土木工程施工课程设计
专业:
姓名:
班级:
学号:
导师:
时间:
目录
第一章 工程概况····················································1
一、建筑、结构概况···············································1
二、施工条件概况·················································1
第二章 工程量计算··················································
一、土方工程量····················································
二、基础工程工程量················································
三、柱工程量······················································
四、梁工程量······················································
五、楼梯工程量····················································
六、预制板工程量··················································
七、工程量清单表··················································
第三章 施工方案····················································
一、施工段划分····················································
二、工期控制······················································
三、施工次序······················································
四、施工工艺······················································
五、施工方法·····················································
六、施工时间·····················································
七、模板方案·····················································
第四章 机械设备选择················································
第五章 关键技术方法················································
第六章 施工总平面图··············································
第七章 施工进度计划表···········································
第一章 工程概况
一、建筑、结构概况
建筑设计特点:本工程为某无线电厂生产车间,总体呈矩形分布,建筑物总高16.90m,总长54.30m,总宽21.3m;共四层,首层层高为4.5m,二、三标准层层高均为4.2m,顶层层高4.0m,屋顶为平屋顶。
结构设计特点:本工程采取钢筋混凝土框架结构,框架柱统一截面尺寸为400mm×450mm,梁截面300mm×400mm、300mm×500mm和300mm×600mm等,楼面铺设180mm厚预应力钢筋混凝土空心板。采取柱下独立基础,尺寸均为2050mm×2050mm,阶梯形;基础埋深为2.0m,下设100厚混凝土垫层;采取现浇混凝土板式楼梯;室外设计地坪标高为-0.45m。
二、施工条件概况
地形:平坦
土质:亚粘土
雨季:4-6月份
地下水位:最高地下水位在地面以下2.0m
开工时间:7月8日
施工工期:275天(依据施工定额)
钢筋:由加工厂加工成型后运至现场。
混凝土:采取商品混凝土,水电由市区供给。
交通:厂内可通行车辆
材料:建筑材料齐全,技术力量雄厚,劳动力由企业工程处统一调配。
第二章 工程量计算
依据施工段划分标准,每层分两个施工段,分界线在5号轴线柱右侧。取1~5轴基础层为第1施工段,6~10轴基础层为第2施工段,其它层依次类推。
一、土方工程量
