1、 Huawei Technologies Huawei APS Project Business Analysis Factory Planner Revision 5.0 14-Aug-2002 © 2001 i2 Technologies, PROPRIETARY and CONFIDENTIAL TABLE OF CONTENTS PURPOSE 5 SCOPE OF THE IMPLEMENTATION 5 2003 Go Live 5 OVERVIEW OF OPERATIONS – AS IS PROCESS 6 Ov
2、erview of business process 6 MDS 8 MPS 8 Purchasing 9 Manufacturing plan 10 BUSINESS SCENARIOS 11 In Scope Business Scenarios 11 Out Of Scope Business Requirements 12 BUSINESS SCENARIO DETAIL: FP-1. MATERIAL ASSIGNMENT ACCORDING TO DEMAND PRIORITY 13 BUSINESS SCENARIO DETAIL: FP-2. PLAN
3、 FOR TIER1 ORDERS WITH ORDER HOLD STATUS 14 BUSINESS SCENARIO DETAIL: FP-3. ASSIGN HIGHER DEMAND PRIORITY IF ONE OF ITS WORK ORDER HAS BEEN RELEASED. 15 BUSINESS SCENARIO DETAIL: FP-4 MATERIAL PLANNING FOR POC FORECAST 16 BUSINESS SCENARIO DETAIL: FP-5. R&D MATERIAL REQUIREMENT 17 BUSINESS
4、SCENARIO DETAIL: FP-6. ACCOUNT FOR THE SHIPMENT TIME TO DELIVER TO CUSTOMER 18 BUSINESS SCENARIO DETAIL: FP-7. ASSEMBLY COORDINATE FOR (POC AND ATO) UNDER PTO 19 BUSINESS SCENARIO DETAIL: FP-8. PTO FROM THE SAME SHIPSET WILL COMPLETE TOGETHER 20 BUSINESS SCENARIO DETAIL: FP-9. SAFETY STO
5、CK 21 BUSINESS SCENARIO DETAIL: FP-10. OPERATION LEVEL MATERIAL CONSUMPTIONS 22 BUSINESS SCENARIO DETAIL: FP-11. CONSUME FROM INVENTORY BUFFERS 23 BUSINESS SCENARIO DETAIL: FP-12. ALTERNATE PART FUNCTION 24 BUSINESS SCENARIO DETAIL: FP-13. ENGINEERING CHANGE ORDER 25 BUSINESS SCENA
6、RIO DETAIL: FP-14. COORDINATE WORK ORDERS FOR FINISHED AI AND SEMI-FINISHED AI 26 BUSINESS SCENARIO DETAIL: FP-15. AI WORK ORDER GENERATED BASED ON LOT SIZING RULE 28 BUSINESS SCENARIO DETAIL: FP-16 CHECK BOM, SUPPLIER DATA AND UNPLANNED ORDERS. 29 BUSINESS SCENARIO DETAIL: FP-17. RELEASE
7、 WORK-ORDER WITH MATERIAL SHORTAGE 30 BUSINESS SCENARIO DETAIL: FP-18 REVIEW LATE ORDERS AND MAERTAIL ASSIGNMENT 32 BUSINESS SCENARIO DETAIL: FP-19. WIP REPORTING AND PLANNING 33 BUSINESS SCENARIO DETAIL: FP-20. SCHEDULE FROZEN PERIOD 34 BUSINESS SCENARIO DETAIL: FP-21. RESOURCE GROUP
8、ING FOR PRODUCTION PLANNING 35 BUSINESS SCENARIO DETAIL: FP-22. MULTIPLE PARALLEL RESOURCE PLANNING 36 BUSINESS SCENARIO DETAIL: FP-23. FINITE CAPACITY BALANCING RULE 37 BUSINESS SCENARIO DETAIL: FP-24. MINIMUM UTILIZATION REQUIRED FOR SUBCONTRACTORS – MANUAL PROCESS 38 BUSINESS SCENARIO
9、DETAIL: FP-.25 REVIEW CAPACITY PLAN 40 BUSINESS SCENARIO DETAIL: FP-26 REVISE CAPACITY PLAN 41 BUSINESS SCENARIO DETAIL: FP-27. SCHEDULING RULE 42 BUSINESS SCENARIO DETAIL: FP-.28 ADJUST SCHEDULE 43 BUSINESS SCENARIO DETAIL: FP-29. CONSOLIDATE PR BASED ON TIME AND LOT SIZING RULE 44 BUSI
10、NESS SCENARIO DETAIL: FP-30. PROCUREMENT SUGGESTION WITH BLANKET PO NUMBER 45 BUSINESS SCENARIO DETAIL: FP-31. VENDOR ALLOCATION 46 BUSINESS SCENARIO DETAIL: FP-32. FORECAST FOR VMI VENDORS 47 BUSINESS SCENARIO DETAIL: FP-33. DELIVERY SCHEDULE FOR JIT VENDORS 48 BUSINESS SCENARIO DETAIL
11、 FP-34. EACH FACTORY BUILDING AT SHENZHEN SHOULD CONSUME INVENTORY FROM ITS OWN BUILDING FIRST, OUTPUT FACTORY LOCATION FOR PO FOR VENDOR DELIVERY INFORMATION 49 BUSINESS SCENARIO DETAIL: FP-35. OUTPUT PRODUCTION SCHEDULE 51 BUSINESS SCENARIO DETAIL: FP-36. REPORTING 52 OUT OF SCOPE BUSI
12、NESS REQUIREMENTS 54 FP-O-1 Manually Entering of BOM 54 FP-O-2 Different Attribute For Part in BOM 54 FP-O-3 Large Quantity Small Value Item Management 54 FP-O-4 AI Phase In and Phase out 54 FP-O-5 Adding Urgent Orders in FP directly 54 FP-O-6 Inventory Tracking Status 55 FP-O-7 Customize ATO
13、 Routing. 55 FP-O-8 Schedule Work Orders For Portion of AI Forecast 55 FP-O-9 Check Software and Documents Before Work Order Release 55 FP-O-10 Plan Change KPI 56 FP-O-11 Track Factory’s Execution Adherence to the Schedule 56 REVISION HISTORY 57 MAJOR CHANGES SINCE LAST REVISION 57 REQUIRED A
