1、 滨海木栈道施工技术方案3#标段 目 录 一、工程概况······························5 1.1 工程简介····························5 1.2 工程管理····························5 1.3 工程目标····························6 1.4 工程分类····························6 二、 编制依据及相关文件··························6
2、2.1 编制依据····························6 2.2 主要规范、规程和标准··························7 三、施工准备及条件··········· ················7 3.1 技术准备····························7 3.2 施工机械一览表···························8 3.3 现场环境及主要措施·······················9 四、施工步骤及主要程序作业方法························11 4.1 施工步骤········
3、····················11 4.2 劳动力投入···························11 4.3 施测程序···························11 4.4 施工测量组织工作···························11 4.5 基底处理···························12 4.6 级配砂石垫层···························12 4.7 防腐木铺装···························14 4.8 栏杆····························
4、17 4.9 木栈桥···························18 4.10 加固体系计算·························18 4.11 预制埋件···························20 4.12 混凝土施工及成品保护·····················21 4.13 截洪沟···························22 4.14 石砌挡土墙···························24 4.15 钢筋混凝土挡土墙···························25 4.16 青石板碎拼及台阶·
5、··························27 五、作业过程中的质量控制和质量保证····················29 5.1 质量保证体系····························29 5.2 质量检查程序···························30 5.3 质量措施··························31 六、本工程作业的安全文明施工及环境管理···················33 6.1 临边防护····························33 6.2 安全生产及相关制度·············
6、··············34 6.3 安全应急措施···························36 6.4 文明施工、保护措施·······················40 6.5 强化施工现场管理·······················41 6.6 环境卫生管理···························41 6.7 综合治理···························42 6.8 空气及噪声污染控制·······················42 6.9 季节性施工···························42 七、
