资源描述
目 录
一、 工程概况··················································2
1、工程概况··················································2
2、配电线路的选择············································2
3、施工用电总容量计算········································4
二、确定线路走向、电源线线径及电箱位置·························5
三、绘制临时供电施工图·········································8
四、安全用电技术措施和电气防火措施·····························8
五、计算书·····················································10
六、安全用电···················································13
七、安全防火及灭火注意事项······································19
八、用电管理及分承包用电管理···································19
九、用电安全责任制·············································21
临时用电施工方案
一、工程概况
1、工程概况
即将兴建的安徽唐汉华章酒业有限公司化验楼工程建筑面积约1755m2,为一栋三层的框架结构的建筑物。檐口高度为12.8.米,长度为48米,宽度为13.7米,合理使用年限50年,抗震设防烈度为6度第三组,耐火等级二级。结构类型为钢筋混凝土框架结构,合理使用年限50年,建筑耐火等级为二级,屋面防水使用年限为10年。
外墙为240厚煤矸石烧结空心砖墙,内隔墙采用200厚煤矸石烧结空心砖墙。
垫层采用C15混凝土,基础为C25,主体混凝土强度等级为C25,二次结构的混凝土等级为C20。由宿州市规划设计研究院进行图纸设计,由宿州市建筑勘察设计院进行地质勘察,由宿州市建筑勘察设计院进行监理,由巢湖水利电力建设有限公司施工。
现场目前的施工用电接驳点由业主提供的一个配电室,现场的材料堆场和加工棚一起考虑,拟建建筑物侧北面设一个临时钢筋木工加工房,以方便材料的垂直运输,减少水平转运距离;现场主要用电设备为施工井架和振动器,电渣压力焊、电弧焊、钢筋机械,木工机械等。
业主提供的是三相五线制电力系统供电(TN-S),在建筑物的前面围墙边设置一级(总)电箱,电箱内设置四线漏电开关(型号:DZ10LE-200/430)、石板闸刀开关(型号:HKT200A/380V)、三相电表(型号:DT862a)、电流互感器(型号:LMK1-0.5),输电线路属架空敷设,输入线径为(25mm2),保护接地线径为(16 mm2),变电装置能满足施工用电需要。
2、配电线路的选择
施工用电由总配电箱提供,又分别向下接出二级箱至钢筋木工房、工程,施工办公室,员工住地等,二级箱往下是个施工机械设备的开关箱(或三级箱)。上述电箱与线路走向之具体位置详见《施工用电平面布置图》。本临时施工用电应采用三相五线制即TN-S接零保护系统,必须实行“三级配电、两级保护”。
工程用电设备清单
序号
设备名称
功率(KW)
单位
数量
总功率(KW)
备 注
1
井架用卷扬机
7.5
台
1
7.5
2
砼输送泵
75
台
1
75
3
砂浆搅拌机
7.5
台
1
7.5
4
直螺纹套丝机
5.5
台
1
5.1
5
插入式振动器
1.1
台
5
5.5
6
平板振动器
1.1
台
2
2.2
7
钢筋切断机
7.5
套
1
7.5
8
钢筋弯曲机
2.8
台
1
2.8
9
钢筋调直机
7.5
台
1
7.5
10
木工圆盘锯
3.0
台
3
9
小计: 电动机总功率: ∑P1=129.5KW
11
电渣压力焊
45 KVA
台
45
12
电弧焊
25KVA
台
2
50
小计: 电焊机总功率: ∑P2=95KVA
13
室内照明
均值6W/平米
平米
400
2.4
小计: 室内照明总功率: ∑P3=2.4KW
14
现场照明
30
小计: 室外照明总功率: ∑P4=30KW
3、施工用电总容量计算
3.1施工用电设备清单(见下页表1):
3.2负荷计算:工程施工需用的用电总容量的∑P可按下式计算:
∑P=1.05(k1∑P1/cosφ+ k2∑P2+ k3∑P3+k4∑P4)
其中:
k1(电动机数大于30台时)=0.50
k2(电焊机为大于10台时)=0.50
k3(室内照明)=0.80
k4(室外照明)=1.00
cosφ(电动机的平均功率因素)=0.75
则: ∑P=1.05(k1∑P1/cosφ+ k2∑P2+ k3∑P3+k4∑P4)
=1.05×[0.5×444/0.75+0.5×480+0.8×8+1.0×10]
=580KVA .