14、PPROVALS 58 Purpose The Business Analysis document captures the As-Is Process, identifies improvement opportunities and defines the To-Be Process. It also documents business scenarios that describe the workflows and business processes that the software solution should address. It elaborates on the
15、 available inputs, required processing (including timing and frequency considerations) and the required outputs. Each scenario in turn helps in defining what solution features would be required. The document is a supporting tool to decide on the features and functionality needed in the solution. Th
16、e use case scenarios are later used to validate and accept resolved issues. The document should be used at the start of the Solution Architecture phase, and continually reviewed throughout the implementation as more information becomes available. The To-Be Process Map is a separate document availab
17、le in i2 Project Document Library for Huawei project. Scope of the Implementation 2003 Go Live As a module in the APS solution, FP perform material and capacity planning, as well as factory scheduling for HW. FP plans for all demands in HW, including customer orders, forecasts, R&D, as well as i
18、nternal demands. The The organization involved in the scope of Phase I is Huawei’s factory in ShenZhen for all the product divisions. This phase will enable the HW ShenZhen factory to: · Provide material requirement forecast planning for all planned procured parts up to 12-18 month · Plan mater
19、ial based on the feasible production plan up to 4-6 months, or the longest lead-time for non-critical material · Improve demand due date performance by reviewing early warning of late orders and material shortage · Plan for alternate component requirements · Generate production plan over the plan
20、ning horizon, and production schedule for the frozen period. · Provide visibility into material and capacity problems · Better supply to demand match to reduce inventory level Planning horizon will be 6 months that starts with daily buckets for the first two weeks, followed by weekly buckets fo
21、r the next 1.5 month, and then followed by monthly buckets. For the monthly run of FP to generate master material requirement planning, up to 18 months of forecast can be used. FP generates procurement plan only for non-critical components. MP generates the procurement plan for critical components
22、 From MP, the constraint forecast demand (AI and POC) as well as the critical material supply would be the input to FP. FP will perform the factory level detailed material planning for all components, as well as all the major bottleneck resources. Scheduling will also be performed on the bot
23、tleneck resources. Use the FP schedule result as a base; factory will schedule other non-constraining resources as well as the operators. FP outputs the production plan including WIP back to MP as its supply. Based on a feasible material and capacity, FP sends material requirement forecast, and
24、procurement recommendation for all planned parts to SCC for collaboration. Exceptions such as material shortage and expedition recommendations are also provided to the buyer. FP also outputs JIT/VMI pull signal based on near term production schedule. Overview of Operations – As Is Process Overvi
25、ew of business process At HUAWEI the planners of different department are in charge of materials planning. And the planners only plan the products for their own department. All the planning processes are separately. The whole process is: a. Gathering and process all demands with MDS (M b. Generat
