1、-精品word文档 值得下载 值得拥有-高地温隧道综合施工技术研究报告中铁十六局集团 杨长顺摘要:本文针对禄劝铅厂引水隧洞突发性高地温地质情况,分析了高地温的热源及产生原因,说明了高地温给施工带来的困难及危害;介绍了施工中采取的各种综合技术措施,研究探讨了高地温隧道通风降温计算方法及应用,进行了用于指导施工的通风降温计算。可供类似工程参考。关键词:高地温隧道 无轨运输 综合技术 通风降温The high ground temperature tunnel synthesizes the technology memoir being under constructionChina Railwa
2、y 16th Group C0,Ltd YangchangshunAbstract: The main body of a book the tunnel has dashed forward specifically for the Lu Quan lead factory draws water sending out high nature ground temperature geology condition , has analysed the high ground temperature heat source and has produced cause , difficul
3、ty and damage having explained that the high ground temperature is brought about by construction; Synthesis technology measure having introduced various adopting in construction, the ground temperature tunnel ventilation having studied investigation and discussion highly cools down calculating metho
4、d and applies, the cooling having carried out the ventilation being used to guide to be under construction secretly schemes against. May provide the similar project reference. Keywords: high ground temperature tunnel,trackless transportation, synthesis technology ,be ventilated cooling down1 工程概况禄劝铅
5、厂水电站工程位于云南省昆明市禄劝县境内的普渡河下游,电站装机容量257MW,工程规模为中型。我单位施工的C2、C3标为发电厂引水隧洞SD0100SD5690段,隧洞开挖为圆形断面,开挖直径为786810,初期支护断面770。发电引水普渡河左岸,隧洞沿线地表坡度变化大,前后段山体宽厚,中部缓和,冲沟切割较深,岩体倾向右岸,形成有前后两级陡岩组成的向普渡河倾斜的大斜坡地貌,隧洞最大埋深380m,由三条支洞施工,洞身穿过围岩岩性为震旦系灯影组,含硅质条带白云岩,岩体性脆、质硬。受区域断裂影响,隧洞附近猫得村处河左岸出露一热泉,其矿化度较高;库外枢纽下游多处发育热泉,含硫量大,矿化度高,出露于普渡河背
6、斜倾伏段。普渡河流域地处低纬亚热带高原湿润季风气候区。本流域具有年降雨量集中程度高,光热资源条件好,降雨量丰富,干湿季分明的特点。根据气象站资料统计,多年平均气温在14.715.8之间,极端最高气温在31.433.4之间,极端最低气温在-7.86.5之间,最热月(7月)平均气温19.7,最冷月(1月)平均气温7.7 ,多年平均降雨量约986.0mm,多年平均降雨日数134.6d。该项目于2007年1月开工,采用无轨运输施工,2008年1月12月为高地温围岩施工期。高地温地段以外,围岩一般温度为2223,按30以上为高低温段,高地温地段里程为SD1+300SD2+500;其中,70以上高温岩层地