7、本工程危险点及控制措施·····················46 7.1 危险点源分析及控制措施····················46 7.2 作业环境·····························49 7.3 职业安全健康···························50 葫芦岛龙湾中央商务区滨海木栈道景观工程 南、北广场施工技术方案 一、工程概况 1.1、工程简介 施工方案是用来指导施工项目全过程各项活动的技术、经济和组织的综合性文件,是施工技术与施工项目管理有机结合的产物,它是工程开工后施工活动能有序、高效、科学合理地进行的保障。
8、本公司为强化此工程的管理,将对本工程实行项目法管理,建立项目经理部管理体系。我公司按照公司服务控制,项目授权管理,专业施工保障,各方通力协作的模式,卓有成效的实施质量方针与目标。 葫芦岛市龙湾中央商务区滨海木栈道景观工程,南、北广场平台区域铺装青石板碎拼面层,广场内设置原木和石材坐凳,广场临海一侧设置木栏杆,以保证行人安全,广场内设置各种景观小品令游人驻足观赏,南广场内设置重檐六角亭。 1.2、工程管理 本工程施工工期紧,交叉作业多,涉及技术面广,应合理安排工作面,工序搭接,流水作业,要保证充足的各专业劳动力配备,保证材料供应按期到货,施工中不等不靠,创造条件,平行流水交叉作业。施工段的
9、划分应以相互配合,减少二次施工为主,工程开工之前,在适当的位置修筑临时便道,与原有道路顺接,满足材料、机械设备及施工车辆的进场需要,方便施工,同时,为尽量减少施工对行人及其他车辆的干扰,施工车辆现场走行路线应按规定的交通通道进行。工程施工现场条件复杂,地形变化多样,而且所处地理位置特殊,具有较高的施工难度及施工危险性,所以在施工区域的外边缘处(临海)设置安全保护网,以保证施工人员安全。施工过程中,受现场实际情况的影响,各分部分项工作互相制约,施工时应及时进行调整,互相配合,确保工程的施工进度和质量,让工程在保证安全、质量、进度的前提条件下,按期完成施工任务。 1.3、工程目标 (1) 质量
10、目标:全部合格,争取优良。
(2) 安全目标:安全评分达到优良标准,保证无安全事故。
1.4、工程分类
1、按使用功能分类
(1)南、北广场:主要以供行人休息,游玩,驻足观赏海边风景使用。
2、按面层材料分类:
(1)青石板碎拼铺装:主要用于南北广场地面铺装,一般以人行为主,青石板采用自然面厚度为40mm-60mm厚,切割大小为200mm 11、区滨海木栈道景观工程施工图
2.1.2、葫芦岛市龙湾中央商务区滨海木栈道景观工程招标文件(第三标段)
2.2、主要规范、规程和标准(表1)
序号
名 称
编 号
1
建设工程项目管理规范
GB/T50326-2001
2
工程测量规范
GB50026-2007
4
建筑地基基础工程质量验收标准
GB50202-2002
5
市政道路工程质量检验评定标准
CJJ1-90
6
钢筋工程施工及验收规范
JG18-2003
7
砼结构工程施工质量验收规范
GB50204-2002
8
砌体工程施工质量验收规范
GB50203-2002 12、
9
建筑地面工程施工质量验收规范
GB50209-2002
10
建筑工程施工质量验收统一标准
GB50300—2001
11
建筑施工安全检查标准
JGJ59-99
12
施工现场临时用电安全技术规范
JGJ46-2005
13
建筑机械使用安全技术规程
JGJ33-2001
14
国家建筑标准设计图集
04J008-P83-XJA6
15
古建筑修建工程质量检验评定标准
CJJ39-1991
16
本公司质量管理手册、质量管理体系文件和规章制度
三、施工准备及条件
3.1、技术准备
3.1.1、熟悉和审查施工图纸,组织图纸会审
1、由 13、技术部门负责施工图纸收发,建立管理台帐
2、各专业会审图纸针对施工技术和图纸的疑点做好记录
3、开工前及时与业主和设计单位联系做好设计交底和图纸会审工作
3.1.2、准备与本工程有关的规程、规范、图集,根据施工图准备与本工程有关的规程、规范及有关图集并发给项目部相关人员(规范、规程、图集详见编制依据)。
3.1.3、根据建设单位提供的水准点、坐标、控制桩认真组织测量放线,做好控制保护。了解周围环境情况,使施工人员明确具体位置及深度部位。
3.1.4、技术工作计划
根据工程特点及实际情况,经过详细技术论证,编写技术方案并做技术交底,技术交底及时准确并有针对性。
