土木工程施工课程设计
专业:
姓名:
班级:
学号:
导师:
时间:
精品资料
目录
第一章 工程概况····················································1
一、建筑、结构概况···············································1
二、施工条件概况·················································1
第二章 工程量计算··················································
一、土方工程量····················································
二、基础工程工程量················································
三、柱工程量······················································
四、梁工程量······················································
五、楼梯工程量····················································
六、预制板工程量··················································
七、工程量清单表··················································
第三章 施工方案····················································
一、施工段划分····················································
二、工期控制······················································
三、施工顺序······················································
四、施工工艺······················································
五、施工方法·····················································
六、施工时间·····················································
七、模板方案·····················································
第四章 机械设备选择················································
第五章 主要技术措施················································
第六章 施工总平面图··············································
第七章 施工进度计划表···········································
精品资料
第一章 工程概况
一、建筑、结构概况
建筑设计特点:本工程为某无线电厂生产车间,总体呈矩形分布,建筑物总高16.90m,总长54.30m,总宽21.3m;共四层,首层层高为4.5m,二、三标准层层高均为4.2m,顶层层高4.0m,屋顶为平屋顶。
结构设计特点:本工程采用钢筋混凝土框架结构,框架柱统一截面尺寸为400mm×450mm,梁截面300mm×400mm、300mm×500mm和300mm×600mm等,楼面铺设180mm厚预应力钢筋混凝土空心板。采用柱下独立基础,尺寸均为2050mm×2050mm,阶梯形;基础埋深为2.0m,下设100厚混凝土垫层;采用现浇混凝土板式楼梯;室外设计地坪标高为-0.45m。
二、施工条件概况
地形:平坦
土质:亚粘土
雨季:4-6月份
地下水位:最高地下水位位于地面以下2.0m
开工时间:2016年7月8日
施工工期:275天(根据施工定额)
钢筋:由加工厂加工成型后运至现场。
混凝土:采用商品混凝土,水电由市区供应。
交通:厂内可通行车辆
材料:建筑材料齐全,技术力量雄厚,劳动力由公司工程处统一调配。
第二章 工程量计算
根据施工段的划分原则,每层分两个施工段,分界线在5号轴线柱右侧。取1~5轴基础层为第1施工段,6~10轴基础层为第2施工段,其他层依次类推。
一、土方工程量
根据土的类别取基坑放坡系数为0.5。
基础尺寸:2.05m×2.05m。
下底:(四周考虑0.3m的工作面)。
上底:。
采用机械挖土,考虑到基坑开挖尺寸及运输车辆的进出,选择采用条形开挖;不考虑地基梁所需挖土的土方量。
(1)、开挖工程量
第1施工段:
010101003001 [(3×6+0.15+1.025+0.1+0.3)+(4×6+0.15+1.025+
0.1+0.3)×2+(3.75+1.025+0.1+0.3-1.325)+(6+1.025+0.1+0.3)×2]××(2.1-0.45)×(2.65+4.3)=512.74
第2施工段:
010101003002 [(5×6-0.15+1.025+0.1+0.3)×3]××(2.1-0.45)×(2.65+4.3)=538
