某住宅小区智能化系统
施工组织设计方案书
The Project Plan for XXX Housing Intelligent System
目录
1 编制说明....................................................................5
1.1 编制原则..............................................................5
1.2 关于施工工期及范围....................................................5
1.3 关于工程进度..........................................................5
1.4 备注说明..............................................................5
2 编制依据....................................................................6
3 工程概况....................................................................7
4 业主的配合条件..............................................................9
4.1 施工前的配合要求......................................................9
4.2 施工期间的协调工作....................................................9
4.3 不可预见的协调........................................................9
5 总体施工方案...............................................................10
5.1 总体施工方案.........................................................10
5.1.1 基础工程.......................................................10
5.1.2 设备安装调试工程...............................................15
5.1.3 总体管理措施...................................................15
5.2 施工准备.............................................................16
5.2.1 施工管理制度的建立.............................................16
5.2.2 施工技术准备...................................................16
5.2.3 施工准备.......................................................16
5.3 施工平面布置.........................................................17
5.3.1 施工平面布置原则...............................................17
5.3.2 施工平面布置...................................................18
6 施工部署...................................................................19
6.1 施工指导思想.........................................................19
6.2 项目施工管理架构...........................................................................19
6.3 施工阶段划分.........................................................20
6.4 各施工段的施工顺序...................................................21
6.4.1 搭建园区的网络架构,建立园区弱电井,确定路由位置的施工顺序.......21
6.4.2 楼宇内的施工顺序...............................................21
6.4.3 各系统的施工顺序...............................................22
6.4.4 整体工程施工顺序...............................................25
6.5 安装工程特点.........................................................26
6.6 弱电施工与其他施工单位的协调和配合...................................26
7 工程资源投入计划...........................................................28
7.1 施工设备的投入.......................................................28
7.2 劳动力的投入.........................................................28
7.3 主要材料进场计划.....................................................28
7.3.1 辅材的进场计划.................................................29
7.3.2 线缆的进场计划.................................................29
7.3.3 设备的进场计划.................................................29