3.1.5、施工试验 14、工作计划
根据工程情况及时计算各种施工物资(主要材料、成品、半成品)的用量,按有关规范、标准进行试验工作。
3.1.6、现场准备
1、根据有关单位指定或协商办理水源、电源、架设线路、搭设围挡、临建办公、宿舍、划定材料堆放场地。
2、根据有关单位提供的水准点、坐标点和控制桩,做引点控制防护。
3、按施工需要在施工范围内合理使用用地进行平面布置,保证施工需要。
3.2、施工机械一览表
下表1为施工过程中,随着工程进度的全面开展,拟定投入的主要大型施工机械参照表。
拟投入本工程的主要施工设备参照表1
序号
设备
名称
型号
规格
数量
国别
产地
制造
年份
额 15、定功率(KW)
生产
能力
用于施
工部位
备注
1
挖掘机
EX200
2
进口
2009
1.2m3
土方
2
装载机
ZL50C
2
国产
2008
1m3
土方
3
小 型
碾压机
M4215
1
国产
2010
回填
4
打夯机
HW170
4
国产
2010
回填
5
洒水车
东风
2
国产
2008
送水
6
农用四轮车
东方红
4
国产
2009
装载
3.3、现场环境及主要措施
3.3.1、现场条件说明:该工程 16、施工场地地形复杂,道路、交通运输较为困难;施工用电采用发电机发电;施工用水采用水车及人工运送。各种材料运输全部靠人力肩挑背扛,施工难度较大。施工垃圾及渣土的运出按当地政府有关规定办理。
我公司将以“过程精品”为原则,对施工过程的每道工序采取更加严格的质量管理措施。从工程质量策划开始,确保从加工定货、施工工艺、过程控制直到竣工验收的每一个环节都处于良好的受控状态,并最终达到预定的质量目标。同时,本工程例为我公司重点工程。
3.3.2、本工程布置在沿海的悬崖峭壁上部和下部,施工安全防护是本工程的重点。
主要措施:针对本工程的特殊性,必须采取靠可的安全防护措施,在山崖临边设安全防护栏杆进行全线 17、封闭;在悬崖下园路施工采取沿路搭设安全防护棚。以确保施工安全。
3.3.3、因本工程的特殊性施工区域无水源和电源,施工用水和绿化种植用水,是施工过程中的难点。
主要措施:大体积商品混凝土和水泥砂浆场外预后拌运至作业面,零星用量现场搅拌;混凝土的养护和绿化种植用水,采取水车场外取水运至作业面,现场配备蓄水箱每天用水车加满保证普通施工用水,混凝土先期养护采用塑料薄膜覆盖,以减少养护用水量;施工用电使用发电机自行发电,在施工机械集中区域和办公区布置DM6500CM单相汽油发电机(5KW)两台,三项交流柴油发电机(24KW)一台,并合理控制用电量,降低发电燃油成本。
四、施工步骤及主要程序作 18、业方法
4.1、施工步骤
准备工作——测量作业———素土夯实、挡土墙——铺设级配砂石——砼垫层浇筑——附属设施、绿化——主路铺装——自检——报验——交付使用
根据工程图纸的施工内容,拟定将滨海木栈道暂划分为三个施工段,由生产负责人进行生产任务分配。
4.2、劳动力投入如下
木栈道工程施工队劳动力投入计划:力工35名,技工95人,其中瓦工30人、木工20人、混凝土工15人、钢筋工20人、铺装工25人、种植工20人。
根据施工现场实际情况各施工队之间的劳动力可随时进行调整,满足施工要求。
4.3、施测程序
准备工作——测量作业——自检——报验——进入下道工序
4.4、施工测量组织 19、工作
由项目部专业测量人员成立测量小组,根据给定的坐标点和高程控制点进行工程定位、建立轴线控制网。按规定程序检查验收,对施测组全体人员进行详细的图纸交底及方案交底,明确分工,所有施测的工作进度及逐日安排,由组长根据项目的总体进度计划进行安排。
4.5、基底处理
4.5.1、工艺流程
处理地基表面 → 级配砂石 → 分层铺筑砂石 → 洒水 → 夯实或碾压 → 找平验收
4.5.2、处理地基表面
4.5.3、将地表面的浮土和杂质清除干净,平整地基,并妥善保护基坑边坡,防止坍土混入砂石垫层中。
4.5.4、基坑(槽)附近如有低于基底标高的孔洞、沟井、墓穴等,应在未填砂石前按设计要求先进 20、行处理。对旧河暗沟应妥善处理,旧池塘回填前应将池底浮泥清除。
4.6、级配砂石垫层
