收藏 分销(赏)

谈建设工程施工索赔和反索赔的探.doc

上传人:精*** 文档编号:3275224 上传时间:2024-06-28 格式:DOC 页数:8 大小:47.54KB
下载 相关 举报
谈建设工程施工索赔和反索赔的探.doc_第1页
第1页 / 共8页
谈建设工程施工索赔和反索赔的探.doc_第2页
第2页 / 共8页
谈建设工程施工索赔和反索赔的探.doc_第3页
第3页 / 共8页
谈建设工程施工索赔和反索赔的探.doc_第4页
第4页 / 共8页
谈建设工程施工索赔和反索赔的探.doc_第5页
第5页 / 共8页
点击查看更多>>
资源描述

1、谈建设工程施工索赔和反索赔旳探讨摘要施工索赔和反索赔是业主和承包商在工程项目施工过程中正常旳业务往来,它旳健康开展,对于培养和发展建设市场,增进建筑业旳发展,起着非常重要旳作用。 关键词:施工索赔、反索赔、风险-Talk about construction project claim and counter claimAbstractConstruction claim and counter claim is the normal business between the owner and the contractor,during the project construction pr

2、ocess , its health plays a very important rolein cultivating and developing construction market and promoting the development of the construction industry.Keywords: construction claim and counter claim, riskDirectoryThe abstract Abstract One The main characteristics of a claim 1.1 Risk claims 1.2 Co

3、nstruction conditions change claims 1.3 Quantities change too big claims 1.4 Time limit extension and delay claim 1. 5 To speed up the construction claim 1. 6 Other reasons claims Two The main characteristics of counter claim 2.1 Construction period delay counter claim 1 2.2 Construction defects cou

4、nter claim 2.3 A claim for payment of designated subcontractor Three Claims and counter claims relations Four Conclusions Five ReferencesOne The main characteristics of a claim1.1 Risk Claims Generally ,it includes the contract risk, political risk, economic risk, such as inflation, changes in natur

5、al conditions, complicated construction site conditions, the change of various laws and regulations, foreign currency exchange project risk, and so on. Because in the current construction market, the owner is always in a dominant position,they may shift the risk that should be borne by the owner to

6、the contractor by using improper or illegal means when tendering and the contract is signed,which causes contractors risking rate increases, so the construction claims is often put forward by the contractor, and their differences are often large. In recent years, due to the increase in construction

7、engineering construction team in China, the vast majority of construction enterprise exists serious task -insufficient phenomenon, which has caused an increasingly competitive construction market, the construction unit adopted a variety of unfair means in the bidding and contract signing, so on the

8、surface , the rights and obligations of the contractor and the owner are equal, but in all kinds of terms and attached conditions, there is essentially no equality.1. 2 Construction conditions change claims In the construction process, engineering inevitably appears new changes, especially the desig

9、n change. Contractors quotation is calculated on the basis of the original tender documents and drawings.According to the terms of the contract,any change of the number and nature of the work in the construction drawings and the change of any portion of the project construction plan are changes. If

10、such changes affect the cost of the contractor, the contractor can ask to estimate again,and puts forward to extend the time limit for a project requirements. In the actual construction, such claims will often cause controversy,and it is mainly because the difference between the owner and the contra

11、ctor for respective interests Angle.1. 3 Big change in construction quantities claimsOf actual construction, the complete quantities differ with quantities from design, 4th edition FIDIC52. 3 terms make a clear regulation, when price increases or decreases over 15%, it is allowed to make an adjustme

12、nt to the effective contract price.Main claims has the following several aspects: first, the damage caused by contractors construction equipment imbalance, due to the contractor at the time of bidding, and quantities as stated in the contract documents according to the tender documents and construct

13、ion requirements, formulate the construction plan, determine the number of construction equipment shall be equipped with, type, model and organization order, transport comes into play, and the large increase in quantity, certainly will ask for an increase in new construction machinery, or increase t

14、he number of the original mechanical, cause the contractor unplanned investment, expand the planned cost of the project. If the slashing of quantities, the cause of original equipment slowdown or unused, lead to losses of the contractor, at the same time, the change of the quantity, also make the co

15、ntractor construction material quantity change has been prepared, caused the claim. Second, it will cause the change of the schedule of quantities, which can cause period extended or reduced.1. 4 time limit extension and claim for the delayPeriod extension and claim for the delay, usually includes t

16、wo aspects: one is the contractor required extend the time limit for a project, 2 it is the contractor request payment due to contractors reason lead to project delays caused by the loss. Engineering construction, due to factors such as weather, hydrological, geological and engineering factors more

