1、单击此处编辑母版标题样式,单击此处编辑母版文本样式,第二级,第三级,第四级,第五级,*,*,PM,工作职掌介绍,1,概要,名词解释,PM,智能介绍,试产阶段划分,PM,及各单位在试产各阶段,R&R,2,名词解释,PM:Project Manager,项目经理,PC:Production Control,生管,MC:Material Control,物管,Buyer/Purchase,采购,MFG:Manufacture,制造,IE:Industrial Engineer,工业工程师,ME:Mechanical Engineer,机构工程师,EE:Electric Engineer,电子工程师,
2、SQE:Supplier Quality Engineer,供应商管理工程师,QA:Quality Assurance,品质保证,QE:Quality Engineer,品质工程师,3,名词解释,HWQA:Hardware Quality Assurance,硬体质量保证,SWQA:Soft Quality Assurance,软体质量保证,IPQC:in process quality control,制程质量管控,IQC:input quality control,进料质量管控,4,PM,职能介绍,什么是,PM?,项目经理,-,新产品试产的主导者,简单来说,如果新产品试产是条珍珠项链,,P
3、M,就是那根线,.,PM,是新产品试产的主导者,在试产中协调各部门的工作,确保试产顺利进行,.,5,试产阶段划分,EVT,(,工程验证测试,),DVT,(,设计验证测试,),PVT,(,生产制程验证,),MP,(,导入量产,),EVT,Engineering Verification Test,工程验证测试,拟在检查产品的基本功能是否像预期一样进行工作,DVT Design Verification Test,设计验证,测试,是产品生产中不可缺少的一个检测环节,包括模具测试、电子性能、外观测试等,PVT Process Verification Test,制程验证测试,意为小批量过程验证测试,
4、主要验证新产品的各功能实现状况并进行稳定性和可靠性测试,MP Mass Production,量产,批量性生产,符合出货要求,6,PM,以及各单位,在各试产阶段,R&R,研发,/,营业主导召开新产品,Kick off meeting,告知新产品的产品规格,量产的大致日程,以及客户是否有特别的测试要求等,.,PM,根据营业给出的大日程制定试产,schedule,。,PM,组建,Team Roster,各部门主管根据,PM,提供的试产计划指定小组成员,.,PM,主导,EVT,prepare meeting,将新产品的规格以及试产各阶段的,milestone,告知,team,成员,与此同时,统计,E
5、VT,各单位对样品的需求,.,MC,根据,EVT,样品需求数量,run material shortage list,缺料部分发给,buyer,请,buyer,回复物料交期,.,7,PM,以及各单位,在各试产阶段,R&R,PM,确认物料交期是否能满足试产需求,tracking,备料进度,在产品试产前各单位需准备文件及治工具,IE,提供,SOP,及治工具清单,QE,提供,QII,(,Quality Inspection Instruction,检验指导书),PM,主导试产前准备会议,确认文件,治工具以及物料满足试产日程,明确试产具体时间和场地,以及试做人员安排,各试产阶段前都须有小批量的工程试组
6、对治工具,物料进行确认,确保后续试产顺利进行,.,工程试组参与人员为,PM,,工程,IE,QA,试产结束后,各单位将问题点整理成,issue list,统一发给,PM,整合,问题点包括作业困难点,治具问题,来料问题,组装问题等,QA,提供功能及外观检验报告,8,PM,以及各单位,在各试产阶段,R&R,PM,主导试产,iss,ue review meeting,检讨各问题点,QA,根据生产良率以及信耐性评价等判定产品是否可以进入下一个阶段,或是导入量产,9,Kick off,Meeting,RD/Sales,Milestone,PM,Team Roster,PM,Design Review,P
7、M&RD&Eng&QA,DFx Report,NG,OK,Material,Preparation,Tooling Creation,MC&Buyer,RD/Eng,Lab stage,1.PM collect EVT sample requirement from each Dept.when making milestone.,2.Material preparation include washer and lens,3.RD review tooling with ENG.,4.RD make samples for self-check on Lab stage to make su
8、re production feasibility.,5.Design issue need include operation,、,fixture,、,process,New Project Pilot Run Process,10,New Project Pilot Run Process,Lab stage,Phase Gate Review,NG,OK,EVT material prepare,Fixture,prepare,Document,prepare,Fixture prepare include Assy and testing.,Document:SOP,SIP,PM co
9、llect all the issues from each Dept.,MC,IE&QA,Eng,ALL,EVT,Reliability Test,Issue List,ALL,QA,11,New Project Pilot Run Process,Reliability Test,Issue List,Purge List,Phase Exit,Reliability test pass,and issues be closed,production can go to DVT.,Purge list should be confirmed by MC and QA,MC inform buyer;QA hold old material,Pass,Eng,DVT,close,Material Prepare,Fixture update,Document update,12,