(2)、填方工程量
a、基础回填:
第1施工段:
010103001001 512.74-41.51-18×[(1.2-0.45)×0.45×0.45+2.25×2.25×0.1]=459.38
第2施工段:
010103001002 538-34.59-15×[(1.2-0.45)×0.45×0.45+2.25×2.25×0.1]=493.54
b、房心回填:
第1施工段:
010103001003 [(6-0.3)×(7.5-0.3)×7+(6-0.3)×(3.75-0.3)+(6-0.3)×(6-0.3)×2]×0.45=167.4
第2施工段:
010103001004 (6-0.3)×(7.5-0.3)×10×0.45-0.3×0.4×(6-0.3)
=184.0
二、基础工程工程量
(1)、基础混凝土工程量
第1施工段:
010501003001 18×(2.05×2.05×0.4+1.25×1.25×0.4)=41.51
第2施工段:
010501003002 15×(2.05×2.05×0.4+1.25×1.25×0.4)=34.59
(2)、基础钢筋工程量
第1施工段:
010515001011 41.51×36=1.5t
第2施工段:
010515001012 34.59×36=1.25t
(3)、基础模板工程量
第1施工段:
011703003001 18×(2.05×4+1.25×4)×0.4=95.04
第2施工段:
011703003002 15×(2.05×4+1.25×4)×0.4=79.2
(4) 垫层混凝土量
第1施工段:
010501001001 2.07×0.1×[19.275+25.275×2+3.55+7.125×2]
=18.14
第2施工段:
010501001002 2.07×0.1×([(5×6-0.15+1.025+0.1)×3]
=19.24
三、 柱工程量
(1)柱混凝土工程量
第1施工段:
010502001001 18×0.4×0.45×(4.5+1.2)+0.2×0.3×(4.5+0.2)
=18.75
第2施工段:
010502001002 15×0.4×0.45×(4.5+1.2)+0.25×0.3×(4.5+0.2)×2=16.1
第3、5施工段:
010502001003 18×0.4×0.45×4.2+0.2×0.3×4.2=13.86
010502001005 18×0.4×0.45×4.2+0.2×0.3×4.2=13.86
第4、6施工段:
010502001004 15×0.4×0.45×4.2+0.25×0.3×4.2×2=11.97
010502001006 15×0.4×0.45×4.2+0.25×0.3×4.2×2=11.97
第7施工段:
010502001007 18×0.4×0.45×4.0+0.2×0.3×4.0=13.2
第8施工段:
010502001008 15×0.4×0.45×4.0+0.25×0.3×4.0×2=11.4
(2) 柱钢筋工程量
010515001021 18.75×130/1000=2.44t
010515001022 16.1×130/1000=2.1t
010515001023 13.86×130/1000=1.8t
010515001024 11.97×130/1000=1.56t
010515001025 13.86×130/1000=1.8t
010515001026 11.97×130/1000=1.56t
010515001027 13.2×130/1000=1.72t
010515001028 11.4×130/1000=1.48t
(3) 柱模板工程量
第1施工段:
011703007001 18×(0.4+0.45)×2×(4.5+1.2)+(0.2+0.3)×2×(4.5+0.2)=179.12
第2施工段:
011703007002 15×(0.4+0.45)×2×(4.5+1.2)+(0.25+0.3)×2×2×(4.5+0.2)=155.69
第3、5施工段:
011703007003 18×(0.4+0.45)×2×4.2+(0.2+0.3)×2×4.2=132.72
011703007005 18×(0.4+0.45)×2×4.2+(0.2+0.3)×2×4.2=132.72
第4、6施工段:
011703007004 15×(0.4+0.45)×2×4.2+(0.25+0.3)×2×2×4.2=116.34
011703007006 15×(0.4+0.45)×2×4.2+(0.25+0.3)×2×2×4.2=116.34
第7施工段:
011703007007 18×(0.4+0.45)×2×4.2+(0.2+0.3)×2×4.0=132.52
第8施工段
011703007008 15×(0.4+0.45)×2×4.0+(0.25+0.3)×2×2×4.0=110.8
四、 梁工程量
(1)梁混凝土工程量
第1施工段:
基础梁:
010503001011 7×0.3×0.5×(6-0.4)+0.3×0.5×(6-0.2-0.15)+2×0.3×0.5×(6-0.45)+0.3×0.5×(7.5-0.45)+0.3×0.5×(3.75-0.45)+0.3×0.6×(7.5-0.45)+6×0.3×0.4×(6-0.4)+0.3×0.4×(6-0.45)+7×0.3×0.4×(7.5-0.45)=21.85