依据土类别取基坑放坡系数为0.5。
基础尺寸:2.05m×2.05m。
下底:(四面考虑0.3m工作面)。
上底:。
采取机械挖土,考虑到基坑开挖尺寸及运输车辆进出,选择采取条形开挖;不考虑地基梁所需挖土土方量。
(1)、开挖工程量
第1施工段:
[(3×6+0.15+1.025+0.1+0.3)+(4×6+0.15+1.025+
0.1+0.3)×2+(3.75+1.025+0.1+0.3-1.325)+(6+1.025+0.1+0.3)×2]××(2.1-0.45)×(2.65+4.3)=512.74
第2施工段:
[(5×6-0.15+1.025+0.1+0.3)×3]××(2.1-0.45)×(2.65+4.3)=538
(2)、填方工程量
a、基础回填:
第1施工段:
512.74-41.51-18×[(1.2-0.45)×0.45×0.45+2.25×2.25×0.1]=459.38
第2施工段:
538-34.59-15×[(1.2-0.45)×0.45×0.45+2.25×2.25×0.1]=493.54
b、房心回填:
第1施工段:
[(6-0.3)×(7.5-0.3)×7+(6-0.3)×(3.75-0.3)+(6-0.3)×(6-0.3)×2]×0.45=167.4
第2施工段:
(6-0.3)×(7.5-0.3)×10×0.45-0.3×0.4×(6-0.3)
=184.0
二、基础工程工程量
(1)、基础混凝土工程量
第1施工段:
18×(2.05×2.05×0.4+1.25×1.25×0.4)=41.51
第2施工段:
15×(2.05×2.05×0.4+1.25×1.25×0.4)=34.59
(2)、基础钢筋工程量
第1施工段:
41.51×36=1.5t
第2施工段:
34.59×36=1.25t
(3)、基础模板工程量
第1施工段:
18×(2.05×4+1.25×4)×0.4=95.04
第2施工段:
15×(2.05×4+1.25×4)×0.4=79.2
(4) 垫层混凝土量
第1施工段:
2.07×0.1×[19.275+25.275×2+3.55+7.125×2]
=18.14
第2施工段:
2.07×0.1×([(5×6-0.15+1.025+0.1)×3]
=19.24
三、 柱工程量
(1)柱混凝土工程量
第1施工段:
01050001 18×0.4×0.45×(4.5+1.2)+0.2×0.3×(4.5+0.2)
=18.75
第2施工段:
01050002 15×0.4×0.45×(4.5+1.2)+0.25×0.3×(4.5+0.2)×2=16.1
第3、5施工段:
01050003 18×0.4×0.45×4.2+0.2×0.3×4.2=13.86
01050005 18×0.4×0.45×4.2+0.2×0.3×4.2=13.86
第4、6施工段:
01050004 15×0.4×0.45×4.2+0.25×0.3×4.2×2=11.97
01050006 15×0.4×0.45×4.2+0.25×0.3×4.2×2=11.97
第7施工段:
01050007 18×0.4×0.45×4.0+0.2×0.3×4.0=13.2
第8施工段:
01050008 15×0.4×0.45×4.0+0.25×0.3×4.0×2=11.4
(2) 柱钢筋工程量
18.75×130/1000=2.44t
16.1×130/1000=2.1t
13.86×130/1000=1.8t
11.97×130/1000=1.56t
13.86×130/1000=1.8t
11.97×130/1000=1.56t
13.2×130/1000=1.72t
11.4×130/1000=1.48t
(3) 柱模板工程量
第1施工段:
18×(0.4+0.45)×2×(4.5+1.2)+(0.2+0.3)×2×(4.5+0.2)=179.12
第2施工段:
15×(0.4+0.45)×2×(4.5+1.2)+(0.25+0.3)×2×2×(4.5+0.2)=155.69
第3、5施工段:
18×(0.4+0.45)×2×4.2+(0.2+0.3)×2×4.2=132.72
18×(0.4+0.45)×2×4.2+(0.2+0.3)×2×4.2=132.72
第4、6施工段:
15×(0.4+0.45)×2×4.2+(0.25+0.3)×2×2×4.2=116.34
15×(0.4+0.45)×2×4.2+(0.25+0.3)×2×2×4.2=116.34
第7施工段:
18×(0.4+0.45)×2×4.2+(0.2+0.3)×2×4.0=132.52
第8施工段