7.3.4 设备检验计划...................................................30
8 工程进度安排及保障.........................................................31
8.1 施工进度计划.........................................................31
8.2 工期保证措施.........................................................32
8.2.1 总体控制措施...................................................32
8.2.2 分项工程工期保证措施...........................................33
8.3 工程的主要阶段.......................................................34
9 主要分项工程施工方法.......................................................35
9.1 系统工程的实施方法...................................................35
9.1.1 公共设备的安装和调试...........................................35
9.1.2 室内设备的安装及调试...........................................35
9.2 线管和线槽的敷设.....................................................36
9.3 系统线缆规格和敷设...................................................38
9.4 综合布线系统的施工...................................................39
9.5 楼宇自控系统工程的安装...............................................42
9.6 综合安保系统工程的安装...............................................43
10 项目管理和责任............................................................45
10.1 工程管理及责任......................................................45
10.1.1 供货商(某某公司)责任范围......................................45
10.1.2 物业管理中心责任范围..........................................47
10.1.3 监理责任范围..................................................47
10.2 设计联络和人员规定..................................................48
10.2.1 设计联络......................................................48
10.2.2 某某公司施工人员在工程所在地的规定............................48
10.3 包装要求............................................................48
10.4 发运要求............................................................49
10.5 运输及现场保管......................................................49
10.6 安装及调试..........................................................49
11 质量保护、创优计划........................................................51
11.1 创优目标............................................................51
11.2 质量保证体系........................................................51
11.2.1 施工质量管理组织机构..........................................51
11.2.2 质量管理职责..................................................51
11.2.3 质量控制体系的运行............................................52
11.2.4 各施工阶段性的质量保证措施....................................54
11.3 工程创优体系及保证措施..............................................56
11.3.1 施工计划的质量控制............................................56
11.3.2 技术制度、技术策划执行质量的保证...............................56
11.3.3 工程档案质量的保证............................................58
11.3.4 材料质量的保证................................................58
11.3.5 施工班组操作质量的保证........................................59
11.3.6 工序产品保护制度..............................................59
11.4 单项工艺实施质量控制措施............................................59
12 安全生产及文明施工........................................................63