首层梁:
010503002011 矩形梁[(6+7.5+3.75-3×0.45)+(7.5×2+6-3×0.45-0.25)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×0.3×0.8+(6-0.3)×0.2×0.4=17.03
010503003011 异形梁[(24-4×0.4)×(0.25×0.5+0.2×0.18)]+[(6×6-6×0.4)×(0.25×0.32+0.18×0.45)]+[(4×6-4×0.4)×(0.25×0.5+0.2×0.18)]=12.86
第2施工段:
基础梁:
010503001021 8×0.3×0.5×(6-0.4)+2×0.3×0.5×(7.5-0.45)+2×0.3×0.6×(7.5-0.45)+6×0.3×0.4×(6-0.4)+6×0.3×0.4×(7.5-0.45)=16.86
首层梁:
010503002021 矩形梁[2×(7.5×2-2×0.45)+2×(7.5×2-2×0.45-2×0.2)+(7.5×2-2×0.45)]×0.3×0.8+(6-0.3)×0.2×0.4=17.18
010503003021 异形梁[(30-5×0.4)×(0.25×0.5+0.2×0.18)]+[(5×6-5×0.4)×(0.25×0.32+0.18×0.45)]+[(5×6-5×0.4)×(0.25×0.5+0.2×0.18)]=13.53
第3、5施工段:
01050300203/51 矩形梁[(6+7.5+3.75-3×0.45)+(7.5×2+6-3×0.45-0.25)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×0.3×0.8+(6-0.3)×0.2×0.4=17.03
01050300303/51 异形梁[(24-4×0.4)×(0.25×0.5+0.2×0.18)]+[(6×6-6×0.4)×(0.25×0.32+0.18×0.45)]+[(4×6-4×0.4)×(0.25×0.5+0.2×0.18)]=12.86
第4、6施工段:
01050300204/61 矩形梁[2×(7.5×2-2×0.45)+2×(7.5×2-2×0.45-2×0.2)+(7.5×2-2×0.45)]×0.3×0.8+(6-0.3)×0.2×0.4=17.18
01050300304/61 异形梁[(30-5×0.4)×(0.25×0.5+0.2×0.18)]+[(5×6-5×0.4)×(0.25×0.32+0.18×0.45)]+[(5×6-5×0.4)×(0.25×0.5+0.2×0.18)]=13.53
第7施工段:
010503002071 矩形梁[(6+7.5+3.75-3×0.45)+(7.5×2+6-3×0.45)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×0.3×0.7+[(24-4×0.4)×0.25×0.5]+[(6×6-6×0.4)×(0.25×0.5]+[(4×6-4×0.4)×0.25×0.5]=24.35
第8施工段:
010503002081 矩形梁5×(7.5×2-2×0.45)×0.3×0.7+[(30-5×0.4)×0.25×0.5]+[(5×6-5×0.4)×0.25×0.5]+[(5×6-5×0.4)×0.25×0.5]=25.31
(2) 梁钢筋工程量
010515001031 (21.85+12.86)×115/1000+17.03×150/1000=6.55t
010515001032 (16.86+13.53)×115/1000+17.18×150/1000=6.07t
010515001033 12.86×115/1000+17.03×150/1000=4.03t
010515001034 13.53×115/1000+17.18×150/1000=4.14t
010515001035 12.86×115/1000+17.03×150/1000=4.03t
010515001036 13.53×115/1000+17.18×150/1000=4.14t
010515001037 14.55×150/1000+9.8×115/1000=3.31t
010515001038 14.81×150/1000+10.50×115/1000=3.43t
(3)梁模板工程量
第1施工段:
011703010001 基础梁7×0.5×2×(6-0.4)+0.5×2×(6-0.2-0.15)+2×0.5×2×(6-0.45)+0.5×2×(7.5-0.45)+0.5×2×(3.75-0.45)+2×0.6×(7.5-0.45)+6×0.4×2×(6-0.4)+0.4×2×(6-0.45)+7×0.4×2×(7.5-0.45)=146.96
011703011001 矩形梁[(6+7.5+3.75-3×0.45)+(7.5×2+6-3×0.45-0.25)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×(0.3+0.8×2)+(6-0.3)×(0.2+0.4×2)=136.90
011703012001 异形梁[(24-4×0.4)×(0.5+0.25+0.32+0.2+0.18)