15×(0.4+0.45)×2×4.0+(0.25+0.3)×2×2×4.0=110.8
四、 梁工程量
(1)梁混凝土工程量
第1施工段:
基础梁:
7×0.3×0.5×(6-0.4)+0.3×0.5×(6-0.2-0.15)+2×0.3×0.5×(6-0.45)+0.3×0.5×(7.5-0.45)+0.3×0.5×(3.75-0.45)+0.3×0.6×(7.5-0.45)+6×0.3×0.4×(6-0.4)+0.3×0.4×(6-0.45)+7×0.3×0.4×(7.5-0.45)=21.85
首层梁:
01050300 矩形梁[(6+7.5+3.75-3×0.45)+(7.5×2+6-3×0.45-0.25)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×0.3×0.8+(6-0.3)×0.2×0.4=17.03
异形梁[(24-4×0.4)×(0.25×0.5+0.2×0.18)]+[(6×6-6×0.4)×(0.25×0.32+0.18×0.45)]+[(4×6-4×0.4)×(0.25×0.5+0.2×0.18)]=12.86
第2施工段:
基础梁:
8×0.3×0.5×(6-0.4)+2×0.3×0.5×(7.5-0.45)+2×0.3×0.6×(7.5-0.45)+6×0.3×0.4×(6-0.4)+6×0.3×0.4×(7.5-0.45)=16.86
首层梁:
矩形梁[2×(7.5×2-2×0.45)+2×(7.5×2-2×0.45-2×0.2)+(7.5×2-2×0.45)]×0.3×0.8+(6-0.3)×0.2×0.4=17.18
异形梁[(30-5×0.4)×(0.25×0.5+0.2×0.18)]+[(5×6-5×0.4)×(0.25×0.32+0.18×0.45)]+[(5×6-5×0.4)×(0.25×0.5+0.2×0.18)]=13.53
第3、5施工段:
/51 矩形梁[(6+7.5+3.75-3×0.45)+(7.5×2+6-3×0.45-0.25)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×0.3×0.8+(6-0.3)×0.2×0.4=17.03
/51 异形梁[(24-4×0.4)×(0.25×0.5+0.2×0.18)]+[(6×6-6×0.4)×(0.25×0.32+0.18×0.45)]+[(4×6-4×0.4)×(0.25×0.5+0.2×0.18)]=12.86
第4、6施工段:
/61 矩形梁[2×(7.5×2-2×0.45)+2×(7.5×2-2×0.45-2×0.2)+(7.5×2-2×0.45)]×0.3×0.8+(6-0.3)×0.2×0.4=17.18
/61 异形梁[(30-5×0.4)×(0.25×0.5+0.2×0.18)]+[(5×6-5×0.4)×(0.25×0.32+0.18×0.45)]+[(5×6-5×0.4)×(0.25×0.5+0.2×0.18)]=13.53
第7施工段:
矩形梁[(6+7.5+3.75-3×0.45)+(7.5×2+6-3×0.45)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×0.3×0.7+[(24-4×0.4)×0.25×0.5]+[(6×6-6×0.4)×(0.25×0.5]+[(4×6-4×0.4)×0.25×0.5]=24.35
第8施工段:
矩形梁5×(7.5×2-2×0.45)×0.3×0.7+[(30-5×0.4)×0.25×0.5]+[(5×6-5×0.4)×0.25×0.5]+[(5×6-5×0.4)×0.25×0.5]=25.31
(2) 梁钢筋工程量
(21.85+12.86)×115/1000+17.03×150/1000=6.55t
(16.86+13.53)×115/1000+17.18×150/1000=6.07t
12.86×115/1000+17.03×150/1000=4.03t
13.53×115/1000+17.18×150/1000=4.14t
12.86×115/1000+17.03×150/1000=4.03t
13.53×115/1000+17.18×150/1000=4.14t
14.55×150/1000+9.8×115/1000=3.31t
14.81×150/1000+10.50×115/1000=3.43t
(3)梁模板工程量
第1施工段:
