1、 平坝区十字乡大屯河现代烟水示范园一期工程一标段 (协议编号:XXQ-YWXDTH-XDYSSFYYQYB) 竣 工 资 料 (第九卷) 施工管理工作汇报 海南三亚实业 12月 目 录 第一章·工程概况···························01 1.1工程概况································01 1.2工程特征及关键经济技术指标························02 1.2关键建设内容····························02 1.3设计变更情况
2、··························04 第二章·工程招投标··························06 2.1工程招标·································06 2.2工程投标 ······························06 第三章·施工进度管理························06 3.1 施工部署标准···························07 3.2 施工部署情况························07 3.3 施工进度····················
3、·······08 第四章·关键工程施工方法······················15 4.1土石方明挖工程施工······························15 4.2浆砌石工程施工·························16 4.3混凝土工程施工·································18 4.4 砂、碎石垫层施工·····························26 4.5回填土工程施工········································26 第五章·施工质量管理··········
4、·························27 5.1质量目标····································27 5.2质量确保体系·····························27 5.3施工质量控制······························36 5.4 创优计划··································36 5.5工程施工质量自检情况·························37 5.6质量事故处理·································37 5.7工程
5、施工质量情况································37 第六章·安全生产和文明施工·····························40 6.1施工安全管理及方法··························40 6.2文明施工管理及方法····························42 6.3施工期环境保护·································43 第七章·协议管理·······························45 7.1价款结算·····························
6、··45 7.2财务管理································45 附件··································46 附件1:施工管理机构设置情况······························46 附件2:项目部关键工作人员情况统计·························47 附件3: 投入施工关键工程设备·······················48 附件4:工程项目施工管理工程大事记····················49 附件5:技术标准目录、施工中使用技术标准··············
7、····50 附件6:施工图片····························51 会 签 栏 审 定: 审 核: 编 写: 参与人员: 第一章·工程概况 1.1工程概况 安顺市平坝区十字乡大屯河现代烟水示范园一期工程由贵州水利科技开发有限责任企业严格根据相关要求进行设计,并经贵州省水利厅以黔水烟【】6文同意建设。该工程在安顺市平坝区十字乡境内;该项目标招标人是:安顺市西秀区水务局,现场管理机构是:安顺市西秀区水务局。 该项目工程本标段招标范围为:新建提水泵站一座(装机3*110kw,两用一备)及对应配套设施;铺
8、设安装提水钢管0.926km;新建一座灌区高位水池600m3,新建排洪渠409.1m等,(具体内容详见工程量清单)。 该工程本标段关键建设内容为:将军岩泵站水源工程、将军岩提水泵站工程(包含集水池工程、泵房工程、1.5m宽水泥路、提水管工程高位水池工程)、管理房工程,景观台至管理房引水管工程、排洪渠工程(包含渠道工程、交通工程)、金属结构设备及安装工程、机电设备及安装工程等。 1.1.1 对外交通 本工程所在地在安顺市平坝区十字乡境内,关键对外交通为县道及乡村公路,公路情况很好,基础能满足本工程所需工程物资材料运输道路条件要求。 1.1.2场内交通 场内交通关键以县道及乡村公路为主,