]+[(6×6-6×0.4)×(0.18+0.1+0.32+0.25+0.32+0.1+0.18)]+[(4×6-4×0.4)×(0.18+0.2+0.32+0.25+0.5)]=113.68
第2施工段:
011703010002 基础梁8×0.5×2×(6-0.4)+2×0.5×2×(7.5-0.45)+2×0.6×2×(7.5-0.45)+6×0.4×2×(6-0.4)+6×0.4×2×(7.5-0.45)=136.54
011703011002 矩形梁[2×(7.5×2-2×0.45)+2×(7.5×2-2×0.45-2×0.2)+(7.5×2-2×0.45)]×(0.3+0.8×2)+(6-0.3)×(0.2+0.4×2)=160.93
011703012002 异形梁[(30-5×0.4)×(0.5+0.25+0.32+0.2+0.18)
]+[(5×6-5×0.4)×(0.18+0.1+0.32+0.25+0.32+0.1+0.18)]+[(5×6-5×0.4)×(0.18+0.2+0.32+0.25+0.5)]=121.8
第3、5施工段:
011703011003/5 矩形梁[(6+7.5+3.75-3×0.45)+(7.5×2+6-3×0.45-0.25)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×(0.3+0.8×2)+(6-0.3)×(0.2+0.4×2)=136.90
011703012003/5 异形梁[(24-4×0.4)×(0.5+0.25+0.32+0.2+0.18)
]+[(6×6-6×0.4)×(0.18+0.1+0.32+0.25+0.32+0.1+0.18)]+[(4×6-4×0.4)×(0.18+0.2+0.32+0.25+0.5)]=113.68
第4、6施工段:
011703011004/6 矩形梁[2×(7.5×2-2×0.45)+2×(7.5×2-2×0.45-2×0.2)+(7.5×2-2×0.45)]×(0.3+0.8×2)+(6-0.3)×(0.2+0.4×2)=160.93
011703012004/6 异形梁[(30-5×0.4)×(0.5+0.25+0.32+0.2+0.18)
]+[(5×6-5×0.4)×(0.18+0.1+0.32+0.25+0.32+0.1+0.18)]+[(5×6-5×0.4)×(0.18+0.2+0.32+0.25+0.5)]=121.8
第7施工段:
011703011007 矩形梁[(6+7.5+3.75-3×0.45)+(7.5×2+6-3×0.45)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×(0.3+2×0.7)+[(24-4×0.4)×(0.25+2×0.5)]+[(6×6-6×0.4)×(0.25+2×0.5)]+[(4×6-4×0.4)×(0.25+2×0.5)]=218.51
第8施工段:
011703011008 矩形梁5×(7.5×2-2×0.45)×(0.3+2×0.7)+[(30-5×0.4)×(0.25+2×0.5)]+[(5×6-5×0.4)×(0.25+2×0.5)]+[(5×6-5×0.4)×(0.25+2×0.5)]=224.85
五、 楼梯工程量
(1) 楼梯混凝土工程量
010506001001 现浇楼梯3×2×(6-0.3)×(3.75-0.325)×0.2
=23.43
(2) 楼梯钢筋工程量
010515001041 现浇楼梯23.43×55/1000=1.29t
(3) 楼梯模板工程量
011703029001 现浇直型3×2×(6-0.3)×(3.75-0.325)=117.14
六、 预制板工程量
(1)预制板混凝土工程量
010512002001 YKB6062:4×72×0.34=97.92
010512002002 YKB6092:4×90×0.455=163.8
第1施工段:
YKB6062:32
YKB6092:44
第2施工段:
YKB6062:40
YKB6092:46
(2)预制板钢筋工程量
010515005001 后张法YKB6062钢筋:4×72×17.18/1000=4.95t
010515005002 后张法YKB6092钢筋:4×90×24.23/1000=8.73t
七、 工程量清单表
表一:土方工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
010101003001
第1施工段挖方
亚粘土
1.65m
512.74
2
010101003002
第2施工段挖方
亚粘土
1.65m
538
3
010103001001
第1施工段基础回填
亚粘土、原土及郊区运来
459.38
4
010103001002
第2施工段基础回填
亚粘土、原土及郊区运来
493.54
5
010103001003
第1施工段房心回填
亚粘土、原土及郊区运来
167.4
6
010103001004
第2施工段房心回填
亚粘土、原土及郊区运来
184
表二:基础工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
010501003001
第1施工段基础混凝土
基础高0.8m
阶梯形
41.51
3
2
010501003002
第2施工段基础混凝土
基础高0.8m
阶梯形