基础梁7×0.5×2×(6-0.4)+0.5×2×(6-0.2-0.15)+2×0.5×2×(6-0.45)+0.5×2×(7.5-0.45)+0.5×2×(3.75-0.45)+2×0.6×(7.5-0.45)+6×0.4×2×(6-0.4)+0.4×2×(6-0.45)+7×0.4×2×(7.5-0.45)=146.96
矩形梁[(6+7.5+3.75-3×0.45)+(7.5×2+6-3×0.45-0.25)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×(0.3+0.8×2)+(6-0.3)×(0.2+0.4×2)=136.90
01170301 异形梁[(24-4×0.4)×(0.5+0.25+0.32+0.2+0.18)
]+[(6×6-6×0.4)×(0.18+0.1+0.32+0.25+0.32+0.1+0.18)]+[(4×6-4×0.4)×(0.18+0.2+0.32+0.25+0.5)]=113.68
第2施工段:
基础梁8×0.5×2×(6-0.4)+2×0.5×2×(7.5-0.45)+2×0.6×2×(7.5-0.45)+6×0.4×2×(6-0.4)+6×0.4×2×(7.5-0.45)=136.54
矩形梁[2×(7.5×2-2×0.45)+2×(7.5×2-2×0.45-2×0.2)+(7.5×2-2×0.45)]×(0.3+0.8×2)+(6-0.3)×(0.2+0.4×2)=160.93
01170301 异形梁[(30-5×0.4)×(0.5+0.25+0.32+0.2+0.18)
]+[(5×6-5×0.4)×(0.18+0.1+0.32+0.25+0.32+0.1+0.18)]+[(5×6-5×0.4)×(0.18+0.2+0.32+0.25+0.5)]=121.8
第3、5施工段:
/5 矩形梁[(6+7.5+3.75-3×0.45)+(7.5×2+6-3×0.45-0.25)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×(0.3+0.8×2)+(6-0.3)×(0.2+0.4×2)=136.90
01170301/5 异形梁[(24-4×0.4)×(0.5+0.25+0.32+0.2+0.18)
]+[(6×6-6×0.4)×(0.18+0.1+0.32+0.25+0.32+0.1+0.18)]+[(4×6-4×0.4)×(0.18+0.2+0.32+0.25+0.5)]=113.68
第4、6施工段:
/6 矩形梁[2×(7.5×2-2×0.45)+2×(7.5×2-2×0.45-2×0.2)+(7.5×2-2×0.45)]×(0.3+0.8×2)+(6-0.3)×(0.2+0.4×2)=160.93
01170301/6 异形梁[(30-5×0.4)×(0.5+0.25+0.32+0.2+0.18)
]+[(5×6-5×0.4)×(0.18+0.1+0.32+0.25+0.32+0.1+0.18)]+[(5×6-5×0.4)×(0.18+0.2+0.32+0.25+0.5)]=121.8
第7施工段:
矩形梁[(6+7.5+3.75-3×0.45)+(7.5×2+6-3×0.45)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×(0.3+2×0.7)+[(24-4×0.4)×(0.25+2×0.5)]+[(6×6-6×0.4)×(0.25+2×0.5)]+[(4×6-4×0.4)×(0.25+2×0.5)]=218.51
第8施工段:
矩形梁5×(7.5×2-2×0.45)×(0.3+2×0.7)+[(30-5×0.4)×(0.25+2×0.5)]+[(5×6-5×0.4)×(0.25+2×0.5)]+[(5×6-5×0.4)×(0.25+2×0.5)]=224.85
五、 楼梯工程量
(1) 楼梯混凝土工程量
现浇楼梯3×2×(6-0.3)×(3.75-0.325)×0.2
=23.43
(2) 楼梯钢筋工程量
现浇楼梯23.43×55/1000=1.29t
(3) 楼梯模板工程量
现浇直型3×2×(6-0.3)×(3.75-0.325)=117.14
六、 预制板工程量
(1)预制板混凝土工程量
01051200 YKB6062:4×72×0.34=97.92
01051002 YKB6092:4×90×0.455=163.8
第1施工段:
YKB6062:32
YKB6092:44
第2施工段:
YKB6062:40
YKB6092:46
(2)预制板钢筋工程量
后张法YKB6062钢筋:4×72×17.18/1000=4.95t