即现场须提供大于上述总容量的变压器或变配电室,选用630 KVA变压器较适宜。
30
二、确定线路走向、电源线线径及电箱位置
1、根据施工现场用电设备布置情况,动力与照明分开,由一级电箱分出2路干线(LFG1、2)架空引至各二级分配电箱,再由分配电箱引至各用电设备的开关箱。
(1)LFG1动力电源由一级电箱输出分左路输到井架边,线路上的负荷由吊笼1台、砂浆机1台、焊机1台、水泵1台、锯木机3台、平板振动器1台、插入式振动器3支等组成。
(2)LFG2动力电源由一级电箱输出供给钢筋加工场,线路上的负荷由钢筋弯切机1台、焊机1台等组成。
(3)照明电源由一级电箱分出,与沿动力电杆架设,引至二级分配电箱后再输出。照明电源不从动力电源分出,即照明电源与动力电源互不影响。
2、据《施工现场临时用电安全技术规范》规定,本供电采用三相五线制供电即(TN-S)系统,采用三级漏电保护制度。
3、配电箱的选择:采用总公司统一规格的各级电箱作配电箱,二级电箱的要求:
(1)箱内设漏电开关(型号:DZ10L-100/3),闸刀开关带保险(型号:HK-100/3)、熔体电流50(A),接线柱(3×100A)组成.
(2)漏电开关的动作电流及动作时间指标分别为(50mA,小于0.1S)。
(3) 二级电箱外壳必须联通保护接地且重复接地。
(4) 各楼层用电考虑施工及敷设方便,宜设在吊笼侧并每层设一个配电箱,由该电箱输出各个流动电箱。
4、级电箱位置及布线原则:
(1)井架式起重机配电箱设在笼架边,便于电源进出线。
(2)砂浆搅拌机位于水泥库旁、笼架的一侧,其配电箱就设在水泥库旁。
(3)弯切机配电箱设在机侧,采用埋地敷线,以便材料进场。
(4)振捣器配电箱应布置在使用地点附近(即流动电箱)。
(5)电焊机为可移动设备,采用回路供电,导线采用橡皮套软电缆。
(6)分配电箱距固定式用电设备距离均不超过3米,距交流弧焊机距离不大于5米,、水泵的距离大于1.5米、小于6米。
现场计划用电量统计表 (附表1)
序号
名 称
功 率
(KW)
数 量
合计功率
(KW)
备 注
1
卷扬机(吊笼)
7.5
1
7.5
2
钢筋弯切机
3.0
1
3
3
锯木机
3
3
9
4
砂浆机
3
1
3
5
电焊机
25
2
50
JC=50%需换算到JC=100%
6
振捣机
2.5
3
7.5
7
平板式振动器
1.1
1
1.1
8
水泵
1.1
1
1.1
9
照明
30
1
30
合计
112.2
5、各支路用电导线截面及电气开关的选择(附件算书)
(1)第一路电线(LFG1):
选择截面的原则:①大部分为动力负荷,按发热条件选择。
查表选线径:相线截面积为25 mm2铜芯线,允许载流量为130(A)、(环境温度35℃)中性线截面为25mm2。
(2) 第二路电线(LFG2):
选择截面的原则:①为动力负荷,按发热条件选择。
查表选线径:相线截面积为16mm2铜芯线,允许载流量为100(A)、(环境温度35℃)中性线截面为10mm2。
(3) 支路引至二级电箱导线截面选择:
查表得:选择16mm2的单支或多股绝缘铜芯导线9BX-3*16),允许载流量为100A,并架空敷设。
(4)二级箱引至三级箱导线截面及箱内电器选择。
A、 5KW以下机械使用
查表得:四芯电缆套管埋地或架空敷设(型号:BX-4*2.5)。或2.5mm2以上单支或多鼓绝缘铜芯线架空敷设。
开关为:闸刀开关带保险(型号:HK1-40/3)其熔体电流3.36-4(A)。
漏电保护器:为三级漏电开关(型号:DZ10L-40/3)。
B、 5KW-12KW机械使用
查表得:四芯电缆套管埋地或架空敷设(型号:BX-4*4)。或4mm2以上单支或多鼓绝缘铜芯线架空敷设。
开关为:闸刀开关带保险(型号:HK-40/3)其熔体电流5-12(A)。
漏电保护器:为三级漏电开关(型号:DZ12L-40/3)。
(4) 三级电箱至电机开关及开关至电机的导线和开关选择
A、 导线