26、e MPS c. Run MRP and Scheduling d. Process WO and PR e. Execute WO and PR The Bill-of-materials for a typical Huawei sales order item is as in the following figure: Note that PTO at the top of the BOM is a packing process, and does not have any routing. The sales order line ite
27、m will be at ATO level. SMT factory is in the MTS mode, producing according to forecast. There is a SMT inventory warehouse for SMT boards. ATO factory perform the final assembly and testing when Huawei receives the order. In simple words, ‘Planning at the ATO level’ is ATO. The ‘Planning at
28、the SMT level’ is MTS (Made To Stock). ATO’s are unique to customers whereas SMT’s are not. Thus, multiple unique ATO’s share common SMT. MDS In MDS phase, planners gather all the forecasts first. Then check and adjust the forecasts. After confirming the forecasts, the planners gather all the de
29、mands together, that mainly coming from the following four ways a. Demands from marketing plan department b. Demands from the business department (real sales orders) c. Internal demands between different departments d. Independent requirements from different departments After this phase, planne
30、rs know all the demands that needed to be planned. MPS To generate MPS, planners first generate a MPS plan and get the relation reports. Then they adjust the MPS result before sending to the planning manager for approval. After the planning manager confirmed the MPS result, the planners need to
31、maintain the new MPS plan. Then the MRP scheduling plan is generated. When adjusting the MPS plan, the planners consider the five factors below: a. Version change b. The capacity constraint of the key resources c. The requirements change from the marketing, and changes in internal requirements
32、 d. The planning percentage e. Other things such as basic data not accurate, the planning attribute not correct and special orders etc. Purchasing Ø Purchasing forecast There are two types of purchasing forecast, one is weekly forecast, and the other is monthly forecast. Weekly forecast co
33、vers three months purchasing forecasts. The materials are mainly locally supplied. And the purchase lead time are relatively short. Some examples are packaging materials, PCB etc. Monthly forecast covers nine months purchasing forecasts. Special materials are only purchased when the real sales or
34、ders are received. They are manually managed and released. Ø The MAX/MIN method allows MAX and MIN inventory for the materials. When the material’s inventory is lower than the MIN value, they will be purchased use the following formula: Purchase quantity = MAX – Inventory – PO (time based) + Re
35、quired quantity of sales order (time based) R&D material planners manually plan and enter the PR of the material for R&D’s exclusive use. Manufacturing plan The planners generate the production reports using the manufacturing data of the first three weeks. Planner only releases the manufacturing
36、orders that begin in the next two days in the manufacturing execution system. Normally planners only release work orders when the materials of work order are all ready in the inventory. But in some urgent cases, they also release the work order even when not all the materials are all ready. The sh
37、ortage material may be arriving within the following two days. Work orders for special AI are released when the actual sales orders are received. Business Scenarios Introduction: Based on the interview questions and discussions with Business Units process owners and factory schedule