7、段为SD1+734SD1+842,该段局部围岩极端温度达76,上报资料75为平均值;K1+500K2+100段有少量裂隙水,水温最高达70;高地温岩层分别由1#、2#支洞施工,分界里程为SD2+100, 分界点围岩温度为40。附:开挖断面图(临时支护)2 高地温的热源 火山热的热源:由于火山供给的热是地下岩浆集中处的热能而产生的热水,这种热水(泉水)成为热源又将热供给周围的岩层。当隧道或地下工程穿过这种岩层,就有发生高温、高热的现象。 放射性元素的裂变热的热源:在地球内部由于放射性元素不断进行脱变或其他原因放出大量热能,加之岩石是热的不良导体,因此在地下深处积累了大量热能,发生较高温度,此种现
8、象称为地热现象。 其它原因:浅层或地表水与深部热水循环交替,成为承压高温热水,形成高温异常区。岩浆侵入体的余热、硫化矿床的氧化热等。 热源分析:2008年12月1#支洞与2#支洞贯通,2009年3月及5月两次实测原来温度最高地段暴露面岩温均为3233,少量裂隙水温43.,隧洞附近温泉水池水温仍为63。禄劝铅厂水电站引水隧洞的埋深不大,施工中出现高地温属于不可预见的突发事件,形成原因非常复杂。地热不属于火山热的热源,热源来源范围局限为:放射性元素的裂变热的热源、浅层或地表水与深部热水循环交替、岩浆侵入体的余热、硫化矿床的氧化热等。因为隧洞穿越为陡岩地形,水平方向必然临近深埋地段,地温受深埋地段影
9、响;隧道处于地下温泉多发地段,距隧洞约600m处有一处温泉,水温7080,距隧道约300m处普渡河边有一处温泉,水池水温63,形成温泉的地质条件及温泉的影响,是隧洞形成高地温的主要原因,因事发突然,缺乏对地质资料的深入研究,不排除其它方面的复杂原因。3 高地温隧道施工技术措施禄劝铅厂引水隧洞在施工时突然遇到了国内没有、国外罕见、又缺乏相关地质资料的高地温,隧道穿越高地温岩层时,施工作业环境恶化,严重威胁到施工人员的健康和安全,大大降低了劳动生产率;隧道内的高温高湿还导致机械设备的工作条件恶化、效率降低、故障增多,装载机、汽车经常熄火。禄劝铅厂引水隧洞1#支洞掘进至SD1+300以后,围岩温度不
10、断升高,当围岩温度达到50以上时,施工环境严重恶化,开始采用加大通风量、喷雾洒水措施降温,初始还能维持施工,但当岩温达到60时,由于施工人员的中暑反映及机械设备的故障,使施工一度被迫中断。由于事发突然,国内还没有60以上大断面或接近大断面的无轨运输高地温隧道施工经验,经有关专家论证,借鉴国内外矿井施工的有关降温措施,研究了适合高地温隧道施工的综合技术措施,强化措施后,改善了施工条件,使施工安全、顺利进行,保证了进度、质量。主要技术措施如下:3.1 通风降温依据传热学原理,参照有关围岩与风流间传热量的计算方法,研究开发适合高地温隧道施工的通风降温计算公式、计算方法。通过对隧道内的围岩导热、导温系
11、数的测定或选取,进行对流换热过程的理论分析,借鉴矿井热环境调节理论,依据国内外学者对不稳定换热系数的定义,根据大断面或接近大断面无轨运输隧道施工的特点,研究60以上高地温的大断面或接近大断面的无轨运输施工隧道风流的热交换和风温计算公式,确定围岩散热所需的通风量。通过减少风阻、防止漏风、更换或增加风机,将通风软管出风口置于距掌子面10m之内的位置,加强通风管理等措施加大进风量。通风降温采用公路隧道施工技术规范有关规定,隧道内气温不宜高于30。在通风量计算时,应尽量加大洞内风速,最低应按1级软风标准(0.31.5m/s),确保洞内风速不小于0.3m/s,使人感觉相对舒适。3.2 喷雾洒水降温采用喷