34.59
2.5
3
010515001011
第1施工段基础钢筋
螺纹钢
t
1.5
0.5
4
010515001012
第2施工段基础钢筋
螺纹钢
t
1.25
0.5
5
011703003001
第1施工段基础模板
基础高0.8m
阶梯形
95.04
装10.5
拆4
6
011703003002
第2施工段基础模板
基础高0.8m
阶梯形
79.2
装9
拆3.5
7
010501001001
第一施工段基础垫层
C15
厚10
18.14
1.5
8
010501001002
第二施工段基础垫层
C15
厚10
19.24
1.5
表三:柱工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
010502001001
第1施工段柱砼
矩形柱
普通砼
18.75
3.5
2
010502001002
第2施工段柱砼
矩形柱
普通砼
16.1
3
3
010502001003
第3施工段柱砼
矩形柱
普通砼
13.86
2.5
4
010502001004
第4施工段柱砼
矩形柱
普通砼
11.97
2
5
010502001005
第5施工段柱砼
矩形柱
普通砼
13.86
2.5
6
0105020010016
第6施工段柱砼
矩形柱
普通砼
11.97
2
7
010502001007
第7施工段柱砼
矩形柱
普通砼
13.2
2.5
8
010502001008
第8施工段柱砼
矩形柱
普通砼
11.4
2
9
010515001021
第1施工段柱钢筋
螺纹钢
t
2.44
1
10
010515001022
第2施工段柱钢筋
螺纹钢
t
2.1
1
11
010515001023
第3施工段柱钢筋
螺纹钢
t
1.8
0.5
12
010515001024
第4施工段柱钢筋
螺纹钢
t
1.56
0.5
13
010515001025
第5施工段柱钢筋
螺纹钢
t
1.8
0.5
14
010515001026
第6施工段柱钢筋
螺纹钢
t
1.56
0.5
15
010515001027
第7施工段柱钢筋
螺纹钢
t
1.72
0.5
16
010515001028
第8施工段柱钢筋
螺纹钢
t
1.48
0.5
17
011703007001
第1施工段矩形柱
400×450、
250×300
179.12
装29
拆8.5
18
011703007002
第2施工段矩形柱
400×450、
250×300
155.69
装25.5
拆7
19
011703007003
第3施工段矩形柱
400×450、
250×300
132.72
装21.5
拆6
20
011703007004
第4施工段矩形柱
400×450、
250×300
116.34
装19
拆5.5
21
011703007005
第5施工段矩形柱
400×450、
250×300
132.72
装21.5
拆6
22
011703007006
第6施工段矩形柱
400×450、
250×300
116.34
装19
拆5.5
23
011703007007
第7施工段矩形柱
400×450、
250×300
132.52
装21.5
拆6
24
011703007008
第8施工段矩形柱
400×450、
250×300
110.8
装18
拆5
表四:梁工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
010503001011
第1施工段基础梁砼
普通砼
21.85
4.5
2
010503002011
第1施工段矩形梁砼
普通砼
17.03
3
011703012011
第1施工段异形梁砼
普通砼
12.86
4
010503001021
第2施工段基础梁砼
普通砼
16.86
4.6
5
010503002021
第2施工段矩形梁砼
普通砼
17.18
6
011703012022
第2施工段异形梁砼
普通砼
13.53
7
010503002031
第3施工段矩形梁砼
普通砼
17.03
3
8
011703012032
第3施工段异形梁砼
普通砼
12.86
9
010503002041
第4施工段矩形梁砼
普通砼
17.18
3
10
011703012042
第4施工段异形梁砼
普通砼
13.53
11
010503002051
第5施工段矩形梁砼
普通砼
17.03
3
12
011703012052
第5施工段异形梁砼
普通砼
12.86
13
010503002061
第6施工段矩形梁砼
普通砼
17.18
3
14
011703012062
第6施工段异形梁砼
普通砼
13.53
15
010503002071
第7施工段矩形梁砼
普通砼
24.35
2.5
16
010503002081
第8施工段矩形梁砼
普通砼
25.31
2.5
17
010515001031
第1施工段钢筋量
螺纹钢
t
6.55
3
18
010515001032
第2施工段钢筋量
螺纹钢
t
6.07
2.5
19
010515001033
第3施工段钢筋量
螺纹钢
t
4.03
2
20
010515001034
第4施工段钢筋量
螺纹钢
t
4.14
2
21
010515001035
第5施工段钢筋量
螺纹钢
t
4.03
2
22
010515001036
第6施工段钢筋量
螺纹钢
t
4.14
2
23
010515001037