12.1 安全管理机构和管理制度的建立........................................63
12.1.1 安全生产管理机构..............................................63
12.1.2 安全管理组织计划..............................................63
12.1.3 安全防护措施..................................................64
12.2 文明施工纲要........................................................65
12.3 文明施工目标........................................................65
12.4 文明施工管理机构....................................................65
12.5 文明施工检查措施....................................................65
12.6 文明施工标准........................................................66
12.7 建立安全教育制度....................................................67
12.8 保证文明施工的措施..................................................68
12.9 保证施工安全的措施..................................................68
12.10 防火安全措施.......................................................68
12.11 安全施工措施.......................................................69
12.12 成品保护安全措施...................................................72
13 流程图....................................................................73
13.1 项目管理流程图......................................................73
13.2 施工准备流程图......................................................74
13.3 设计图纸的审核流程图................................................75
13.4 设计图纸变更流程图..................................................76
13.5 材料设备变更流程图..................................................77
13.6 施工安装流程图......................................................78
13.7 材料入库流程图......................................................79
13.8 材料出库流程图......................................................80
13.9 工程材料供应流程图..................................................81
13.10 文件存档流程图.....................................................82
13.11 文档发送流程图.....................................................83
13.12 定货流程图.........................................................84
13.13 验货流程图.........................................................85
14 项目经理及相关人员........................................................86
14.1 主要管理人员........................................................86
14.2 主要项目负责人......................................................86
15 测试、检验和验收...........................................................87
15.1 概述................................................................87
15.2 到货检验............................................................87
15.3 开箱检验............................................................87
15.4 安装验收............................................................87
15.5 完工测试............................................................88
15.6 大联调..............................................................88
15.7 试运行..............................................................88
15.8 质保期..............................................................88
15.9 最终验收............................................................88