12、射混凝土的喷头做喷雾器,将进水管路改为25mm,接高压风、水管路,进行喷雾洒水作业。在出渣前,对爆破作业后新暴露的岩面、岩块、碎渣喷水洒水降温,减少热源;施工时,采用24台喷雾器配合通风降温。3.3 隔绝高温围岩喷混凝土时,添加0.03%高效引气剂,使混凝土内部形成分布均匀的不连续的封闭球形气泡,气泡孔径范围为0.020.2 mm,可起到一定的隔热作用。3.4 热水防治热水对风流的加热作用相当显著。在裂隙水温较高的地段,挖积水坑,采用抽水机将热水排出出,降低工作面的热源。3.5 采取有效的个体防护据有关资料介绍,个体防护的方法是让施工人员穿戴冷却背心或冷却帽。我们经过研究,认为研制冷却帽、冷却
13、背心周期长、成本高,不太现实。根据插袋式冷却背心是在冷却背心中插入蒸发冷却袋或羽冰冷却袋或相变冷却袋的原理,决定利用普通冰柜制作冰块,用于施工人员个体防护。可使用冰箱专用的制冰容器或矿泉水瓶、塑料袋灌水制作冰块。先期进洞拉风管至工作面及实施喷雾洒水的工作的人员采用矿泉水瓶、塑料袋灌水制作冰块,用于施工人员个体防护。先期进洞拉风管至工作面及实施喷雾洒水的工作的人员在高温环境下工作,应在安全帽内放置冰块,使用挎包携带1020块(约510kg)冰块,置于胸前、背后灵活使用,冰块融化升温后随时更换,通过冰块降温完全消除工作时的闷热感,起到了很好的防护作用,施工中没有人出现中暑症状。3.6 工作面人工制
14、冷降温当采用隔绝热源、加强通风、喷雾洒水等非制冷措施不足以消除热害时,根据有关资料,可用空调系统进行降温。考虑到隧道施工断面大、输送距离长,采用空调系统造价高的原因,否决了安装空调系统的方案,根据隧道施工人员多集中在掌子面范围的特点,决定采用订制、运输冰块到掌子面作为施工降温预案。3.7强化人员健康管:高地温隧道施工时,为了施工人员的身体健康,同时也是为了提高劳动效率,改8小时作业为3小时作业,对施工人员全面体检,禁止有高血压、心脏病的患者及循环器官有异常的人员参加劳动,同时配备医务人员进行热痉挛症、热虚脱症和热射症等中暑症的防治工作。3.8无轨运输设备防高温措施装载机、汽车作业时,随时注意水
15、温表的指示读数,要求不能超过80。装载机出渣作业时,使用经改进的喷射混凝土喷头,不间断的对装载机喷雾洒水降温,每隔半小时在装载机水箱内加注冷水并投放适量冰块,防止装载机因为高温造成的发动机功率下降、制动性能减弱等故障,在驾驶室内搁置自制冰块,配合设备的空调系统为操作人员创造舒适的工作条件;增加自卸汽车的配置数量,减少汽车在洞内的作业时间,汽车进洞前在水箱内加注冷水,投放适量冰块,驾驶员携带冰块配合空调降温;加强行车路面的洒水降温工作,防止暴胎;利用钻孔时间,对装载机、自卸汽车进行保养,确保设备运转正常。3.9 加强监测工作用数据指导施工对洞内外温度进行全天候检测,在夏季晴天时,因进风温度较高,
16、白天宜停止洞内爆破作业,利用当地白天热晚间凉,利于通风降温的特点施工;雨天时,全天作业;阴天时,根据气温确定;当夏季夜间作业不能满足进度要求时,考虑建一间进风房,安装制冷设备,将通风机进风口空气制冷作为预案。夏季夜间施工,采用喷雾洒水配合通风降温仍然不能把工作面区域温度降到30以下时,应启动运输冰块降温预案;在预定通风时间内,风流温度达不到预期目的时,应延长时间。施工时,必须按有关规定对洞内有害气体进行检测。岩温量测应尽量利用掌子面残孔,没有残孔时利用新钻炮孔,使用32cm长的温度计,应全部插入,要尽量早测、深测,测量要靠近受风流影响小的边、角、底部,每次不少于3个孔。采用GPR地质雷达法进行
17、隧道地质超前预报,探测掌子面前方23米范围内的地质情况。探测的目的主要是预防大量温泉水的涌入,探测结果是围岩整体性较好,仅有少量裂隙水,不需要采取措施。3.10 其他措施针对选用专用爆破器材的意见行了咨询,有关爆破专家认为100以下岩温对普通雷管、炸药没有多大影响,可不采取措施,但应严格按操作规程施工。针对对混凝土施工采用措施的建议及要求,根据围岩开挖后,随暴露时间的增加,岩温不断下降这一实际情况,确认岩温对混凝土的影响不大,但为了慎重起见,还是采取了选定合适的水灰比,采用高炉矿渣水泥(分离粉碎型水泥)等措施。4 隧道通风降温计算数学模型及公式4.1 围岩与风流间传热量及通风流量的一般计算公式