在基底之上,包括主道路与道路一侧截洪沟系统,在基底处理完毕之后上铺300厚级配砂石垫层,级配砂石应选用天然级配砂石或人工级配砂石:宜采用质地坚硬的中砂、粗砂、砾砂、碎(卵)石、石屑或其他工业废粒料。在缺少中、粗砂和砾石的地区,可采用细砂,但宜同时掺入一定数量的碎石或卵石,其掺量应符合设计要求。颗粒级配应良好,级配砂石材料,不得含有草根、树叶、塑料袋等有机杂物及垃圾。用做排水固结地基时,含泥量不宜超过3%。碎石或卵石最大粒径不得大于垫层或虚铺厚度的2/3,并不宜大于30mm。
4.6.1、用人工级配砂石,应 21、将砂石拌合均匀,达到设计要求,并控制材料含水量,见表2;
4.6.2、应分层铺设砂石垫层,分层夯压密实。
4.6.3、铺筑砂石的每层厚度,一般为150~250mm,不宜超过300 mm,分层厚度可用样桩控制,如坑底土质较软弱时,第一分层砂石虚铺厚度可酌情增加,增加厚度不计入垫层设计厚度内。如基底土结构性很强时,在垫层最下层宜先铺设150~200mm厚松砂,用木夯仔细夯实。
4.6.4、砂和砂石地基底面宜铺设在同一标高上,如深度不同时,搭接处基土面应挖成踏步和斜坡形,施工应按先深后浅的顺序进行。搭接处应注意压实。
4.6.5、分段施工时,接槎处应做成斜坡,每层接槎处的水平距离应错开0.5 22、~1.0m,并充分压(夯)实,并酌情增加质量检查点。
4.6.6、如发现砂窝或石子成堆现象,应将该处砂子或石子挖出,分别填入级配好的砂石。
4.6.7、洒水
铺筑的砂石应级配砂石在夯实碾压前,应根据其干湿程度和气候条件,适当地洒水以保持砂石的最佳含水量,一般为8%~12%。
4.6.8、夯实或碾压
本工程视地形条件的不同,可选用夯实或压实的方法。对于平台处大面积的砂石垫层,宜采用压路机进行碾压,边角不倒位处可用蛙式打夯机夯实。夯实或碾压的遍数根据要求的密度由现场试验确定。蛙式打夯机时,要一夯压半夯,行行相接,全面夯实,一般不少于3遍。采用压路机往复碾压,一般碾压不少于4遍,其轮距搭接 23、不小于500㎜。边缘和转角处应用蛙式打夯机补夯密实。
夯实施工方法 表2
项次
压实方法
虚铺厚度(mm)
含水量
(%)
施工说明
1
夯实法
200~250
8~12
用蛙式夯夯实至要求的密度,
一夯压半夯,全面夯实
2
碾压法
200~300
8~12
用6~10t的平碾往复碾压密实,平碾行驶速度可控制在24km/h,碾压次数以达到要求的密实度为准,一般不少于4遍
4.6.9、找平和验收
4.6.10、施工时应分层找平,夯压密实,压实后的干密度按灌砂法测定,也可参照灌砂法用标准砂体积置换法测定。检查结果应 24、满足设计要求的控制值。下层密实度经检验合格后方可进行上层施工。
4.6.11、最后一层压(夯)完成后,表面应拉线找平,并且要符合设计规定的标高。
4.7、南北广场腐木栏杆施工
4.8.1、广场铺装前,开始进行栏杆的施工。
4.8.2、栏杆安装于主广场地面挡砼的预安埋件上,埋件尺寸为-200×200×10,设置为Φ10 L=150mm带弯锚的一级圆钢。
4.11.1、埋件的制作安装注意事项:
严禁使用电、火焊切割板材,截面尺寸较大且无法使用无齿锯的型钢,可先用火焊断料,然后用磨光机将断料处磨平。加工完的埋件,必须进行调直,以保证埋件的平整度。
4.11.2、埋件制作完成后, 25、要经检验合格后方可运至现场使用;
4.11.3、埋件位置标高准确,确保埋件尺寸位置准确无误后与箍筋点焊牢固。
(1)清除木材面毛刺、污物,用砂布打磨。
(2)打磨后需光滑,表面光亮、线条平直。
(3)防腐木栏杆底部加固做法
4.7.1、材料准备
木料准备:木材品种、材质、规格、数量必须与施工图要求一致。板、木方材不允许有腐朽、虫蛀现象,在连接的受剪面上不允许有裂纹,木节不适过于集中,且不允许有活木节。原木或方木含水率不应大于25%,木材结构含水率不应大于18%。防腐、防虫、防火处理按设计要求施工。
4.7.2、防腐木板构件加工制作
构件加工制作:各种木构件按施工图要求下 26、料加工,根据不同加工精度留足加工余量。加工后的木构件及时核对规格及数量,分来堆放整齐,堆放时适当采取防变形措施。
4.7.3、木构件组装:
1、结构构件质量必须符合设计要求,堆放或运输中无损坏或变形。
2、木结构的支座、支撑、连接等构件必须符合设计要求和施工规范的规定,连接必须牢固,无松动。