16 技术文件和培训............................................................89
16.1 图纸、手册和技术文件.................................................89
16.1.1 概述..........................................................89
16.1.2 图纸..........................................................89
16.1.3 手册..........................................................89
16.1.4 技术文件......................................................89
16.1.5 图纸、手册和技术文件的确认....................................89
16.1.6 图纸、手册和技术文件的交付....................................90
16.2 培训................................................................90
16.2.1 概述..........................................................90
16.2.2 培训计划和内容................................................90
1 编制说明
1.1 编制原则
某某住宅小区(以下简称“某某小区”或“某某住宅小区”或“住宅小区”)。智能化系统工程施工组织设计中的主要施工方案和施工方法,以及主要生产资源要素的优化配置和诸多方面的施工保障措施等均遵循科学严谨、细致、实用、合理的原则,按照建设单位提供的工程有关资料的内容而编制的本设计是该工程施工中必备文件,也是工程技术资料的组成部分,旨在保障本工程保质保量、安全施工,达到质优、按期、顺利完成的目的的综合阐述。。。。。。
1.2 关于施工工期及范围
本施工组织设计按工程全部竣工的施工工期考虑编制的,其施工项目范围包
括闭路电视监控子系统、可视对讲子系统、家庭智能控制子系统、三表远程抄送
子系统、小区巡更子系统、一卡通消费子系统、停车场管理子系统、设备集中控
制子系统、电子公告牌子系统、物业计算机子系统、综合布线子系统、小区宽带
局域网子系统、有线电视子系统、电话子系统。总工期大约475 天(开始施工日
期由甲方决定)。
1.3 关于工程进度
本设计中所考虑安排的施工总进度计划将来以甲方要求的工程总进度、以及
甲方有关的工程(主要是室内工程)总进度为依据进行设计,工程总计划及工程
施工进度也是按前面施工队进度进行设计,便于及时地指导工程施工进度。
1.4 备注说明
本计划因限于各种可能潜在因素的影响,在考虑安排选择施工方案与方法,
施工程序、工艺流程、工期计划、质量技术、安全保证措施以及未尽事项等方面
难免有遗漏、谬误之处,有待以后予以详细地修正、补充、完善,使其成为本工
程施工中必须的指导性文件。
2 编制依据
1. 某某住宅小区智能化工程招标书
2. 某某住宅小区平面图
3. 智能建筑设计标准 GB/T 50314-2000
4. 计算机机房设计规范 GB 50174-93
5. 民用闭路监视电视系统工程技术规范 GB 50198-94
6. 有线电视系统工程技术规范 GB 50200-94
7. 建筑设计防火规范 GB J16-87
8. 民用建筑电气设计规范 JGJ/T 16-92
9. 电气装置工程施工及验收规范 GBJ 232-82
10. 建筑与建筑群综合布线系统工程设计规范 CECS 72:97
11. 建筑与建筑群综合布线系统工程施工及验收规范 CECS8997
12. 有线广播录音、播音室声学设计规范和技术用房技术要求GYJ26-86
13. 有线电视加解扰系统通用技术要求 GY/T114-94
14. 有线电视广播系统技术规范 GY/T106-92
15. 防盗报警控制器材通用技术条件 GB 12663-90
16. 安全防范工程程序与要求 GA/T75-94
17. 入侵探测器通用技术条件 GB 10408.1-89
18. 防雷及接地安装工艺标准 322-1998
19. 金属线槽配线安装工艺标准 313-1998
20. 钢管敷设工艺标准 305-1998
21. 建筑电气安装分项工程施工工艺标准 533-1996
22. 建筑与建筑群综合布线系统工程施工及验收规范 CECS 89:97
23. 中国工程建筑标准化协会的《建筑与建筑群综合布线系统工程施工规范》
3 工程概况
某某住宅小区位于四川省XX 市XX 辖区范围内,项目总用地约15.93 公倾。
总建筑面积308003 平方米,其中住宅面积286012 平方米,公共建筑面积(包括
地下停车场)21991 平方米;地下建筑面积12341 平方米,地上建筑面积295663
平方米。容积率:1:1.86。
某某住宅小区由20 栋联排楼、9 栋塔式楼组成;共有72 个单元,81 部电梯,规划总住户为2006 户。机动车位共555 个,其中地上停车场171 个停车位,地下停车场384 个停车位。
本次工程主要包括3 大类共13 个子系统:
= 安全防范系统:闭路电视监控子系统;可视对讲子系统;家庭智能控制子系
统(包括三表抄送子系统);小区巡更子系统;
= 物业管理系统:一卡通消费管理子系统;停车场管理子系统;设备集中控制
子系统;电子公告牌;物业计算机子系统;
= 信息网络系统:综合布线子系统;小区宽带局域网子系统;有线电视系统;
电话子系统。
某某小区智能化系统组成如图3-1 所示:
图3-1 某某住宅小区智能化系统组成图
某某小区智能化系统示意图如图3-2 所示:
图3-2 某某住宅小区智能化系统示意图
4 业主的配合条件
4.1 施工前的配合要求
在施工前,施工工程中需要必备的施工条件,如:仓库、施工办公室、施工
用水用电等辅助办公及施工设施,这就需要业主来配合我公司,安排部署、落实
到位。
我们建议要求仓库面积不小于150 平方米,建立在小区中心或易管理的地
方。另需要1 间办公室用作智能化系统工程办公之用,满足基本要求即可。施工
用水电建议在施工工地的每栋楼提供一个接点,我公司将安装相应的水电表,提
供施工工地现场用电、用水。
4.2 施工期间的协调工
首先,在施工工程中必须要和土建工程紧密配合,完成水平子系统线管预埋
的铺设工作;其次,由于装修工程直接影响室内家庭智能设备的安装,因此需要
业主协调好装修工程的装修时间,协调装修工程和弱电工程进度。
4.3 不可预见的协调