后张法YKB6092钢筋:4×90×24.23/1000=8.73t
七、 工程量清单表
表一:土方工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
第1施工段挖方
亚粘土
1.65m
512.74
2
第2施工段挖方
亚粘土
1.65m
538
3
第1施工段基础回填
亚粘土、原土及郊区运来
459.38
4
第2施工段基础回填
亚粘土、原土及郊区运来
493.54
5
第1施工段房心回填
亚粘土、原土及郊区运来
167.4
6
第2施工段房心回填
亚粘土、原土及郊区运来
184
表二:基础工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
第1施工段基础混凝土
基础高0.8m
阶梯形
41.51
3
2
第2施工段基础混凝土
基础高0.8m
阶梯形
34.59
2.5
3
第1施工段基础钢筋
螺纹钢
t
1.5
0.5
4
第2施工段基础钢筋
螺纹钢
t
1.25
0.5
5
第1施工段基础模板
基础高0.8m
阶梯形
95.04
装10.5
拆4
6
第2施工段基础模板
基础高0.8m
阶梯形
79.2
装9
拆3.5
7
第一施工段基础垫层
C15
厚10
18.14
1.5
8
第二施工段基础垫层
C15
厚10
19.24
1.5
表三:柱工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
第1施工段柱砼
矩形柱
一般砼
18.75
3.5
2
第2施工段柱砼
矩形柱
一般砼
16.1
3
3
第3施工段柱砼
矩形柱
一般砼
13.86
2.5
4
第4施工段柱砼
矩形柱
一般砼
11.97
2
5
第5施工段柱砼
矩形柱
一般砼
13.86
2.5
6
6
第6施工段柱砼
矩形柱
一般砼
11.97
2
7
第7施工段柱砼
矩形柱
一般砼
13.2
2.5
8
第8施工段柱砼
矩形柱
一般砼
11.4
2
9
第1施工段柱钢筋
螺纹钢
t
2.44
1
10
第2施工段柱钢筋
螺纹钢
t
2.1
1
11
第3施工段柱钢筋
螺纹钢
t
1.8
0.5
12
第4施工段柱钢筋
螺纹钢
t
1.56
0.5
13
第5施工段柱钢筋
螺纹钢
t
1.8
0.5
14
第6施工段柱钢筋
螺纹钢
t
1.56
0.5
15
第7施工段柱钢筋
螺纹钢
t
1.72
0.5
16
第8施工段柱钢筋
螺纹钢
t
1.48
0.5
17
第1施工段矩形柱
400×450、
250×300
179.12
装29
拆8.5
18
第2施工段矩形柱
400×450、
250×300
155.69
装25.5
拆7
19
第3施工段矩形柱
400×450、
250×300
132.72
装21.5
拆6
20
第4施工段矩形柱
400×450、
250×300
116.34
装19
拆5.5
21
第5施工段矩形柱
400×450、
250×300
132.72
装21.5
拆6
22
第6施工段矩形柱
400×450、
250×300
116.34
装19
拆5.5
23
第7施工段矩形柱
400×450、
250×300
132.52
装21.5
拆6
24
第8施工段矩形柱
400×450、
250×300
110.8
装18
拆5
表四:梁工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
第1施工段基础梁砼
一般砼
21.85
4.5
2
第1施工段矩形梁砼
一般砼
17.03
3
第1施工段异形梁砼
一般砼
12.86
4
第2施工段基础梁砼
一般砼
16.86
4.6
5
第2施工段矩形梁砼
一般砼
17.18
6
第2施工段异形梁砼
一般砼
13.53
7
第3施工段矩形梁砼
一般砼
17.03
3
8
第3施工段异形梁砼
一般砼
12.86
9
第4施工段矩形梁砼
一般砼
17.18
3
10
第4施工段异形梁砼
一般砼
13.53
11
第5施工段矩形梁砼
一般砼
17.03
3
12
第5施工段异形梁砼
一般砼
12.86
13
第6施工段矩形梁砼
一般砼
17.18
3
14
第6施工段异形梁砼
一般砼
13.53
15
第7施工段矩形梁砼
一般砼
24.35
2.5
16
第8施工段矩形梁砼
一般砼
25.31
2.5
17
第1施工段钢筋量
螺纹钢
t
6.55
3
18
第2施工段钢筋量
螺纹钢
t
6.07
2.5
19
第3施工段钢筋量
螺纹钢
t
4.03
2
20
第4施工段钢筋量
螺纹钢
t
4.14
2
21
第5施工段钢筋量