5KW以下机械使用2.5mm2以上的四芯电缆套管埋地或架空敷设。
5KW-12KW机械使用4mm2以上的四芯电缆套管埋地或架空敷设。
B、 开关
吊笼、搅拌机、水泵使用控制电箱按钮开关(控制箱中的交流接触器根据电机功率而定,且不能和开关放在一起)。
锯木机使用密封式开关(禁止使用倒顺及闸刀开关)。
钢筋切铁、拉铁、弯曲机使用倒顺开关(防水、防尘型)。
电焊机、砂轮机使用闸刀开关。
(6) 选择照明线路的导线截面及照明箱内各电气开关
A.假设三相功率不平均分配,按最不利因素考虑,20KW功率全部安装在三相中的一相上,则计算电流为:IJS=Pe/Ue=20/0.22=90.9(A)
查表选择:
导线截面为:单支或多鼓绝缘铜芯线(BX-2*6mm2)。
室内照明导线截面为:2.5mm2以上单支或多鼓绝缘铜芯线,进户时做防水弯头,其架设高度大于或等于2.5(M)。
施工照明及生活照明:采用线径大于或等于2.5mm2的两芯护套线。
一级漏电总开关:三极漏电开关(DZ16L-60/3)。
单相闸刀开关:二极闸刀开关2*30(A)。
二级漏电保护器:二极漏电开关(DZ15L-40/1),其额定漏电动作电流≤30mA,额定动作时间<0.1S。
三级漏电保护器:三极漏电开关(DZ15L-32/1),其额定漏电动作电流≤30mA,额定动作时间<0.1S。
B、 照明线与动力线同杆架设或单独架设,与LFG1同杆,独立供给施工照明、办公室和宿舍照明。
(6)电焊机导线采用三芯橡套软电缆YHH型或YHHR型的规格,焊钳用≥380V*500A且能耐高热的专用焊钳.
(7)照明接零保护线截面:BX-1*6 mm2,与动力线同杆架设。
(8)三级电箱及设备外壳接地采用大于或等于2.5mm2的铜芯线,一、二级电箱外壳接地及重复接地采用大于或等于6mm2的多股铜芯线联接。
三、绘制临时供电施工图
1、 总接线系统图。
2、 施工现场临时用电平面图。
3、 施工用电立面图。
四、安全用电技术措施和电气防火措施
(一)技术措施:
1. 工地的一切用电设备必须由电工接线和管理,不得擅自架设和装电路,电工必须持证上岗,严禁违章操作。
2. 电工在接线、电气设备安装时,应按照施工设计和有关电气安全技术规程进行作业,应正确使用绝缘防护用品和经定期检查校验的绝缘检验工具。电气操作人员严格执行电工操作规程。
3. 电缆架空敷设时,应沿墙壁或电杆设置,并和绝缘子固定,严禁用金属裸线作绑线,室外架空高度不小于3M,室内不小于2.5M。水平沿墙敷放或门口固定最低点不得小于1.8M。
4. 电工人员严禁带电操作,线路上禁止带负荷接线,正确使用电工器具。
5. 电气设备的金属外壳必须做接地、接零保护。
6. 电气设备所用保险丝,禁止用其它金属丝代替,并且需与设备容量相匹配。
7. 凡移动式照明,必须采用安全电压。
8. 施工现场临时用电施工,必须执行施工组织设计和安全操作规程。
9. 开机前认真检查开关箱内的控制开关设备是否齐全有效,漏电保护器是否可靠,方能使用。严禁赤手触摸一切带电绝缘导线。
10. 下班后1小时必须把总电制关好并把电箱门锁上。
11. 电工必须定期检查所有漏电开关是否正常,并认真登记安全生产检查记录。
12. 开关箱距操作者的水平距离不超过3米,按钮开关不能安装在交流接触器一侧。
13. 开关箱内禁止放任何杂物,箱不能堆放沙子、水泥、白灰、水泥袋等,且灌木、杂草要清除干净。
14. 开关箱安装距地面高度为1.3M-1.5M,且安装牢固,要具有防尘、防雨功能。
15. 开关箱必须完整无缺,并配上锁,锁匙由专人保管。
16. 开关箱必须有当心触电的标志。
17. 三级漏电保护开关的额定漏电动作电流应不大于30mA,额定漏电动作时间应小于0.1S。
18. 其余规定参照《施工现场临时用电安全技术规范》JGJ46-2005。
(二)防火措施
1. 在电箱的侧边设置干砂或干粉灭火机。
2. 当发生电火灾时应立即切断电源,用干砂灭火,或和干粉灭火机灭火,严禁使用导电的灭火剂灭火。