第7施工段钢筋量
螺纹钢
t
3.31
1.5
24
010515001038
第8施工段钢筋量
螺纹钢
t
3.43
1.5
25
011703010001
第1施工段基础模板
钢模、木模
146.96
装60
拆21
26
011703011001
第1施工段矩形模板
钢模、木模
136.90
27
011703012001
第1施工段异形模板
钢模、木模
113.68
28
011703010002
第2施工段基础模板
钢模、木模
136.54
装63
拆22
29
011703011002
第2施工段矩形模板
钢模、木模
160.93
30
011703012002
第2施工段异形模板
钢模、木模
121.8
31
011703011003
第3施工段矩形模板
钢模、木模
113.68
装41.5
拆14.5
32
011703012003
第3施工段异形模板
钢模、木模
136.54
33
011703011004
第4施工段矩形模板
钢模、木模
160.93
装42.5
拆15
34
011703012004
第4施工段异形模板
钢模、木模
121.8
35
011703011005
第5施工段矩形模板
钢模、木模
113.68
装41.5
拆14.5
36
011703012005
第5施工段异形模板
钢模、木模
136.54
37
011703011006
第6施工段矩形模板
钢模、木模
160.93
装42.5
拆15
38
011703012006
第6施工段异形模板
钢模、木模
121.8
39
011703011007
第7施工段矩形模板
钢模、木模
218.51
装33
拆11.5
40
011703011008
第8施工段矩形模板
钢模、木模
224.85
装34
拆12
表五:楼梯工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
010515001041
现浇直型楼梯砼
普通砼
23.43
5
2
010515001041
现浇直型楼梯钢筋
螺纹钢
t
1.29
1
3
011703029001
现浇直型楼梯模板
钢模、木模
117.14
装113
拆13.5
表六:预制板工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
010512002001
YKB6062h砼量
普通砼
97.92
9.5
2
010512002002
YKB6092砼量
普通砼
163.8
15.5
3
010515005001
YKB6062钢筋
后张法螺纹钢、钢绞线
t
4.95
1.5
4
010515005002
YKB6092钢筋
后张法螺纹钢、钢绞线
t
8.73
2.5
5
A1
第1/3/5/7施工段
YKB6062数量
块
32
1台班
6
A2
第2/4/6/8施工段
YKB6062数量
块
40
1台班
7
B1
第1/3/5/7施工段
YKB6062数量
块
44
1台班
8
B2
第2/4/6/8施工段
YKB6062数量
块
46
1台班
第三章 施工方案
针对该工程工期紧、结构体系复杂、工程量大、工序交叉多、场地狭窄、环境制约等特点,在保证工程质量和安全生产的前提下,应以工期为主导,精心组织、合理安排,充分利用有效的时间和空间,采用先进的施工工艺,确保整个工程如期完成目标。施工方案选择如下:
1、钢筋工程:钢筋由专人统一计划配料,钢筋由专门的钢筋加工车间加工,现场钢筋连接分别采用绑扎接头搭接,电渣压力焊、双面搭接焊等施工工艺。
2、模板工程:基础承台及地梁、墙、梁、楼梯模板采用胶合板模板和钢模板。
3、砼工程:砼全部采用预拌商品砼,由场外砼搅拌站供应,用砼搅拌运输车运至现场,砼泵送车输送砼。
4、地面以上主体结构工程施工布置:
地面以上主体结构工程支模和钢筋绑扎同时进行,在钢筋加工、砼浇筑方面进行流水作业。模板拟采用18厚木模板配制,支撑采用门字架搭设。外脚架采用落地式钢管脚手架。
5、施工机械:工程现场设置1台提升架,以供垂直运输。
一、施工段划分
根据施工段的划分原则,每层分两个施工段,分界线在5号轴线柱右侧。取1~5轴基础层为第1施工段,6~10轴基础层为第2施工段,其他层依次类推。
二、 工期控制
(1)、计划编制原则
根据总的施工部署和总体施工方案的安排,编制工程进度计划时以基础、主体及外墙装饰为主,利用好每一天的工作时间,分区组织施工,分段流水作业,来确保工程的工期要求,全面地完成本次招标范围内的工程项目,让建设单位满意。
(2)、施工进度计划
计划开工日期:2016年7月8日
计划竣工日期:2017年4月8日
总工期:275日历天
三、施工顺序
1、总体施工顺序:
基础工程→主体框架结构→砌筑围护结构→内外墙装修→水电安装、防雷测试→竣工验收。
2、各阶段施工顺序安排:
基础阶段:±0.00以下基础(包括地面砼板)。
测量放线→基坑开挖、修边、检底、排水→承台砼垫层→放线→承台、地梁→回填土→承台、地梁钢筋安装绑扎→浇砼。
主体阶段阶段:±0.00以上主体结构施工。
绑扎柱筋→隐蔽验收→安装柱模板、梁板模板→浇柱砼→绑扎梁板钢筋→隐蔽验收→浇梁板砼→下一楼层施工段施工。砌砖、室内装修施工随主体进度插入施工。
装饰阶段:内外装饰。
内装饰施工程序为:顶棚→墙面→楼地面。
外墙面装饰为:外墙全高吊垂直线,逐层弹出水平控制线→做灰饼、冲筋→找平层抹灰→安装门窗框→贴外墙面砖。
竣工阶段:室内外清理、竣