9、依据现场实际情况及业主指定位置进行新建或整修。场内交通关键以公路运输为主,并以方便施工,降低二次运输为标准,使现场施工道路能满足工程安全、进度及质量等方面要求。 1.2工程特征及关键经济技术指标 1.2.1工程特征 项目工程特征表 序号 项目 单位 数量 备注 1 水文 利用水文系列年限 年 53 安顺气象站1957- 项目区多年平均降雨量 mm 1330 2 园区计划 计划面积 亩 14232 5片区 I#片区 亩 3830 II#片区 亩 3210 试点区 III#片区
10、亩 1796 IV#片区 亩 1876 V#片区 亩 3420 精品区 亩 100 试点区 3 关键供水水源 将军岩泵站以上集水面积 K㎡ 1218.1 取水水源:大屯河 付家摊泵站以上集水面积 K㎡ 227.1 取水水源:大屯河 4 浇灌定额 花卉类 M³/亩 100 金刺梨 M³/亩 50 中草药 M³/亩 30 5 年用水量 山区现代水利计划区 万M³ 126.73 实施试点区 万M³ 29.64 6
11、 关键建筑物及设备 6.1 山区现代水利计划区 拦河堰整改 座 2 提水泵站 座 2 总功率550KW 灌面 亩 14232 排涝渠 M/条 380/1 水利自动化和信息化 亩 14232 山塘整改 座 4 6.2 其中:实施试点区 提水泵站 座 1 总功率330KW 输水干管 Km 2.06 精品区高效节水喷灌 亩 100 官网13.2km,喷头2280套 排涝渠 M/条 380/1 水利自动化和信息化 亩
12、 3310 含1个泵站 1.2.2关键经济技术指标 项目总体计划投资估算2151.40万元,实施方案投资700.31万元,建筑工程投资253.42万元,机电设备及安装工程149.74万元,金属结构设备及安装工程170.09万元,施工临时工程1352万元,独立费用80.19万元,基础预备费33.35万元。 1.3关键建设内容: 1.3.1将军岩泵站水源工程 该分部工程依据设计图纸,用全站仪进行管轴线测设及现场放线。(1)提水管沟槽开挖、过公路段砼拆除(2)提水管焊接安装、埋设段支墩浇筑、沟槽土方回填;(3)集水池、闸阀井基础开挖、底板混凝土浇筑、侧墙及顶
13、板混凝土浇筑;(4)高位水池基础开挖、主体混凝土浇筑;(5)高位水池周围隶属工程施工;(6)泵房基础开挖、主体砌筑、(7)屋面混凝土浇筑,(8)机电设备安装及集水池围墙砌筑、周围零星工程施工。 1.3.2管理房及隶属工程 施工过程:该分部工程先依据设计图纸,用水准仪及全站仪进行管理房独立基础轴线测量及现场放线。(1)管理独立基础开挖、混凝土浇筑;(2)管理房一层主体结构混凝土浇筑;(3)管理房二层主体结构混凝土浇筑;(4)管理房屋面主体结构混凝土浇筑;(5)管理主体模板及外架拆除;(6)管理房主体填充墙砌筑、二次结构施工(7)管理室内、外装修及门窗安装(8)管理室外隶属零星工程施工。 1
14、3.3小濛弄排洪渠工程 施工过程:该分部工程先依据设计图纸,用水准仪及全站仪进行小濛弄排洪渠中轴线测量及现场放线。(1)排洪渠原渠道杂草灌木清除、土石方开挖(2)排洪渠侧墙砌筑;(3)排洪渠勾缝及抹面;(4)排洪渠侧墙C15砼压顶浇筑。 1.4 设计变更情况 1.4.1高位水池底板原设计为10cm厚C15砼找平垫层,但在基础石方开挖施工过程中,设计标高以下最深处有约2.35米深天然溶槽,因基础为岩基,开挖难度大,为确保基础平整性及安全性,经参与单位现场研究决定,先将高位水池基础溶槽采取C15埋石砼回填,然后再用C15砼将基础垫层找平0.3m,依据各参建单位现场收方测量数据,C15埋
15、石砼回填平均深度为0.83米。 1.4.2高位水池闸阀室基础在坑洼之地松动岩石之上且四面为高边坡,山体水流较多、较急。为预防溢流管管、排污管和四面山体水流长久对闸阀室基础冲刷,确保基础稳定性和水池周围排水通畅,经参建单位现场研究决定:先在闸阀室前砌筑一条顶宽(0.6m,底宽为1.2m高度约1.4m,长9m)M7.5浆砌石堡坎,堡坎内用石渣回填至地坪基础面,上铺10cm厚碎石垫层,再在水池四面浇筑10cm厚C15砼地坪。 1.4.3将军岩上水管水击泄放阀安装过程中,为确保在上游管道压力升高时能立即将上游压力水泄放。经参建单位现场研究决定:需在水击泄放阀处配套一根长约8米Φ325螺旋钢管泄水。
16、 1.4.4管理房二楼框架柱表面原设计为仿石材外墙漆,为管理房外墙装饰整体配套性及美观性。经参建单位现场研究决定:将二楼框架柱用防腐木板进行外包装饰,总长度约为56.4米。 1.4.5将军岩集水池安装较多机电及金属设备,为预防路人进入破坏和考虑到安全性,经参建单位现场研究决定:在集水池周围增设高4.2m、厚0.3mM7.5浆砌石围墙,外墙铺设青石板,门窗采取不锈钢护栏,围墙上增设玻璃钢瓦拱形屋顶,围墙外增设C20砼地坪及排水沟。 1.4.6将军岩拦河堰工程因拦河堰坝顶两侧均为岩石坡体,原坝体无损坏渗漏情况,经参建各方现场研究决定将拦河堰作为示范园区二期工程施工。 1.4.7将军岩通村公