3. 电焊机施焊时周围严禁有易燃、易爆物品,并配备灭火器材。
五、计算书
1、计算书中公式符号表示: (附表2)
Pjs
有功功率计算负荷(KW)
Pe
换算后的设备容量 (千瓦KW)
Qjs
无功功率计算负荷(KVar)
Pn
电动机铭牌功率 (千瓦KW)
Sjs
视在功率计算负荷(KVA)
Pes
换算后的额定容量 (千瓦KW)
Ijs
负荷计算电流 (安A)
Ue
线电压 (伏U)
Kx
设备组的需要系数
Φ
相电压与相电流的相角
Jc
铭牌暂载率
Cos,tg,,Kx的系数值通过套表取得
2、各机械组负荷计算:
(1) 提升机组(吊笼) Pjs1、Qjs1
查表:Kx=0.3, COSΦ=0.7, tgΦ=1.02
Pjs1=Kx×Pe=0.3×15=4.5 (KW)
Qjs1=Pjs×tg=4.5×1.02=4.59 (KVar)
(2) 钢筋机、弯切机组
查表:Kx=0.7, COSΦ=0.7, tgΦ=1.02
Pjs=Kx×Pe=0.7×3=2.1 (KW)
Qjs=Pjs×tg=2.1×1.02=2.142 (KVar)
(3) 水泵
查表:Kx=0.7, COSΦ=0.7, tgΦ=1.02
Pjs=Kx×Pe=0.7×4.4=3.08 (KW)
Qjs=Pjs×tg=3.08×1.02=3.14 (KVar)
(4) 电焊机组
查表:Kx=0.45, tgΦ=1.98
A. 先将JC=50%统一换算为JC=100%时的额定容量
Pes= JC ×PN= 0.5 ×60=42.43 (KW)
JC100
B.计算负荷
Pjs=Kx×Pes=0.45×42.43=19.09 (KW)
Qjs=Pjs×tg=19.09×1.98=37.8 (KVar)
(5) 木工机械组
查表:Kx=0.7, tgΦ=0.88
Pjs=Kx×Pe=0.7×9=5.6 (KW)
Qjs=Pjs×tg=5.6×0.88=4.928 (KVar)
(6) 平板式振动组
查表:Kx=0.7, COSΦ=0.7, tgΦ=1.02
Pjs=Kx×Pe=0.7×3.3=2.31 (KW)
Qjs=Pjs×tg=2.31×1.02=2.3562 (KVar)
(7) 振捣棒组
查表:Kx=0.7, COSΦ=0.7, tgΦ=1.02
Pjs=Kx×Pe=0.7×7.5=5.25 (KW)
Qjs=Pjs×tg=5.25×1.02=5.355 (KVar)
(8) 砂灰机组
查表:Kx=0.7, COSΦ=0.68, tgΦ=1.08
Pjs=Kx×Pe=0.7×9=6.3 (KW)
Qjs=Pjs×tg=6.3×1.08=6.804 (KVar)
(9) 照明组
因所有负载不一定同时使用,取Kx=0.7, COSΦ=1, tgΦ=0,并认为照明负荷均匀分配于三相线路中。
Pjs=Kx×Pe=0.7×20=14 (KW)
Qjs=Pjs×tg=0 (KVar)
总计算负荷(取同期系数,Kx=0.9)
Pjs=K∑(Pjs+...+Pjs)=Pjs (提升机组)+Pjs (钢筋机、弯切机组) +Pjs (水泵) +Pjs (电焊机组) +Pjs (木工机械组) +Pjs (平板式振动组) +Pjs (振捣棒组) +Pjs (砂灰机组) +Pjs (照明组)
=0.9×(4.5+2.1+3.08+19.09+5.6+2.31+5.25+6.3+14)
=0.9×62.23=56.007 (KW)
Qjs= K∑(Qjs+...+Qjs)=Qjs (提升机组)+Qjs (钢筋机、弯切机组) +Qjs (水泵) +Qjs (电焊机组) +Qjs (木工机械组) +Qjs (平板式振动组) +Qjs (振捣棒组) +Qjs (砂灰机组) +Qjs (照明组)
=0.9×(4.59+2.142+3.14+37.8+4.928+2.3562+5.355+6.804+0)
=0.9×67.385=60.646(KVar)