在整个施工工程中,都存在着和各施工单位不可预见的协调关系,也存在着
一些不可抗的因素。这都需要业主或甲方监理按照实际情况进行各方面的协调工
作。
5 总体施工方案
5.1 总体施工方案
5.1.1 基础工程
搭建小区内的网络及布线系统,作为本工程的基础工程,也是本工程的重点
工序之一。
按照施工设计方案的规范要求,根据商务楼电信布线标准ANSI/TIA
/EIA-568-A 或B(由甲方决定,默认为A 类标准)标准对各系统线缆进行铺设,
并保证线缆的通路。各栋公共部分采用镀锌铁管的布线方式、各层公共部分采用
金属线槽的布线方式,线缆经各层的弱电井出来后通过吊顶的金属线槽,经天花
镀锌管线槽入室,沿墙面内预埋的镀锌管线槽按照施工图纸指定的位置将线缆铺
设到位。楼栋之间网络系统通过六芯室外多膜光纤连接。
1. 闭路监控系统
闭路监控子系统在园区内通过PVC 管敷设,主要为75-5 视频线,电源线采
用就近接用的方式,如果为带云台摄像机则还需要一根控制线。
2. 可视对讲子系统
可视对讲子系统配线时,某某公司根据线长和系统的负荷以及建筑物内布局
和电气、电磁情况来灵活设计。
单元系统中干线视频线采用SYV75-5,当线长超过100 米且增益达不到
1Vp-p 时,增加视频放大器;单元系统中户线视频线采用SYV75-3,当线长超过
50 米时,则采用SYV75-5;连接管理中心视频线采用SYV75-5 或SYV75-7。
信号线根据实际情况选用不同线经,一般全部采用RVV 4 芯信号线,考虑
门禁的情况下,采用RVV 6 芯线或8 芯线。
电源线可根据传输距离计算电压衰减值。一般情况下,电源线可与信号线相
同规格。
布线注意事项:
布线要按照建筑电气弱电系统的相关标准来设计。楼宇可视对讲系统特别强
调以下注意事项:
视频线和信号线严禁与强电线包括AC220V 连在一个层内或一个线槽、桥架
内。严格意义上,也不能走同一个线井,如无法分开走线井,也应间隔60cm
以上;
视频线和信号线尽量不要与有线电视、电缆、电话走同一通道,如无法分开,
信号线要用屏蔽线(RVVP)布线;
信号线也不能与其他系统的开关电源走同一通道。
3. 电话子系统
多层住宅楼电话配线系统
在每个梯口的竖井内设置电话分线箱,室外电缆引入处设置两个100 对电话
分线箱或3/2 个50 对电话分线箱(3 个单元以上采用2 个100 对电话箱,3
个单元采用3 个50 对电话分线箱,2 个单元采用2 个50 对电话分线箱),
经电话分线箱将电话线引入住户的电话插座上。
高层住宅电话配线系统
在一层的弱电电缆井内设置2 个100 对电话分线箱,在第四层和第十四层分
别设置100 对的电话分线箱,各电话分线箱将电话线分配至各个住户的电话插座
上。
楼内部电话管线的设计
某某小区楼内部采用结构化综合布线系统,其弱电井内上升管路采用规格为
100*50*1 的金属线槽,楼层平面配管采用直径为20 毫米的PVC 管,安装
方式为暗装,到用户终端后墙埋至各住户的墙上终端盒。
标记
公号电话大对数线缆直接接入电话控制中心指定的机柜内,将其直接打在
110 配线架上,标签纸使用白色标签纸标记清楚局端入口电话;由电话控制
中心到配线间,配线架标签的颜色为灰色。工作区线缆接入110 配线架标签
纸颜色使用橙色标签纸/语音采用蓝色标签纸,标注清楚插接的标注号码或
相对应的房间号。
4. 家庭智能化系统
NDT 是家庭智能化系统的核心,作为一个高科技产品,其安装和调试必须
按标准的程序分步实施。任何不按标准实施的操作,都可能造成NDT 系统不能
正常工作,或后期无法维护。所以要求,所有NDT 系统的室内布线部分,必须
严格按以下标准步骤执行:
1) 布线前的准备工作
需准备的工具及附件:
《NDT 外接设备端口分配表》、智能化系统室内施工图、万用表、剥线钳、
改锥、电工刀、绝缘胶布、透明胶、标签、玻璃胶、电钻、铁锤、四芯电话
线。
A) 端口分配
将NDT 的20 个接口,按标准《NDT 外接设备端口分配表》做出分配规划。
此表作为NDT 重要的原始资料,一份电脑存档,一份现场施工。两份均应
妥善保存,以便NDT 的调试和维护有据可查。
注:1-16#为标准输入端口,可按需要分配给各类探测器,计量表等信号采
集设备;17、18 为12V 直流输出端口,可分配给警灯、警号等12V 输出控
制设备;19、20 为继电器输出端口,分配给家电控制器用,通过家电控制
器来控制家电。
B) 标签制作
按上一步做出的分配表的编号,制作两份相应的线头不干胶标签,以在布线
施工时标识线路使用。
C) 芯线定义
根据购买电缆的色组,定义各条芯线的功能,填写《NDT 外接设备端口分
配表》相应的芯线定义栏。同一工程芯线定义必须保持一致。
2) 现场布线施工
1. 土建开槽
A. 底盒墙洞开挖
水平距大门门框、底端距地详见设计图纸。挖墙尺寸:高:290mm,宽:
255mm,深:110mm
B. 按图纸指定走线路径开槽,在离NDT 外接设备的安装位置最近的地方,
挖标准86x86 暗埋底盒安装孔。若是家电控制器的出线端,则该暗埋孔位置应水平紧靠将控制的强电输出插座暗埋孔位置,要确保强电插座的火线能以最短的长度进入控制器底盒。
注:若图纸未标明详细走线路径的,应由布线工程师现场标示,并作出书面
记录,方可开凿。走线路径应尽量沿墙阴角线,且水平走线一定不能低于门、
窗的上框高度,绝对禁止墙下角或地埋走线。
2. 埋管及设备端底盒予埋
A. 底盒组装
a. 用自攻螺钉装上电源和转接板拖架,固定;
b. 装上底盒定型铁条;
c. 装上底盒盖板;
B. NDT 底盒暗埋
将底盒水平固定在墙洞内,若墙厚度不够,须将墙挖通,则在底盒背面
应加丝网再抹墙料。底盒正面盖板则都应加丝网再抹墙料固定。底盒边
缘应与墙面相平,绝不能凸出墙面或凹进超过3mm,以保证NDT 面板
能与墙良好结合。
C. 设备端出线底盒予埋
将标准86x86 暗埋底盒安装固定在上一步骤1-B 所述暗埋孔内。若该出
口为家电控制器出线端,则该暗埋底盒应由NDT 产品提供商提供或由
其指定型号购买。
D. 埋管
根据走线路径,沿槽予埋PVC 管,PVC 管必须全封闭予埋,在管的两
端(NDT 底盒端和设备出线盒端)须使用缩结封闭固定。
3. 穿线
根据各外接设备的位置及走线路径,计算出各设备的线缆长度(要加入
两端线头予留余量),切取相应长度的电缆,并根据《NDT 外接设备端口分
配表》的编号,在电缆两端贴上标签,在标签上再贴上透明胶,以防标签破
损,然后穿入PVC 管。在电缆的两端还须用绝缘胶布封闭,以防污损线头。
予留的电缆包好后规则地卷在底盒内,不可随意悬在外面。
4. 线路的检测记录
按《NDT 外接设备端口分配表》的编号顺序,将信号电缆的出线盒端
四根芯线短路连接,在NDT 底盒端用万用表的欧姆档,两两组合测试四芯
的通断状况。
A