17、delay. When the contractor the cost of the extra spending without compensation, certainly will cause the claim.1. 5 to speed up the construction of the claimDisrupted when the project schedule, influence the realization of the overall objectives, lead to project cannot be completed on time and affec

18、ted the economic benefits of the owner, the owner through the analysis of project delays, will bring us great economic losses or political influence, or as part of project delay caused a series of engineering delay, the owner can use extra measures to release speed up the construction instructions,

19、request the contractor to invest more resources to complete the project, ensure the realization of overall objectives, and this will inevitably lead to the contractors project cost increases, caused by contractors claim.1. 6 Other causes of claimOwner defaults to provide construction site,and doesnt

20、 pay payment on due time, as a result,it causes the contractor construction team failed to play, or contractors cash flow difficulties, which affect the construction schedule, so it will cause the claim.Two The main characteristic of the counter claim2. 1 counter claim time limit for a project delay

21、In engineering project implementation process, due to the contractors reason, lead to after the completion date to pull, affect the use of the owner, the owner shall have the right to the contractor to claim for compensation, generally in the contract documents, the claim for compensation of a certa

22、in amount of calculation for each delay day, there are rules and ceiling.2. The 2 counter claim construction defectsWhen the construction quality of contractor does not conform to the specification requirements, or use of equipment, materials do not conform to the provisions of the contract, or in t

23、he guarantee period should be under unfinished before repair project, the owner shall have the right to the contractor shall be investigated for responsibility. If the contractor has not completed within the prescribed time limit, mending, owner shall have the right to employ others to finish mendin

24、g, and lodge a claim against the contractor.2. 3 payment to designated subcontractors claimIf the contractor has failed to provide the reasonable payment to the designated subcontractor has proved that the owner to the contractor for all designated subcontractor payments paid to the subcontractor. I

25、n addition to the above several kinds of counter claim, due to the fault of the contractor, to the owner party and third party personnel caused personal injury or economic losses, the owner of the claim.Three claims and counter claimsClaims and counter claim is a claim according to the different obj

26、ect and definition, its fundamental purpose is a direction of the other party in contract is the other party liability caused by events, to the other party demands compensation, claim and counter claim must be based on contract, require the events of the real, the proof be definite, charge calculati

27、on is reasonable and accurate, and responsibility analysis to clear, this to the parties to the contract to handle easy to accept, and reduce disputes and disputes.Four ConclusionsConstruction claims and counter claim is the owner and the contractor of the project construction process of normal busi

28、ness between us, its health, to cultivate and develop construction market, promote the development of the construction industry plays a very important role: one is to improve the contract both sides to strengthen internal management, to perform the contract strictly, to maintain the normal market or

29、der. 2 it is conducive to reasonably determine the project cost, make more solid is the fact that the project cost. 3 it is to force the parties to a contract faster familiar with international practice, familiar with claims and claims processing methods and skills, adapt to the situation after Chin

30、as accession to the WTO of the construction market, improve the level of competition in the construction enterprises.Five References1 SheLiZhong compiled. Contract for construction project management M. South China university of technology press, 20232 SheLiZhong; cultivating students engineering co

31、nsciousness and ability of research and claim schedule of Higher building Education, Journal of Architectural Education in the I nstitutions who Learning, 01, 2023FIDIC contract clause3 (international federation of consulting engineers, 1, 1999)4 ShiQing theory of construction claim and counterclaim

32、 management ECONOMIST CHINA ECONOMIST article 第04 period project managers alliance in 20235 Zhang Wei; Li Yingjie claims in terms of the contract analysis example of economic CONSTRUCTION, CONSTRUCTION pa., 1997, 05King 6 Zheng Jibing Zhao Xiuwei, mina project of the construction of the new method:

33、Partnering model (partnership) 01, 20237 Zhang Weidong Wang Xiangqun Song Aidong engineering project risk management present situation and countermeasures of 12, 20238 Li Yonggui theory principle the claim negotiation skills 2023, 17 (11)9 to feel secure, Qian Kun embellish: the construction project contract and claim management, southeast university press, 1993

展开阅读全文
相似文档                                   自信AI助手自信AI助手
猜你喜欢                                   自信AI导航自信AI导航
搜索标签

当前位置:首页 > 环境建筑 > 其他

移动网页_全站_页脚广告1

关于我们      便捷服务       自信AI       AI导航        获赠5币

©2010-2024 宁波自信网络信息技术有限公司  版权所有

客服电话:4008-655-100  投诉/维权电话:4009-655-100

gongan.png浙公网安备33021202000488号   

icp.png浙ICP备2021020529号-1  |  浙B2-20240490  

关注我们 :gzh.png    weibo.png    LOFTER.png 

客服