Sjs= Pjs2+Qjs2 = 56.0072+60.6462 =82.6 (KW)
3、各干路线上的负荷及电流计算:
第一路线:
计算负荷为K∑=0.9
Pjs=K∑(Pjs+...+Pjs)=0.9×(4.5+6.3+19.09+3.08+5.6+2.31+5.251)=41.52 (KW)
Qjs= K∑(Pjs+...+Pjs)=0.9×(4.59+6.804+37.8+3.14+4.928+2.3562+5.355)=58.48 (KVar)
Sjs= P∑js2+Q∑js2 = 41.522+58.482 =75.99 (KW)
Ijs=Sjs÷ 3 ×Ue=75990÷ 3 ÷380=115.46(A)
第二线路:
Pjs=K∑(Pjs+...+Pjs)=0.9×(2.1+19.09)=21.19 (KW)
Qjs= K∑(Pjs+...+Pjs)=0.9×(2.142+37.8)=35.95 (KVar)
Sjs= P∑js2+Q∑js2 = 21.192+35.952 =41.73 (KW)3
Ijs=Sjs÷ 3 ÷Ue=41730÷ 3 ÷380=63.4(A)
4、 级电箱电流计算
(1) 计算电流(开3至5KW以下)
查表:Kx=1,COSΦ=0.68,
Ijs=Ks×Pe÷ 3÷Ue COSΦ=1×5000÷ 3 ÷380÷0.68=11.17(A)
(2) 计算电流(开3至5KW-12KW)
查表:Kx=1,COSΦ=0.7,
Ijs=Ks×Pe÷ 3÷Ue COSΦ=1×5000÷ 3 ÷380÷0.7=10.85(A)
或1×12000÷ 3 ÷380÷0.7=26.07(A)
(3) 计算电流(各分2至开3)
查表:Kx=0.9,COSΦ=0.7,
①3台5KW以下
Ijs=Ks×Pe×3÷ 3 Ue COSΦ=0.9×5000 ÷ 3 ÷380÷0.7=29.3(A)
②3台5KW-12KW以内
Ijs=Ks×Pe×3÷ 3 Ue COSΦ=0.9×12000×3÷ 3 ÷380÷0.7=70.32(A)
5、电气平面图、接线系统图
见附图1《施工平面布置图》
六、安全用电
6.1外线防护现场踏勘
经过现场踏勘,该工程附近无外电线路,不存在在高低压线周围施工的安全问题。
6.2接地、接零保护系统及防雷保护
6.2.1施工现场专用的中性点直接接地的电力线路中,必须采用TN-S接零保护系统即三相五线制。
6.2.2保护零线应单独敷设,不作它用,保护零线上不得装设开关或熔断器,截面应不小于工作零线截面,同时必须满足机械强度。
6.2.3保护零线在整个电路中,除在工作接地线、配电室线或第一级漏电保护器电源侧的零线引出外,在任何地方不得与工作零线有电气连接,如铁质配电箱中的工作零线端子板和保护线端子板,不能同时直接固定在箱体上,工作零线端子板必须与箱体绝缘,再如塔吊上本来用四芯电缆,照明与设备接零保护共用一根芯线时,必须对此作分离绝缘处理,才能引入保护零线与设备或金属机架相连接。
6.2.4保护零线必须用专用的黄/绿双色线,在任何情况下不准用黄/绿双色线作负荷线。
6.2.5手持工具或移动式用电设备的电源插座上必须具备专用的保护接零触头,所用插头、插座应严格避免导电触头误作接零触头使用,并且设备上的保护零线头不得少于二处,并且不能承受张力。
6.2.6每一接地装置的接地线采用二根以上导线在不同地点与接地装置连接,接地装置做好后,应在未接通零线时,用接地电阻测出电阻值,如达不到要求,在接地体周围土壤中加入煤渣、木炭、炉灰等,同时用食盐水浸入接地体周围土壤。
6.2.7接地体可利用建筑物基础钢筋以及本工地内的自来水管或埋入地下的钢结构构件。
6.3漏电保护器
6.3.1保护零线不得通过漏电保护器,漏电保护器应装设在配电箱电源隔离开关的负荷侧和开关箱电源隔离开关的负荷侧。比较好的配置方式为:隔离开关-漏电保护器-熔断器设备或者自动空气开关-设备。