螺纹钢
t
4.03
2
22
第6施工段钢筋量
螺纹钢
t
4.14
2
23
第7施工段钢筋量
螺纹钢
t
3.31
1.5
24
第8施工段钢筋量
螺纹钢
t
3.43
1.5
25
第1施工段基础模板
钢模、木模
146.96
装60
拆21
26
第1施工段矩形模板
钢模、木模
136.90
27
第1施工段异形模板
钢模、木模
113.68
28
第2施工段基础模板
钢模、木模
136.54
装63
拆22
29
第2施工段矩形模板
钢模、木模
160.93
30
第2施工段异形模板
钢模、木模
121.8
31
第3施工段矩形模板
钢模、木模
113.68
装41.5
拆14.5
32
第3施工段异形模板
钢模、木模
136.54
33
第4施工段矩形模板
钢模、木模
160.93
装42.5
拆15
34
第4施工段异形模板
钢模、木模
121.8
35
第5施工段矩形模板
钢模、木模
113.68
装41.5
拆14.5
36
第5施工段异形模板
钢模、木模
136.54
37
第6施工段矩形模板
钢模、木模
160.93
装42.5
拆15
38
第6施工段异形模板
钢模、木模
121.8
39
第7施工段矩形模板
钢模、木模
218.51
装33
拆11.5
40
第8施工段矩形模板
钢模、木模
224.85
装34
拆12
表五:楼梯工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
现浇直型楼梯砼
一般砼
23.43
5
2
现浇直型楼梯钢筋
螺纹钢
t
1.29
1
3
现浇直型楼梯模板
钢模、木模
117.14
装113
拆13.5
表六:预制板工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
YKB6062h砼量
一般砼
97.92
9.5
2
YKB6092砼量
一般砼
163.8
15.5
3
YKB6062钢筋
后张法螺纹钢、钢绞线
t
4.95
1.5
4
YKB6092钢筋
后张法螺纹钢、钢绞线
t
8.73
2.5
5
A1
第1/3/5/7施工段
YKB6062数量
块
32
1台班
6
A2
第2/4/6/8施工段
YKB6062数量
块
40
1台班
7
B1
第1/3/5/7施工段
YKB6062数量
块
44
1台班
8
B2
第2/4/6/8施工段
YKB6062数量
块
46
1台班
第三章 施工方案
针对该工程工期紧、结构体系复杂、工程量大、工序交叉多、场地狭窄、环境制约等特点,在确保工程质量和安全生产前提下,应以工期为主导,精心组织、合理安排,充足利用有效时间和空间,采取优异施工工艺,确保整个工程准期完成目标。施工方案选择以下:
1、钢筋工程:钢筋由专员统一计划配料,钢筋由专门钢筋加工车间加工,现场钢筋连接分别采取绑扎接头搭接,电渣压力焊、双面搭接焊等施工工艺。
2、模板工程:基础承台及地梁、墙、梁、楼梯模板采取胶合板模板和钢模板。
3、砼工程:砼全部采取预拌商品砼,由场外砼搅拌站供给,用砼搅拌运输车运至现场,砼泵送车输送砼。
4、地面以上主体结构工程施工部署:
地面以上主体结构工程支模和钢筋绑扎同时进行,在钢筋加工、砼浇筑方面进行流水作业。模板拟采取18厚木模板配制,支撑采取门字架搭设。外脚架采取落地式钢管脚手架。
5、施工机械:工程现场设置1台提升架,以供垂直运输。
一、施工段划分
依据施工段划分标准,每层分两个施工段,分界线在5号轴线柱右侧。取1~5轴基础层为第1施工段,6~10轴基础层为第2施工段,其它层依次类推。
二、 工期控制
(1)、计划编制标准
依据总施工布署和总体施工方案安排,编制工程进度计划时以基础、主体及外墙装饰为主,利用好每一天工作时间,分区组织施工,分段流水作业,来确保工程工期要求,全方面地完成此次招标范围内工程项目,让建设单位满意。
(2)、施工进度计划
计划开工日期:7月8日
计划完工日期:4月8日
总工期:275日历天
三、施工次序
1、总体施工次序:
基础工程→主体框架结构→砌筑围护结构→内外墙装修→水电安装、防雷测试→完工验收。
2、各阶段施工次序安排:
基础阶段:±0.00以下基础(包含地面砼板)。
测量放线→基坑开挖、修边、检底、排水→承台砼垫层→放线→承台、地梁→回填土→承台、地梁钢筋安装绑扎→浇砼。
主体阶段阶段:±0.00以上主体结构施工。
绑扎柱筋→隐蔽验收→安装柱模板、梁板模板→浇柱砼→绑扎梁板钢筋→隐蔽验收→浇梁板砼→下一楼层施工段施工。砌砖、室内装修施工随主体进度插入施工。
装饰阶段:内外装饰。
内装饰施工程序为:顶棚→墙面→楼地面。