18、隧道围岩与风流间的传热是一个复杂的不稳定传热过程。隧道开掘后,随着时间的推移,围岩被冷却的范围逐渐扩大,其所向风流传递的热量逐渐减少;为简化研究,目前常将这些复杂的影响因素都归结到传热系数中去讨论。因此,隧道围岩与风流间的传热量可依据由牛顿冷却公式得来的壁面与流体间的对流换热量公式进行研究,该公式为: (1)式中:Q对流换热量,等于风流升温热量:V(t2-t1);对流换热系数,W/(m2);F流体接触的壁面面积;t壁面温度与边界层外流体温度的差值。用围岩与风流间的不稳定换热系数K替换公式(1)中的,用UL替换F,用(trm-t)替换t,可得出隧道围岩与风流间的传热量为: ,KW (2)式中:Q
19、井巷围岩传热量(KW),与对流换热量意义相同; K围岩与风流间的不稳定换热系数,KW/(m2); U断面周长(隧道),m; L隧道距开挖面长度,m; tr围岩温度,; t距工作面L处的平均风温,。设在长度L范围内t为变量,长度隧道壁散热量使风流温度升dt。当长度L=0时,t=t0,则 (3)分离变量两边积分、整理,得通风量计算公式: (4)式中:V通风流量,m3/s; t0初始风温,大于风管出口风温13,;空气的平均定压比热,=1.30KJm3.;4.2考虑围岩温度变化的计算公式公式4没有考虑岩温随开挖长度的变化因素,实际上开挖后围岩的温度随暴露时间的增加不断被风流冷却,也就是随开挖长度的增加
20、逐渐降低,围岩与风流间传热如图4所示。假定在开挖后的一段时间内,岩温在短距离内变化为: (5)式中: tr0开挖面围岩原始温度,; k围岩温度变化系数。将(5)代入(3),即得: (6)整理得: (7)微分方程(7)的通解为: (8)根据边界条件:t=t0时,L=0,即得L处平均风温计算公式: (9)当岩温变化系数为零时,公式(9)就可变换为公式(4),可以认为公式(4)是公式(9)的简化式。公式(4)使用简捷、方便,实际使用时,可以按公式(4)计算通风流量,再按公式(9)验证或修正。根据热力学第二定律,物体内的热量通过热传导作用不断地从高温点向低温点流动,使物体内温度逐步均一化。所以,公式(
21、9)中的岩温变化系数k随着时间的增加、围岩内温度逐步均一化而衰减并趋于零,公式(9)的计算结果适用于围岩开挖暴露后至围岩明显冷却这一时段。4.3掘进头近区围岩不稳定换热系数围岩与风流间的不稳定传热系数K是指隧道围岩深部未被冷却的岩体与空气间温差为1时,单位时间内从每m2隧道壁面上向空气放出(或吸收)的热量。它是围岩的热物理性质、隧道形状尺寸、通风强度及通风时间等的函数。由于不稳定传热系数的解析解相当复杂,没有统一的计算方法,一般参照矿井空调设计中的简化公式或统计公式计算。掘进头近区围岩不稳地内换热系数可按吴超主编的矿井通风与空气调节书中给定的公式确定:,KW/m2 (10)其中: ;。式中:岩
22、石的导热系数,实测或按表2选取,KW/m; a岩石的导温系数,实测或按表2选取,m2/h;3掘进头通风时间,h; 掘进头近区长度,m。表1 常见岩石的热学性质指标岩 石密 度(g/cm3)比热度导热系数导温系数a温度()J/(kgk)温度()W/(mk)温度()10-3cm2/s玄武岩2.892.8950883.4887.6501.611.73506.386.83辉绿岩3.0150787.1252.32209.46闪长岩2.92252.04209.47花岗岩2.502.7250787.1975.5502.173.085010.2914.31花岗闪长岩2.622.7620837.1256.020