38、rs, various business scenarios that represent FP’s business requirements have been compiled. In Scope Business Scenarios Serial Number Categories of Scenarios Target User Scenarios within Category/Comments FP-1 ICP - Demands Material assignment according to Demand priority FP-2 Plan For T
39、ier1 Orders With Order Hold Status FP-3 Assign higher demand priority if one of its work order has been released FP-4 Material planning for POC forecast FP-5 R&D Material Requirement FP-6 Account Shipment time to deliver to customer FP-7 PTO From The Same Shipset Will Complete Together FP
40、8 Assembly coordinate for (POC and ATO) under PTO FP-9 Safety Stock Planning FP-10 Operation Level Material Consumption FP-11 ICP - Supplies Consume From Inventory Buffers FP-12 Alternate part Function FP-13 Engineering Change Order FP-14 Coordinate Work orders for finished AI and sem
41、i finished AI FP-15 AI Work Order Generated Based On lot sizing rule FP-16 Check BOM routing error Check BOM, Supplier Data And Unplanned Orders. FP-17 Review factory problems Release Work-order with Material shortage FP-18 Review late orders and material assignment FP-19 Review froze
42、n schedule WIP Reporting And Planning FP-20 Schedule frozen period FP-21 Finite capacity balancing Resource grouping for Production planning FP-22 Multiple parallel resource planning FP-23 Finite capacity balancing rule FP-24 Minimum Utilization Required For Subcontractors – Manual Proce
43、ss FP-25 Review capacity plan Review Capacity Plan FP-26 Revise capacity plan Revise capacity plan FP-27 Generate schedule Scheduling Rule FP-28 Adjust schedule Adjust Schedule FP-29 Procurement recommendation Consolidate PR Based On Time And Lot Sizing Rule FP-30 Procurement Sugges
44、tion With Blanket Po Number FP-31 Vendor Allocation FP-32 Forecast For VMI Vendors FP-33 Delivery Schedule For JIT vendors FP-34 Each Factory Building At Shenzhen Should Consume Inventory From Its Own Building First, Output Factory Location For PO For Vendor Delivery Information FP-35 Outp
45、ut schedule Output Production Schedule FP-36 Reporting Reporting Out Of Scope Business Requirements Serial Number Categories of Scenarios Target User Scenarios within Category/Comments FP-O-1 BOM Manually Entering of BOM FP-O-2 Different Attribute For Part in BOM FP-O-3 Large quantity
46、 small value item Management FP-O-4 AI phase in and phase out FP-O-5 Add demand Adding Urgent Orders in FP Directly FP-O-6 Inventory Inventory Tracking Status FP-O-7 Routing Customize ATO routing FP-O-8 Release schedule Check software and documents before work order release FP-O-9 Sc
47、hedule work orders FOR PORTION OF AI forecast FP-O-10 KPI Plan Change KPI FP-O-11 Track factory’s execution adherence to the schedule Business Scenario Detail: FP-1. Material assignment according to Demand priority User Scenario: Order priority for all demands (sales, forecast, internal,
48、etc) are assigned according to Huawei’s internal rule (e.g., priority based on customer tier). FP must assign material and allocate capacity based on the order priority. Planners/Users Impacted: Planners List of Causes/Triggers for Scenario: Sales, forecast and internal demands entered
49、from MP and ERP need to be prioritized and planned. Related Scenarios: None Frequency: Demand priority logic is used every time the planner produces a plan. Currently the plan is produced once a day. Decision to be Made/Action to be taken: The sequence of which the orders are being fulfilled.
50、 Customer/Decision Maker: Planner Time Allowed to Make Decision: Default Order Priorities set based on customer tier. Order Priorities changes handled in S&OP process. Input Data Requirements: Every demand, as well as forecast, must have a priority. Logic Requirements: Demand sort priority In