外墙面装饰为:外墙全高吊垂直线,逐层弹出水平控制线→做灰饼、冲筋→找平层抹灰→安装门窗框→贴外墙面砖。
完工阶段:室内外清理、完工验收
四、 施工工艺、施工方法
1、工程测量
(一)测量任务
依据施工要求,经过测量工作定位、放线,将建筑物平面位置和高程测定到施工作业面上,为模板安装、墙体砌筑和预埋安装提供依据。遵照先整体后局部、先高精度控制后分测工作程序。
(二)测量准备
熟悉和校对图纸,掌握定位依据,熟悉移交水准点、轴线、标高位置和数据。测量仪器选择及检定、校验。
(三)、平面轴线控制网布设
确保轴线测量正确性,工程轴线测量将由专业测量小组完成。定位测量工作完成后,项目部施工技术责任人会同工程处技术质量科、测量责任人,进行轴线闭合,轴线复核验收后,绘图通知建设单位组织相关单位现场验线,并办理签证手续。确定无误后,方可进行土方开挖施工。
2、土方工程
(一)土方开挖施工准备
1、在基槽开挖之前,场内全部红线桩及建筑物定位桩全部经计划部门测量核准,一经校实后,项目部就落实专员对其进行定时检验复核,以确保测量桩红线点正确性。
2、边坡确定:在基槽开挖前,依据建设方提供地质资料及周围工程施工经验,经过国家规范及各工程施工资料参考,确定土方开挖放坡,坡度暂定1:0.5。
(二)土方回填质量确保方法
1、填土由下而上分层铺填,每层土虚铺厚度小于25cm,分层压实后厚度不得大于20cm。
2、确保土含水率在最优含水量范围,土料含水量通常从手握成团,落地开花为宜。
3、主体结构工程
施工程序:定位放线→柱布绑扎→立柱模→顶撑排架→支梁模板→梁板扎筋→梁板柱砼→水电预埋
3.1、模板工程施工
1、柱模板:
矩形柱模采取胶合板和50×100mm木枋,依据截面尺寸配制成定尺模板,柱边长800mm时采取3道坚向背枋。当边长增加(降低)300mm时,则背枋增加(降低)1根,柱包箍采取Ф48钢管和Ф12螺杆组成。柱包箍上、下端两道距顶面和楼面为250mm。其中间距为500mm,为确保柱模侧向刚度,四面用活动钢管顶撑顶牢,层高超出4.0m柱模支立搭成井字型排架稳固。当柱边长达700mm以上,每增加200mm时,每边中间增加一道Ф12钢筋拉杆(竖向全长排列)。
2、梁板模:
配二套模板,翻转使用,中途对损坏模板陆续补充。支撑采取门式脚手架。
(1)在柱模上弹出梁轴线及水平线并复核。
(2)在安装梁模支架前,首层支撑系统,在专用支柱下脚要铺设通长脚手板,而且楼层间上下支座应在一条直线上,支柱通常采取双排。支柱中间和下方加横杆或斜杆,立杆可调底座。
(3)在支柱上调整预留梁底模板厚度,符合设计要求后,拉线安装梁底模板并找直。
(4)在底模上绑扎钢筋,经检验合格后,清除杂物,安装梁侧模板,用铁钉钉牢,并钉上下锁口楞及外竖楞,附以斜撑。
3、拆模:
严格控制拆模时间,常温下柱模板要求拆除时强度大于1.2MPa,即混凝土浇筑完成12h左右。顶板模板拆除必需待同条件养护混凝土试块达成设计强度75%~100%。
3、2、钢筋工程
1、钢筋加工
(1)钢筋加工形状、尺寸必需符合设计要求。钢筋表面应洁净、无损伤,油渍、漆污和铁锈等应在使用前清除洁净,带有粒状和片状锈钢筋不得使用。
(2)在施工过程中出现钢筋代换时,必需经设计部门及甲方、监理单位认可后,由项目工程师签发核定单,方能代换,其它人无权决定。
2、钢筋绑扎
柱钢筋绑扎
(1)画箍筋间距线:在立好柱子竖向钢筋上,按图纸要求用粉笔划箍筋间距线。
(2)柱箍筋绑扎
1)按已划好箍筋位置线,将已套好箍筋往上移动,由上往下绑扎,宜采取缠扣绑扎。
2)箍筋和主筋要垂直,箍筋转有处和主筋交点均要绑扎,主筋和箍筋非转角部分相交点成梅花交错绑扎。
3)箍筋弯钩叠合处应沿柱子竖筋交错部署,并绑扎牢靠。
4)柱上下两端箍筋应加密,加密区长度及加密区内箍筋间距应符合设计图纸要求。如设计要求箍筋设拉筋时,拉筋应钩应箍筋。
梁钢筋绑扎
(1)在梁侧模板上画出箍筋间距,摆放箍筋。
(2)先穿主梁下部纵向受力钢筋及弯起钢筋,将箍筋按已画好间距逐一分开;穿次梁下部纵向受力钢筋及弯起钢筋并套好箍筋;放主次梁架立筋;隔一定间距将架立筋和箍筋绑扎牢靠;调整箍筋间距使间距符合设计要求,绑架立筋,再绑主筋,主次梁同时配合进行。
3、钢筋连接:
钢筋电渣压力焊接头焊接工艺步骤
焊接准备(试焊、调整焊接参数,并送试验室检验合格)→钢筋扶正对位→紧固夹具→放引弧铅丝→填石棉垫→焊剂入盒→通电引弧→造渣过程→断电顶锻→拆夹钳→等候→拆焊剂盒→等候→法渣壳
3.3砼工程施工
1、砼浇筑:
本工程混凝土浇筑采取梁和柱分开浇筑方案进行施工。
2、砼养护:
在砼结构施工过程中,现场派专职养护工,对已经浇筑砼进行养护。
竖向结构柱砼采取无水养生