3、支座部位应按设计要求或施工规范使用防腐木材料。
5、允许偏差(mm)检验标准:
(1)结构中心线距离±20钢尺量
(2)垂直度 H/200不大于15吊线量(H为构件高)
(3)受压或压弯件纵向弯曲L/300拉线或吊线尺量(l为构件长)
(4)支座轴线对支撑面中心位移±10尺量
(5 27、支座标高±5水准测量
(6)木平台平整度±2靠尺和塞尺
4.9
4.10、加固体系计算
4.10.1、侧压力计算
使用插入式振捣器,混凝土浇筑速度取3m/h,新浇筑的普通混凝土作用于模板的最大侧压力,按以下二式计算,取二式最小值
F=0.22γctoβ1β2V1/2
F=γcH
式中F——新浇筑混凝土的最大侧压力(KN/m2)
γc——混凝土的重力密度,取25KN\m3;
to——新浇混凝土的初凝时间(h),to=200/T+15;
H ——混凝土侧压力计算位置处至新浇筑混凝土顶面的总高度,柱高均取2.5米
β2——混凝土坍落度影响修正系数。当坍落度小于30 28、mm时取0.85;50~90mm时取1.0;110~150mm时取1.15;
β1——外加剂影响修正系数。不掺加外加剂时Kw=1;掺加具有缓凝作用的外加剂时Kw=1.2;
V ——混凝土的浇筑速度(m/h)。
其中:T=10 oC;H=2.5m;β2=1.15;β1=1;V=3 m/h
计算得F=0.22γctoβ1β2V1/2=30.36KN/m2
F=γcH=25×2.5=62.5KN/m2
取最小值30.36KN/m2
砼侧压力设计值:30.36×1×0.85=25.806 KN/m2
震动荷载为4 KN/m,则荷载设计值为4×1.4×0.85=4.76KN/m2
荷 29、载组合:F=25.806+4.76=30.566KN/m2
有效压头h=30.566/25=1.22m
2、对拉螺栓选用:拉杆承受拉力P=25800×0.25×0.25=1612.5,查表得P﹤12900(M12螺栓容许拉力),所以采用φ12螺栓。模板采用50×100mm的木方横肋,肋间距200mm布置,模板背面的加劲木方应刨平整,尺寸一致,误差控制在2mm内。加劲木方外侧用直径48mm钢管作纵肋,间距500mm布置,用对拉螺栓加固。
4.11、预埋件
4.12、 混凝土施工及成品保护
4.12.1、砼供应方式:采用商品砼供应。
4.12.2、砼的浇筑采用罐车及泵送。
4.1 30、2.3、每层浇筑厚20cm-30cm左右,泵管的出料口处配置2台插入式振动器,因为泵送砼的坍落度较大,振动器主要负责下部斜坡流淌处的振捣密实,另外1台振捣器主要负责顶部砼的振捣。为防止集中堆料,先振捣出料点处的砼,使形成自然坡度,然后行列式由上而下进行全面振捣,砼振捣采用Ф50插入式振动棒,每浇一层振捣一遍,每两层之间的振动棒应插入下一层砼中约50mm左右,以消除两者之间的接缝,同时在振捣上层砼时,要在下一层砼初凝之前进行。砼的振捣顺序采用“行列式”,振点均匀排列,每次移动距离不应大于振动棒作用半径R的1.5倍(即50cm左右)。使用振动棒时要做到“快插慢拔”,防止面层砼发生分层、离析,及振动 31、棒抽出时造成空洞等现象。振捣时间为20~30s,视砼表面呈水平,不再显著下沉,不再出现气泡、表面泛浆为准。
4.12.4、成品保护
当混凝土在拆完模板后,对其实行成品保护,施工中应根据不同环境条件,按质量保证体系要求,对成品凝土在拆完的保护采取以下措施:
1)防止二次污染,包括浇捣上层混凝土时流浆或滴浆、混凝土冲毛或冲冼而往下流淌的浆水,上部钢筋(或铁件)长时间裸露生锈而流挂的锈水。
2)用塑料薄膜包裹进行覆盖能保持混凝土表面的整洁,减少水分的损耗,防止后续施工时对为完成的混凝土的表面造成污染。
3)角部可以用废旧木板条钉成角条保护,防止外力碰撞混凝土角部导致混凝土结构出现“崩、缺、 32、掉”等现象,防止混凝土尖锐角部的损坏,从而对混凝土软弱部位进行充分保护
4)进行上部施工时的损坏、污染。
4.13、截洪沟
4.13.1、砂浆拌制及砌筑:
1、按水泥重量的5%掺入添加剂,再倒入水,经机械搅拌,略放置5~10分钟后,将拌好聚合物砂浆进行批档、压实抹面施工,水泥标号不低于32.5,基面处理要求牢固、基层不可有浮沉、油污、疏松物等影响粘结的物质。