6.3.2漏电保护器负荷侧和电源侧不能颠倒,一台漏电保护器负荷侧的工作零线不能与其它支路相连,不能就近引用其它支路的工作零线,不能把单相负载跨接在漏电保护器两端。
6.3.3施工用电实现两级保护,即应装设总漏电保护器和开关箱中设备负荷线的始端装设漏电保护器,并应注意上、下级漏电保护器漏电参数的合理配置,实现分级保护。开关箱内漏电保护器的额定漏电动作电流就不大于30mA,额定漏电动作时间应小于0.1S,一般场所的手持式电动工具和露天、潮湿场所或在金属构架上操作时装设的漏电保护器,其漏电动作时间应小于0.1S,额定漏电动作电流应不大于15mA。
6.3.4 36V及其以下的用电设备,如工作环境干燥可免装漏电保护器。
6.4支线架设
6.4.1室外支线明配时必须固定在瓷瓶或瓷柱上,严禁绑在架管、钢筋上,不允许两根线绑在1个瓷瓶上,在易受机械操作、人员流动多,名种料具制作安装活动范围大的场合,不应采用明配方式。
6.4.2室内支线明配时,进户线的室外端应采用绝缘子固定,过墙必须穿管保护,不得低于2.5m,室内采用瓷夹瓷瓶固定。
6.4.3电线穿管敷设时,管内导线不许接头,穿线管进出配电箱必须从箱底穿入箱内,进入其它地方时管口一定要封好,防止雨水进入。电线管明配时,应用管卡固定好,所有管内线完成后应测试相间和对地绝缘强度应不小于0.5Ω。
6.4.4管内导线总面积不超过管径的40%,使用金属管时,三线必须穿入一个管内。
6.4.5电缆干线应采用埋地或架空敷设,严禁沿地面明设。电缆穿越建筑物、构筑物、道路、易受机械操作的场所及引出地面从2m高度至地下0.2m处,必须加设保护套管。
6.4.6导线从电杆上引下,应穿保护管,上端应做成防水弯头,下端一直把管从箱底穿入箱内。
6.4.7电线进、出配电箱一律从箱底并加护套,分路成束并做防水弯,导线束不得与箱体进、出口直接接触。移动式配电箱和开关箱的进出线必须用橡皮绝缘电缆,并不得承受张力。
6.5现场照明
6.5.1照明宜在总配电箱处单独设置照明配电箱,照明干线应采用三相线与工作零线、保护零线同时引出的方式,也可根据工地具体情况,从配电箱内引出,但必须装设照明分路开关,并注意单相照明分相接电,尽量作到三相平衡。
6.5.2职工宿舍、办公室、食堂等室内照明线路应用PVC管或线槽布放,民工宿舍照明,夏季降温电风扇用220V供电但必须穿管,不露线,不设插座,避免乱拉乱接,并定明供送电时间。
6.5.3通道照明、危险场所照明,必须用专用回路,避免相互干扰。
6.5.4施工作业面局部照明灯具的引线必须使用橡皮绝缘电缆,严禁使用其它导线,地下室照明应使用36V安全电压。
6.5.5室外灯具距地面不得低于3m,室内灯具不得低于2.4m,灯具的金属外壳必须作保护接零,电器、灯具的相线必须经开关控制,不得将相线引入灯具。
6.6配电箱和开关箱
6.6.1配电箱和开关箱采用标准电箱,厚度大于1.5mm,箱内电器应安装在金属或绝缘板上,箱体应安装在通风、干燥、常温场所,周围应有足够十人同时工作的空间和通道,不得有妨碍操作的障碍物,配电箱、开关箱的下底与地面距离应大于1.3m,小于1.5m。箱体必须防雨、防尘、配锁,箱内应分设工作零线和保护零线端子,然后分别通过端子板接入用电回路,工作零线端子板必须与箱体之间保护绝缘,端子板一装在箱内配电板的下部或装在箱体内底侧,并应标明“N”、“PE”。
6.6.2配电箱内应采用三级配电两级保护
三级配电:指总配电箱、分配电箱、开关箱三级控制实现分级配电。
两级保护:指开关箱以及其上一级分配电箱(或总配电箱)中必须装设漏电保护器实现至少两级保护。
配电箱、开关箱应有编号、回路标识、适用范畴说明。
6.7配电室
6.7.1配电屏正面的操作通道宽度不小于1.5m,配电屏后面的维护通道宽度不小于0.8m,配电屏侧面的维护通道宽度不小于1m,配电室天棚距地面不低于3m。配电室的门应向外开关配锁,并采取地面绝缘措施。配电屏的上端距天棚不小于0.5M。
6.7.2配电室应能自然通风,并应采取防止雨雪和动物出入的措施。配电室不应设在地势低洼和可能积水场所,并不能有蒸气。
