,上下相邻大横杆的接头应错开一个立杆。
七、施工安全措施
1、搭设和拆除防护架必须由符合“特种作业人员安全技术考核规定”的架子工进行,操作人员必须持证上岗,且不得穿高跟鞋操作,有不适应高空作业的人员不得上岗(如恐高症等)。操作时必须佩戴安全帽、安全带、穿防滑鞋。
2、 操作人员进入施工现场必须遵守安全生产六大纪律,必须带好安全帽及安全带,并扣好安全扣。
3、 大雾、大雨、大雪和六级以上的大风天气,不得进行防护架上的高处作业,雨雪天后作业必须采取安全防滑措施。
4、 初始搭设时应有临时支撑,防止初立的立杆倾倒伤人。
5、 在搭至近高压线时,须特别注意每次传递竹杆不得与高压线相碰,操作人员必须相互提醒,相互关心。
6、 在搭设时,必须由专业的安全员全程巡视监控作业人员操作的各个环节的安全动态情况,发现有不符合安全规范的地方,尤其是在距高压线很近时必须全程监控。
7、 在作业前,安全员应向班组操作人员作详细的交底并严格按照方案搭设技术要求进行。
8、 作业人员在搭设过程中注意架体高升时防止杆件坠落伤人。
9、 搭设前应设置警戒线,并指派专人看护,防止人员进入警戒区。
八、安全技术措施
1、对各作业班组进行安全用电教育,特别电工、塔吊驾驶员除必要的安全交底、教育外;针对场内的高压线、变压器的使用安全,要求每日交接班检查,任何人未经许可不得进入。
2、项目部把高压线立为重大危险源,针对重大危险源制定专职安全员每日巡检,项目部周检制度。
3、防护架搭设前必须根据规范规定和施工方案,制定防护架的安全技术措施。
4、为防止塔吊钢丝绳碰撞高压线,对塔吊离最近一根高压线5米处设立限位装置,现场设监管人员一名,严禁塔吊转入高压线和校园内侧。
5、塔吊设专职指挥一名,在高压线旁吊物时有专人指挥。
6、搭设时应拉通常拉线,立好立杆档子。
九、防护架体检查
1、防护架搭设和使用前的检查
1.1防护架搭设好后,由工地技术负责人和安全员会同搭设班组按规定项目和要求进行检查,检查合格后办理交接验收手续方准许交付使用。
1.2检验要求如下:
(1)整体防护架必须保持垂直、稳定,不得向外倾斜。
(2)防护架与围墙的拉结点必须牢固,间距符合设计规定。
(3)毛竹、镀锌铁丝的尺寸和材质必须符合规定。
(4)立杆、斜杆底部应有垫块。填土要夯实,不得有松动现象,并应高出周围的地面。
(5)各杆件的间距及倾斜角度应符合规定。
(6)镀锌铁丝绑扎应符合规定,且不允许一扣绑扎三根杆件。
2、 防护架使用期间的检查
2.1防护架使用期间必须设专人经常检查。
2.2检查项目如下:
(1)防护架有否出现倾斜或变形。
(2)与围墙拉撑点是否有缺失。
(3)绑扎点镀锌铁丝有否出现松脱和断裂。
(4)立杆有否出现沉陷和悬空。
检查后不合格部位必须及时修复或更换,符合规范规定后,方准许继续使用。
3、 防护架在特殊情况下的检查
暂停工程复工,大雨、大雪及冰雪融化后的工程,必须重新对防护架进行详细的检查,符合要求后,方准许继续使用。
4、 管理
4.1材料部门购进的防护毛竹规格和材质应符合规范规定,不得采购等外材或残次品作为防护架的部件使用。
4.2施工过程中,未经技术负责人批准,不得随意抽拆防护架上的杆件,并应及时清除防护架上的垃圾和冰雪等杂物。
4.3竹杆应安规定分别堆放,四周设置消防器材,如灭火器、消防桶等备用。
十、 防护架拆除
1、 架子使用完毕后应由专业架子工拆除防护架。
2、 防护架时,作业区及进出口处必须设置警戒标志,派专人指挥,严禁非作业人员进入。
3、 拆除的杆件应自上而下传递或利用滑轮和绳索运送,不得从架子上向下随便抛落。
十一、 安全文明施工
现场安全文明施工应符合施工组织设计及现场的其他要求。
加设防护措施时宜采用采用线路暂时停电措施,并有电气工程技术人员和专职安全人员监护。线路无法停电的情况下,必须在公司电气专业技术人员的指导和监护下进行施工。加设防护措施时,请甲方协调电力公司有关人员到工地现场进行指导和过程监督,一定要做好防护工作。
十二、 工期及劳动力安排
施工进度计划如下:
序
号
任 务
名 称
工期
2016年10月
10
11
12
13
14
15
16
17
18
19
1
架体基土夯实
1天
2
铺设垫板
1天
3
竖立定位
1天
4
架体搭设
6天
5
警示旗警示标志安装
1天
劳动力安排
序 号
工 种
人 数
备 注
1
辅 助 工
8 人
普 通 工 人
2
架 子 工
12 人
持 证 人 员
附图<一>
附图<二>
附图<三>
展开阅读全文