23、1.642.33205.039.06片麻岩2.702.7350766.2870.8502.582.945011.3414.07大理岩2.69252.89石英岩2.6850787.1506.185029.52硬石膏2.652.91504.106.075017.0025.7粘土泥灰岩2.432.6450778.7979.7501.732.57508.0111.66白云岩2.532.7250921.1000.6502.523.795010.7514.97灰 岩2.412.6750824.8950.4501.72.68508.2412.15钙质泥灰岩2.432.6250837.4950.4501.84
24、2.40509.049.64致密灰岩2.582.6650824.8921.1502.343.515010.7815.21泥灰岩2.592.6750908.5925.3502.323.23509.8913.82粘土板岩2.622.8350858.3501.443.68506.4215.15盐 岩2.082.28504.485.745025.2033.80砂 岩2.352.9750502.185.15010.9423.62板 岩2.707621071.8502.60表1来自刘佑荣、唐辉明编著的岩体力学第三章岩石的物理、水理与热学性质。4.4 风管出口风温计算 通风机出口风温确定风流通过通风机后,其
25、出口风温一般可按下式确定: , (11)式中 Kb 通风机放热系数,可取0.550.7; t01 通风机入口处的风温; Ne 通风机额定功率,KW; Mb1 通风机的吸风量,Kg/s。风管出口风温依据实测数据,在没有实测数据的情况下进行通风降温计算时,可按公式(11)计算的通风机出口风温增加24考虑,或参照有关公式进行计算。5 禄劝铅厂引水隧洞降温通风量计算因为开挖掘进的工作面随着循环作业有规律的不断的向前推进,每一个开挖循环都有新的围岩暴露,新暴露的围岩热交换强烈。受风流热交换影响,随着时间的推移,围岩被冷却的范围逐渐扩大,其所向风流传递的热量逐渐减少,围岩温度随着暴露时间的增加不断下降。对
26、于60以上高地温隧道来说,高温随开挖出现,随风流降低。爆破后,受风流影响时间短的开挖面附近壁温高,距开挖面远、受风流影响时间长的壁温低。隧道在掘进期间,人员并不是沿全隧工作,一般只在掘进面或衬砌段工作。本隧洞高地温施工期间还没有开始衬砌作业,我们只需关心工作面一定长度范围内的的温度即可,一般选择掘进头工作长度100120m进行通风计算比较合理。因为热量主要来源于岩温,为简化计算,不考虑围岩温度以外的机械设备放热、弃渣放热等其它热源影响。5.1 计算参数选择 通风断面半径:R=3.85m,周长U=24.19m。 导热、导温系数:因事发突然,计算参数只能查阅参照有关资料,根据表1:白云岩的导热系数
27、=2.523.7910-3KW/m.,取平均值=3.15510-3KW/m.;导温系数a=1.0751.47910-6m2/s,取平均值a=1.27710-6m2/s=4.597210-3m2/h。选取的结果与用实验方法确定的糯扎渡电站洞室相关数值接近。糯扎渡电站洞室岩石导热系数=3.283w/m,导温系数a=1.4310-6m2/s。 计算长度:根据钻孔、出渣、初期支护的工作的需求,选取掘进头长度=110m。 通风时间:时间长影响进度,时间短增加投资,本次计算按爆破通风3h后,人员进洞工作考虑,掘进头通风时间3=3h。 围岩温度:隧洞掘进到SD1600时,出现60高地温,需要进行通风降为计算
28、,因为高地温的出现为不可预料事件,当时只能按预计最高岩温70计算,取平均值tr =65。实际掘进面测点极端最高岩温76,上报资料为平均75,实测距掘进面110m处岩温开挖后冷却为5055左右,实际最高岩温段110m距离内平均岩温小于65,实测平均岩温与预计相差不大。没有实测数据时,掌子面岩温依据地质资料,距掌子面100120m处岩温按掌子面岩温的6080%计(tr0乘以0.60.8的系数),开挖后根据实测数据修正。 洞内初始风温:实测风管出口风温1820,风管出口距掌子面6m时,风管出口附近风温1922。对于小断面的巷道来说,风管出口风温即初始风温,但对于大断面或接近大断面的隧道来说,情况就复