6.8建筑机械和手持电动工具
6.8.1建立和执行专人专机负责制,并定期检查和维修保养。
6.8.2按规定做好接零保护,对产生振动的设备保护零线的连接点不少于两处。
6.8.3在做好接零保护的同时,还要按规定设置符合具体要求的漏电保护器。
6.8.4井架的避雷装置,除应做好保护接零外,还必须按规定做重复接地。
6.8.5每一台电动建筑机械或手持电动工具的开关箱内,除应装设过负荷、短路、漏电保护装置外,还必须装设能在任何情况下都可以使用电设备实行电源隔离的隔离开关。
6.8.6手持电动工具和所有移动式电动建筑机械的负荷线,必须按其容量选用无接头的多股铜芯橡皮护套软电缆,单相时用三芯,三相时用四芯,其截面不得小于1.5mm2(限于手持式电动工具的电缆保护零线,其它应为不小于2.5 mm2)。
6.9防触电措施与触电急救
6.9.1直接接触的防护
6.9.1.1所有的电线、电气设备、控制电器等必须用兆欧表测试绝缘性。
6.9.1.2当不能绝缘处理的地方,必须采用屏护措施,如高、低压线路,露天变压器等。
6.9.1.3人、车辆及其它设施与带电体应保持安全距离,如临时架空线与建筑物外侧或脚手架具外侧边缘的最小安全距离为不小于4m,架空线跨越机动车道时离地面垂直高度不小于6m,线间距离不小于0.3m等。
6.9.1.4在潮湿场所或金属构件上操作应采用安全电压。用电线路均采用二级漏电保护装置。
6.9.2间接接触的防护
采用以下措施自动切断电源:采用自动空气开关、熔断器、漏电保护器及接零、接地保护;用II类绝缘电气设备;采用电气隔离;等位连接。
6.9.3触电急救
6.9.3.1首先使触电者脱离电源,立即就近移到干燥、通风的位置,分别进行现场救护。
6.9.3.2如果触电者伤害不重,神态清醒,但心慌、无力,应让其静卧休息,注意观察并请医生前来或送医院。
6.9.3.3呼吸困难或逐渐微弱,或心脏跳动失常,应立即进行口对口人工呼吸。
七、安全防火及灭火注意事项
7.1规范、标准中对电气设备的安装要求中就包含了防火的要求,我们第一要严格按规定安装,第二要加强维护修理,及时消除火灾隐患。
7.2雷电火灾的防止应安装避雷装置,已安装的要注意维护修理。
7.3静电火灾灭火
7.3.1首先切断电源,再灭火。
7.3.2如果无法及时切断电源时,灭火选择二氧化碳、四氯化碳、二氟一氯一溴甲烷(简称1211)、二氧二溴烷或干粉灭火剂等不导电灭剂,禁止使用泡沫灭火剂,使用水枪带电灭火时,扑救人员应穿绝缘靴,绝缘手套并应将水枪金属喷嘴接地,带电灭火时,现场所有人员应防止电线断电后触及人体以及形成跨步电压。人与带电体就保持安全距离。
7.3.3当火势较大,一时难以扑灭时,应立即通知消防部门,不可延误时机。
八、用电管理及分承包用电管理
8.1搞好安全生产领导是关键,工地项目部应成立项目经理为负责人的安全用电管理小组,配备专职安全管理员,同时要建立项目领导成员轮流安全生产值日制度,解决和生产中的安全问题和进行巡回安全监督检查。
8.2班组是项目的细胞,是搞好安全生产的前沿地,加强安全建设是项目加强安全生产管理的基础。各生产班组要设不脱产安全员,协助班组长搞好安全管理,和班组长一起坚持岗位安全检查,安全值日和班前安全教育制度,同时作好班前安全教育记录,现场维修电工要做好电工维修工作记录。
8.3班组安全用电管理机构图
班 长
班组安全员
中小型设备维修员
临设用电
维修员
大型设备
维修员
现场用电
维修员
8.4“安全第一、预防为主“是建筑施工用电必须遵循的指导方针,施工用电是建筑业容易发生事故的专业,所以我们电气技术人员、安全工作者、广大电工都要坚定不移地贯彻执行这一方针。
8.5建筑施工用电是直接为施工生产服务的,它的好坏直接影响工程的进度和工程质量,又直接影响整个工地职工的安全,所以我们一定要加强施工用电管理,配备一定数量的电气专业技术人员,把施工用电作为安全工作中的一项重要工作来抓。