2、分两次抹灰:
界面层:在清理好并保持湿润的基层上将搅拌好的浆料稍用劲刮涂一道灰浆作为防水界面层,刮涂时应满铺、密实;
防水层:界面层刮好后,随即在其上刮涂一道灰浆作为防水层,刮涂方向应与界面层互成90°,刮涂时应满铺、密 33、实,防水层终凝后应进行养护,通常在防水层缺水表面发白时即应进行,可用花洒轻轻洒水,一天早晚数次,养护期3~7天。
3、砌块排列上、下皮应错缝搭砌,搭砌长度为砌块的l/2,不得小于砌块高度的1/3,也不应小于90mm,如果搭错缝长度满足不了规定的搭接要求,应根据砌体构造设计规定采取压砌钢筋网片的措施。
4、转角处,应将砌块分皮咬搓,交错搭砌。
5、砌块就位与校正:普通烧结砌块提前浇水;但不宜过多。龄期不足28d及潮湿的砌块不得进行砌筑,清除砌块表面的杂物后方可就位,砌筑就位应先远后近、先下后上、先外后内;每层开始时,应从转角处或定位砌块处开始;应吊砌一皮、校正一皮,拉线控制砌体标高和表面平 34、整度。
6、转角及交接处同时砌筑,不得留直磋,斜搓水平投影≮高度的2/3。
7、临时间断处应砌成斜槎,斜槎水平投影长度不应小于高度的2/3。
8、截洪沟图示:
4.13.2、预制沟盖板
1、截洪沟总长约为440m左右,截洪沟上部设置强度等级为C30的砼盖板,砼盖板拟定为外委加工制造。
2、预制沟盖板结构尺寸、预留孔洞、盖板面层坡度要符合标准图或设计的要求。
3、盖板底部主筋保护层厚度偏差±3mm,表面平整,平整度2mm内。
4、盖板对角线差≤5mm。
5、沟盖板图示:
4.14、石砌挡土墙施工
1、正式主、次道路以外地表面标高拟定为±0.000(相对标高),高于正 35、式路面。
2、采用浆砌石石墙工艺,工艺内容采用交错组砌法,按石料形状挂双线分皮卧砌,第一层石块平整的一面朝下,上下石块相互错缝,内外搭接,摆铺稳定,分皮叠砌。
3、浆砌石应用铺浆浆法砌筑,灰缝应饱满,并插捣密实,灰缝一般为20-30mm,铺浆厚度约40-60mm,较大空隙应用碎石块嵌于砂浆中,不允许先填碎石在塞砂浆。
4、浆砌块石不得形成水平或纵向通缝,不得有结搓。
5、用块石填腹时,水平灰缝宽度不得大于30mm,竖向灰缝不大于40mm,填腹石的灰缝应彼此错开。
6、砌体表面的勾缝,无特殊要求时,应在砌筑时留出20mm深的空缝,随即用水泥砂浆将缝勾完,否则应待砌体砂浆凝固后, 36、将空缝清洗干净再勾缝。
7、砌体表面勾缝采用平缝,勾缝所用砂浆标号不低于砌筑砂浆标号。
8、砌体砌筑一次性砌完,不允许随意留施工缝。
4.15、钢筋混凝土挡土墙施工
4.15.1、基础垫层
1、基础垫层施工前在基槽底旁打控制桩,用控制桩控制基础面。
2、混凝土浇筑前检查模板支撑是否有足够的强度、刚度和稳定性,模板接缝要严密,并刷脱模剂。
3、混凝土基础浇捣混凝土后12h内不得浸水,并进行养护。
4.15.2、绑扎钢筋
1、先绑扎基础钢筋并预留墙体预埋筋,然后浇筑基础混凝土,待基础混凝土达到50%强度后进行墙体钢筋绑扎。
2、钢筋制作安装前要认真审核图纸,并设一名专职 37、有经验的钢筋施工员负责钢筋工程的制作,绑扎工作。
3、所有进现场的钢筋,必须有出厂合格证,并经复试合格方可使用。
4、成品钢筋在钢筋作业场内加工成型,由人工或机械运至现场绑扎。
5、现场绑扎时应注意钢筋摆放顺序,钢筋接头相互错开同一截面处钢筋接头数量面积百分率应≤50%,且搭接接头应≥35d。
6、钢筋保护层应满足设计要求,保护层厚度采用与混凝土强度等级相同的混凝土垫块来保证,垫块梅花型交叉布置。
4.15.3、模板支设加固
经监理工程师等相关人员对钢筋骨架进行检查同意后进行支模板施工,本次施工采用拼装钢模。模板支撑要牢固,不能跑模,板缝严密不漏浆,模板高度大于垫层厚度时,要在模板 38、内侧弹线,控制垫层高度。模板支好后,检测模内尺寸及高程,达到设计后方可浇筑振捣。混凝土浇筑过程中派专人对模板进行临测,发现有跑模的迹象立即采取措施。
4.15.4、浇筑混凝土
1、施工过程中严格控制混凝土浇筑质量。
2、混凝土浇筑前应对模板、支架、钢筋、预埋件进行细致检查并作好记录。钢筋上的泥土、油污、杂物应清除干净。经检验合格后进行下道工序。
3、混凝土采用缺罐车运输,泵车浇筑,泵送混凝土坍落度要求160-180mm。