29、杂了,可按洞内初始风温大于风管出口风温13考虑,本次计算取初始风温t0 =20。最高温施工期为2008年56月,根据气象资料,当地5月平均气温21.1,极端最低11.3,夜间平均气温一般为14左右,实测环境温度14时,取通风机入口处的风温t01=14;通风机放热系数Kb =0.6;通风机的吸风量取27.47m3/s即Mb1=33.0Kg/s;风机功率取150KW。代入参数,按公式(10)计算得通风机出口风温:若按计算值增加24估算风管出口风温,与实测数据相差不大,其误差原因与计算参数选取有关。 根据工作需求,长度L=110m处平均风温t=30。5.2通风量计算根据选择的参数采用公式(11)、公
30、式(4),计算通风量得: 洞内风速:0.3m/s,满足要求,计算风流断面不计超挖等扩大、风管等缩小因素。按公式(9)验证,取,tr0=70,计算得:结果与按公式(4)计算时选取的30相差不多,不需要修正。5.3 计算不同时段的通风流量假定开挖后停止掘进,环境温度为恒温,通风为不间断连续的,计算不同时段降温所需的通风流量并绘制降温通风时间与流量关系曲线,用于分析比较。根据图3,平均岩温65时,连续降温通风3h,需要23.35m3/s的通风量可达到平均风温30的目的,但30天后,通风流量趋于平稳,仅需要2.02 m3/s就可达到同样的目的。这种变化也揭示了围岩的冷却过程,用来解释为什么隧洞贯通后仅
31、依靠自然通风就可以使围岩表面温度维持在32左右。实际围岩的冷却过程并没有曲线表示的那么快,因为有许多复杂因素的影响,例如:开挖爆破需要间断通风,通风是不连续的,进风温度随天气、时段不断变化,掘进也不会停止,爆破会给围岩带来新的热量,时间对不稳定换热系数的影响,热源来源及距离等原因;所以图3只能反映变化规律,并不完全符合实际情况。5.4 计算结果分析关于降温通风计算,我们参照了各种文献资料中给定的换热系数计算公式。进行了计算对比,其结果有接近的,也有相差很大的。我们认为,其差异在于时间、在于需求,对于忽略了时间的简化公式,需要短时间达到目的数值就大,需要较长时间达到目的数值就小,其规律如图3所示
32、。2008年12月份1号支洞与2号支洞贯通,之前,1号支洞与上游洞口早已贯通,贯通后拆除了通风设备,仅依靠自然通风,2009年1月实测,曾经是最高围温度段的岩温3233。我们采用的计算公式充分体现了随着通风时间的延长,原岩给予隧道的热量逐渐减少,隧道风温随时间及距离变化,为一不稳定换热过程。根据图2所示曲线,随着通风时间的延长,所需的降温通风量不断下降,完全符合隧道掘进时间越长,围岩的暴露时间就越长,围岩的调热圈就越大,围岩表面不断冷却,温度相应降低这一规律。 根据通风量随时间的变化规律,高温围岩随时间的推移不断冷却,通风量随时间的推移不断减少,但随着隧道不断的掘进,新开挖的高温不断出现,所以
33、选择掘进头进行通风降温计算是合理可行的。为什么很多已建成的隧道原预测温度很高,但实际施工时发现并不高呢?对于大断面隧道而言,施工本身就需要很大的通风量,不算很高的岩温在不知不觉中被通风冷却了,也就被忽视了。6 通风量、风压计算及设备选择1号支洞长293m,交叉点里程SD0664,1#支洞内高地温起点SD1300,2#支洞内高地温起点SD2500,施工时,预计最高温段在其中部,即SD3900处,从洞口到SD1900长1529m,计算时通风管长度按1500m计,选用直径1400mm风管。据风管厂商提供的技术指标,采用PVC增强塑纤布作风管材料,百米漏风率正常时可控制在2%以内。按有关公式计算得:风