8.6机电工长、安全员、电工对安全工作负有相应的责任,要建立起各自的安全用电责任制。
九、用电安全责任制
9.1机电工长安全责任制
9.1.1负责临时用电的施工组织、管理、布置、安排检查、验收。
9.1.2负责临时用电变更设计的编制、申报工作。
9.1.3负责安装、维修或拆除临时用电工程,并按工程的难易和技术复杂性安排相应电工处理。
9.1.4负责临时用电技术档案的管理,负责单项用电的技术交底。
9.1.5参与定时定期对临电进行巡回监督检查,解决和处理临电中的安全问题。
9.1.6负责对电工的培训、考核和安全教育工作。
9.1.7负责分承包方临时用电的审批和安排引电工作。
9.2安全员安全责任
9.2.1负责日常和定期对临时用电的安全巡回检查工作。
9.2.2参与临电施工的安全监督、围护、监护工作,及组织检查、验收工作。
9.2.3组织参与对电工、用电人员的安全培训和教育工作。
9.2.4负责检查班组安全活动和有关记录。
9.2.5负责对分承包临时用电的安全检查。
9.3电工安全责任制
9.3.1负责临时用电的具体施工工作,正确使用电气安全用品。
9.3.2了解所安装设备的电气要求,正确安装调试设备。
9.3.3掌握相应环境条件下设备、电器的选型、运行、维修的安全技术要求。
9.3.4掌握照明装置、日用电器,移动电器、手持式电动工具及临时供电线路的安装、运行、检查、维护的安全技术。
9.3.5掌握电工作业的登高、机械、起重、搬运、焊接等作业的安全技术。
9.3.6掌握本岗位电气系统接线图、设备编号、运行方式、操作步骤和事故处理程序。
9.3.7掌握调度管理要求和用电管理制度。
9.3.8掌握本岗位的现场运行规程和操作票制度,操作维护制度,巡回检查制度,交接班制度。
9.3.9掌握电工作业中保证安全的组织措施和技术措施。
下面为附送毕业论文致谢词范文!不需要的可以编辑删除!谢谢!
毕业论文致谢词
我的毕业论文是在韦xx老师的精心指导和大力支持下完成的,他渊博的知识开阔的视野给了我深深的启迪,论文凝聚着他的血汗,他以严谨的治学态度和敬业精神深深的感染了我对我的工作学习产生了深渊的影响,在此我向他表示衷心的谢意
这三年来感谢广西工业职业技术学院汽车工程系的老师对我专业思维及专业技能的培养,他们在学业上的心细指导为我工作和继续学习打下了良好的基础,在这里我要像诸位老师深深的鞠上一躬!特别是我的班主任吴廷川老师,虽然他不是我的专业老师,但是在这三年来,在思想以及生活上给予我鼓舞与关怀让我走出了很多失落的时候,“明师之恩,诚为过于天地,重于父母”,对吴老师的感激之情我无法用语言来表达,在此向吴老师致以最崇高的敬意和最真诚的谢意!
感谢这三年来我的朋友以及汽修0932班的四十多位同学对我的学习,生活和工作的支持和关心。三年来我们真心相待,和睦共处,不是兄弟胜是兄弟!正是一路上有你们我的求学生涯才不会感到孤独,马上就要各奔前程了,希望(,请保留此标记。)你们有好的前途,失败不要灰心,你的背后还有汽修0932班这个大家庭!
最后我要感谢我的父母,你们生我养我,纵有三世也无法回报你们,要离开你们出去工作了,我在心里默默的祝福你们平安健康,我不会让你们失望的,会好好工作回报社会的。
致谢词2
在本次论文设计过程中,感谢我的学校,给了我学习的机会,在学习中,老师从选题指导、论文框架到细节修改,都给予了细致的指导,提出了很多宝贵的意见与建议,老师以其严谨求实的治学态度、高度的敬业精神、兢兢业业、孜孜以求的工作作风和大胆创新的进取精神对我产生重要影响。他渊博的知识、开阔的视野和敏锐的思维给了我深深的启迪。这篇论文是在老师的精心指导和大力支持下才完成的
感谢所有授我以业的老师,没有这些年知识的积淀,我没有这么大的动力和信心完成这篇论文。感恩之余,诚恳地请各位老师对我的论文多加批评指正,使我及时完善论文的不足之处。
谨以此致谢最后,我要向百忙之中抽时间对本文进行审阅的各位老师表示衷心的感谢。
开学自我介绍范文:首先,我想说“荣幸”,
展开阅读全文