4、混凝土每30cm厚振捣一次,振捣以插入式振捣器为主,要求快插慢拔,即不能漏振也不能过振。振捣棒不能直接振捣钢筋及模板。
5、混凝土必须连续浇筑,以保证结构的整 39、体性。如必须间歇时,间歇时间不得超过120分钟。
6、浇筑混凝土时保证混凝土自由落差不得超过2m。
4.15.5、混凝土养生
1、混凝土浇筑后外露部分立即用塑料薄膜覆盖,人工洒水养生,防止混凝土失水产生表面裂缝。
2、人工洒水养生时间不得少于七天。
3、每次浇筑混凝土时应留2-3组试块与结构同步养生,由同步养生试块强度决定混凝土的强度。
4.15.6、拆模
1、混凝土强度达到75%方可拆除模板。
4.16、青石板碎拼及台阶施工
青石板采用自然面厚度为40mm厚,切割大小宽为200mm 40、mm,粗砂勾缝。
碎拼工艺:
4.16.1、石材面层铺砌
基层处理→弹线找方、找平→试拼→刷水泥、结合层→铺石材→擦缝→清理养护
4.13.2、石材面层铺砌
基层处理:将地面垫层上的杂物清净,用钢丝刷刷掉粘结在垫层上的砂浆并清扫干净。
4.16.3、弹线:在主要部位弹相互垂直的控制十字线,作为检查和控制石材板块的位置,十字线可以弹在混凝土垫层上,钉标高桩并按设计要求找出坡度线。
4.13.4、试拼:在正式铺设前,应按图案、颜色、纹理试拼,另外为检验板块之间的缝隙,核对板块相互位置是否符合要求,然后进行试拼。试拼后按两个方向开始铺设。
4.16.5、刷水泥浆结合层:在铺砂浆之 41、前再次将混凝土垫层清扫干净然后用喷壶洒水湿润,刷一层素水泥浆(水灰比0.5),随刷随铺砂浆。
4.16.6、铺砂浆:根据水平线,定出地面找平层厚度,拉十字控制线,铺1:3干硬性水泥结合层。砂浆从里往处摊铺,铺好后用大杠刮平,再用抹子拍实找平。找平层厚度宜高出石材底面标高3~4mm。
4.16.7、台阶采用人工方法砌筑压顶:
放线定位,根据设计图纸,定位以确定花岗岩的位置和高程;
砌过程中应以测量定位成果为标准;
基底素土夯实后,在基底上铺设200mm厚级配砂石垫层,在垫层基础上浇筑100mm厚强度等级为C20的素砼垫层,然后做30mm厚1:3干硬性水泥结合层,最后铺设40mm厚青石板 42、碎拼面层,在台阶侧壁处内镶嵌35mm厚米黄色文化石贴面,外侧镶嵌30mm厚杂色文化石贴面。
4.16.7.1、干硬性水泥结合层:
干硬性水泥沙浆是塌落度比较低的水泥沙浆,拌和时加的水比较少,其状态为从一米左右的高度,松手自由落在地上就散开呈散粒,以“手握成团,落地开花”,的状态为此水泥砂浆的准配制。
干硬性水泥的配合比为水泥:砂子=1:3配制的水泥砂浆
4.16.8、碎拼石材面层
4.16.9、根据设计要求的规格,挑选碎块石材,有裂缝的石材应剔出。
4.16.10、根据设计要求的图案、尺寸,在基层上弹线并找出面层标高,然后进行试拼,确定缝隙的大小铺砌碎块石材。
4.16.11 43、铺砌1~2昼夜后进行灌缝,粗砂勾缝、勾凹平。
青石碎拼面层纹饰:
五、作业过程中的质量控制和质量保证
5.1、质量保证体系
质量保证体系是以保证和提高工程质量为目标,运用业务系统的严格组织和科学管理制度,把企业各部门、各环节的质量管理职能组织起来,形成一个有明确任务,具体职责、相应权限、互相协调、互相促进的有机整体,使质量管理制度化。
5.2、质量检查程序
质量体系必须结合工程施工的进行顺序、进展情况及时、有效地开展工作。
在开工前负责进行:
(1) 原材料的验证试验、配合比设计等标准试验及定线等测量工作;
(2) 特殊材料或工艺的试验、研究、论证及报批;
(3) 施 44、工准备情况的自检;
(4) 开工报告完成及报批。
在施工过程中负责进行:
(1) 进行工序及工艺过程的试验检测控制。纠正不良操作方法,改进和提高落后的工艺水平,控制工程的质量标准。
(2) 记录整理施工原始记录。
(3) 对完工的分项工程或部位进行自检评定,形成自检记录,对自检合格的工程提交转序申请报告。
(4) 对工程施工过程中出现的各种影响施工和工程质量的情况、问题,及时进行协调、改正和处理。
(5) 对工出现的质量事故负责按规定的程序和要求进行报告处理。
(6) 负责落实有关方面关于工程施工及质量的要求或指令。
工程竣工后负责进行:
(1) 对工程进行自检评定工作。
45、
(2) 整理竣工资料。
(3) 完成竣工报告。
(4) 负责工程质量责任期内的质量问题处理。
(5) 与有关部门对工程进行交(竣)工工程质量鉴定和工程验收工作。
5.3、质量保证措施
(1) 工程工艺控制
单位工程开工前认真编制施工组织设计,经监理工程师审批后,严格按施工组织设计施工。主要分部、分项工程编制施工方案,科学的组织施工。在施工过程中,经常检查施工组织设计及施工方案落实情况,以确保施工生产正常进行。
(2) 工程材料的质量保证
工程材料和辅助材料(包括构件、半成品), 都是构成建筑工程的实体。保证工程材料按质、按量、按时的供应是提高和保证质量的前提。因此供应管理部门 46、必须对采购的原材料、构(配)件、半成品等材料,建立健全进场前检查验收和取样送检制度,杜绝不合格的材料进入现场。
① 水泥、钢材及其它成品半成品进场必须有出厂合格证,并做材质试验,水泥应在有效期内用完。
② 地方材料应先调查料源,取样试验,试验合格并经监理认可后方可进料。
③ 现场设专人收料,不合格的材料拒收。施工过程中如发现不合格的材料应及时清理出现场。
(3) 工程质量保证
① 在总指挥部领导和总工程师的领导下,工程部由专职工程师组成质检室负责质量管理工作。
② 各项目经理部设技术科和质检科,施工作业队设专职质检员,施工班组设义务质检员。
③ 指挥部质检室每月组织一次质量检查 47、每季度由总工程师组织一次质量大检查,召开一次工程质量总结分析例会。
④ 项目经理部每月组织一次本单位的质量大检查,作业队每天进行施工中间检查及竣工质量检查并评出质量等级。
⑤ 班组坚持“三检制”,自检合格后,专职质检员进行全面检查验收。然后由项目经理部质检工程师请监理工程师验收签认。
⑥ 发现违反施工程序,不按设计图纸,规范、规程施工,使用不符合质量要求的原材料、成品和设备时,各级质检人员均有权制止,必要时可向主管领导提出暂停施工进行整顿的建议。
⑦ 各项目经理部每月向指挥部质检室报当月工程质量报表,进行质量分析,建立健全各种工程质量台帐,收集整理各种工程质量资料。
(4) 施工操 48、作的质量保证
施工操作者,是工程质量的直接责任者。工程质量的好坏。除了设计方面的原因外,单就工序质量来说,施工操作者就是关键,是决定因素。
施工操作者,必须具有相应的操作技能,特别是重点部位工程以及专业性质很强的工种工程,操作人员必须具有相应的工种岗位的实践技能。因此,保证施工操作量,就必须按不同工种的质量要求,合理解决施工水平问题。对一些专业技术工种,必须要做到考核持证上岗。
施工操作中,要坚持自检、互检、交接检制度。对工程必须本着自我控制的指导思想。所有工序要坚持样板制,有隐预检要求的还必须坚持隐预检制。要牢固树立“上道工序为下道工序服务”和“下道工序就是用户”的思想,坚持做到不合格 49、的工序不交工。
要按已明确的质量责任制检查操作者的落实情况,各工序实行操作者挂牌制,参加操作者提高自我控制施工质量的意识。做到操作任务明确,质量责任清楚。同时施工操作者还必须做到“原材料把关制”杜绝使用不合格的材料。做好施工工程的成品保护。
在整个施工操作过程中,要贯穿工前有交底、工中有检查、工后有验收的“一条龙”操作管理方法。做到施工操作程序化、标准化、规范化,确保工程质量。
(5) 人员素质的质量保证
在工程质量管理中,“人、机、料、法、环”这五要素,人是决定的素。施工管理层的工程技术人员、专业管理人员、施工操作人员素质的好坏,对施工工程质量起着决定性的作用。必须通过学习不断提高。 50、各专业技工、高级技工等人员必须保持相对稳定,保证其工作的连续性及原有操作技能水平。
(6) 正确处理进度与质量的关系
进度与质量是对立的统一,没有质量就没有进度。实际工程项目施工与管理过程中,必须正确处理质与量的关系。生产指标(任务)、进度(任务)完成后,必须检验质量是否合格。主管领导尤其是项目经理,一定要摆正“进度必须服从质量”这个关系。坚持好中求快,好中求省,严格按标准、规范和设计要求施工。绝不能因为抢工期而忽视质量。
六、本工程作业的安全文明施工及环境管理
6.1、临边防护
1、安全防护栏设置:防止施工人员在山崖临边作业时堕落事故的发生,根据现场实地在山崖边缘1-2米以内搭设临