34、机供风量应不小于: 隧道总风压:h总=3612pa根据计算的风压、风量,在立足现有、国产设备的基础上,选用咸阳风机厂产SDDY1N011A11型风机,其功率为275KW,风量96007100 m3/h,风压40005600Pa,完全可满足要求。7施工中根据实测数据指导施工开始进行通风计算时,调查的是夜间温度,按一天开挖一个循环施工考虑,计算参数取夜间温度14。实际施工时,为了满足进度要求,有时需要一天开挖两个循环,计算参数选择每日8时与20时的温度。根据实测环境温度19,修改计算参数,按公式计算(11)计算得通风机出口即风管进口风温,结合实测选取初始风温t0=25。表2 计算与实测风温对照表环
35、境温度14191919191919备注最高岩温75757565605040开挖面通风时间 h3364321连续时间计算风温29.933.831.531.33129.528.4距开挖面110m实测风温30353330302827距开挖面110m根据实测数据指导施工的施工工艺如图4所示。图4 通风降温施工工艺框图施工准备是否满足要求 通风降温计算确定方案并实施温度测量地质超前预报原方案继续施工 修改方案 否 是8 结语1、禄劝铅厂引水隧洞在施工中遇到了国内隧道施工从未遇到过的高地温,由于采取的综合技术措施先进、适用、方法得当,成功的攻克了高地温无轨运输隧道施工的难题。2、在计算方法方面,除去围岩不
36、稳定换热系数外,其余计算公式及方法均为我们独立研究开发,通过研究创新,填补了国内高地温无轨运输施工隧道通风降温计算方法的空白。新的计算公式符合开挖后围岩温度随通风时间变化这一客观规律;依据岩温开挖后的变化规律,采取掘进头100120m的长度进行通风降温计算的方法合理;通过分析、比较筛选出的不稳定换热系数计算公式切合实际;在高地温隧道施工理论研究、计算方法方面取得了新的进展。3、在施工中,运输冰块降温、进风口空气制冷预案未采用,只是占了洞外环境温度较低的便宜而已;因为地区温度的差异,季节温度的差异,在以后洞外环境温度较高的同类隧道施工中,这些方案仍可作为预案或必须实施的方案。高地温隧道的施工,关
37、键技术是通风降温,进风要凉,流量要大,才能散热、降温;进风凉需要利用好季节、时段,当这些经济手段不能满足要求时,就需要投入一定的财力、设备,将进风空气制冷。4、通过施工,验证了有关高温围开挖暴露后,由于比原岩温度低的风流作用,随暴露时间的增加,调热圈半径增大,隧道周围高温围岩相应被冷却,温度不断下降的规律,为同类隧道提供了宝贵的经验。5、通过实践否定了有关本隧洞因高地温需要特殊衬砌的说法及建议。不仅为无轨运输的高地温水工隧洞、也为同类的公路、铁路隧道施工提供了经验,高地温隧洞是否需要特殊衬砌?不能根据开挖前预测的地温决定,应根据开挖后岩温因风流的的变化情况慎重考虑。6、降温通风计算过程,除了掌
38、握围岩挖后的原始温度外,还需要掌握开挖暴露后距掌子面一定距离的岩温。围岩开挖暴露后的冷却过程因热源不同、地质条件不同、施工方法不同而异,隧道设计过程若能考虑这些因素的影响,提供相关数据,就可以在隧道开挖前就完成通风降温设计或为施工中的设计提供帮助。参考文献1 李岳林主编工程热力学与传热学M北京:人民交通出版社出版20072 吴超主编矿井通风与空气体调节M中南大学出版社20083 刘佑荣、唐辉明编著岩体力学中国地质大学出版社M1999 4 芩衍强等井巷与围岩间不稳定换热系数的探讨J阜新矿业学院学报1987(9) 5贵州工学院董海燕矿井对流换热系数计算及其影响因素分析R来源于百度快照说明:1、该项目已被评为总公司科技成果二等奖,2、内容已尽最大努力压缩作者:杨长顺、1952年10月出生、高级工程师、调研员地址:云南省昆明市关上关岭路199号中铁十六局集团云南工程指挥部邮编:650200联系电话:13908800930电子邮箱:ycs13987353988二九年十二月二十六日-精品word文档 值得下载 值得拥有-