17、路至泵房1.5m宽水泥路(240米)占地位置属于猛帮村民养殖场用地,经安顺市西秀区水务局及我单位数次沟通协调无结果,经参建各方现场研究决定取消此段水泥路施工。 1.4.8管理房进场3.5m宽道路工程原设计为路面为10cm厚C15砼硬化,考虑到示范园区二期工程大型重车会破坏路面,经参建各方研究决定取消路面C15砼硬化,作为二期工程施工。 第二章·工程招投标 2.1工程招标 工程发包人为安顺市西水务局,招投标管理机构为贵州聚泰工程建设咨询。 2.2工程投标 我单位经过资格预审,和安顺市西水务局,业主组织投标单位到现场踏勘;并在安顺市公共资源交易中心开标,经评标委
18、员会评审推荐确定海南三亚实业为中标单位,中标价:贰佰陆拾伍万贰仟伍佰肆拾叁元贰角捌分(¥2652543.28元),招投标管理机构于1月6日核准签发中标通知书。 依据业关键求,我单在1月8日和业主签署了施工协议。 2.2.1工程投标程序 依据工程建设招投标制要求,工程投标程序详见图2-1。 工程招标 资格预审 现场踏勘 标书编制 投标 开标 评标 定标 图2-1 工程投标程序图 第三章·施工进度管理 3.1 施工部署标准 依据协议签署工程项目内容,考虑工期短时间紧,场面窄,工程实施整体部署,全方面交叉铺开作业,全方位同时进行,
19、并充足利用其后及空间条件,整体部署标准为: (1) 科学合理部署,统筹安排,确保关键; (2) 优化节省资源配置,实施动态管理,平行、交叉、流水作业努力争取均衡生产; (3) 安全生产,文明施工,保护环境。 3.2 施工部署情况 3.2.1 施工交通部署 (1)场外交通部署 本工程在安顺市平坝区十字乡境内,距杨武乡约2.5km。 (2)场内交通部署 本工程交椅水库施工所需建筑材料及弃碴均采取汽车或手推车运输,故场内需部署一定规模施工道路。 3.2.2 施工场地部署及临时设施 部署内容:①备料场、②拌和系统、③钢筋模板加工场、④宿舍、 ⑤仓库、⑥施工机械停放场、⑦风、水
20、电系统等。 3.2.3拌和部署 A、混凝土拌合系统部署 部署规模:依据招标文件提供工程量和依据施工进度要求,混凝土拌和系统生产规模依据施工生产要求进行设备选择和部署。 设备选择:JQ350拌和机2台。 部署:因施工场地相互影响,选择在管理房部署砼拌和站,另一拌和机依据浇筑段机动选择合适位置即拌即用。 B、制浆站部署 本工程制浆站依据浇筑现场采取移动式搅拌。 (2)模板加工场 部署:部署管理房右侧边施工营区边位置,方便于管理。 (3)机械修配、停放场 本工程采取机械化施工,须在工地进行机械修理和日常保养工作。机械修配、停放场部署见施工总平面图;占地面积80
21、m2。 (4)施工生活用房及办公室 全部用房采取租、建结合方法,总标准是满足需要和便于管理。 (5)施工用仓库 部署:部署在管理房右侧面。 面积:建筑面积为300m2。 (7)风、水、电系统 风:本工程石方开挖量小,故暂不考虑供风系统问题。 水:安装2台IS65-40-20型潜水泵,即可满足施工用水要求。生活用水和当地村民共用。 电:我单位进场即依据协议安装10KV变压器,采取三相四线供施工用电。 3.2.4施工导流及水流控制 我单位结合相关水文资料及现场踏勘情况看,河内水位降至死水位,全部排出弃水均经过潜水泵排向下游。 3.3施工进度
22、 本工程于1月8日签署施工协议,协议工期90日历天,实际工期307日历天,较协议工期延误203天,因施工过程中受土地协调、春节放假、设计变更及气候影响造成工期延误。 工程实际进度情况以下: (1) 年1月8日和建设单位签署施工协议;同时进场做好施工前期准备工作。 (2)本工程施工进度 将军岩泵站水源分部工程: 于1月12日开工,10月20日工程完工; 管理房及隶属分部工程: 于3月7日开工,11月14日完工; 放水建筑物分部工程: 于4月25日开工,7月1日工程完工; 附表3.1: 工程量完工对比表 项目 编号 工程项目或费用名称 单位 协议工程量 实际完
23、成工程量 备注 第二部分 建筑工程 一 将军岩泵站水源工程 (一) 将军岩拦河堰整改 1 土方开挖 m³ 87 2 石方开挖 m³ 18 3 土石回填 m³ 71 4 清淤 m³ 180 5 30cm厚M7.5浆砌石护坦 m³ 29 6 30cm厚C15钢筋砼防渗墙 ㎡ 79 7 沥青砂浆止水(分缝) m³ 9 8 钢筋制安 t 4.69 9 模板
24、 m³ 277 10 帷幕灌浆 m 54 二 将军岩提水泵站工程 (一) 集水池工程 1 土方开挖 m³ 221 234.96 2 石方开挖 m³ 55 29.44 3 土石回填 m³ 46 93.63 4 清淤 m³ 230 5 进水口过滤网 个 1 1.00 6 15cm碎石垫层 m³ 1 7 10cm厚细砂垫层 m³ 1 8 闸阀井 ㎡ 4 4.00
25、 (1) 土方开挖 m³ 5.6 23.26 (2) 石方开挖 m³ 2.4 (3) C20钢筋砼顶板 m³ 0.47 0.24 (4) C20钢筋砼盖座 m³ 0.2 0.20 (5) C15砼底板(C15cm厚) m³ 0.58 0.58 (6) 3cm厚M10水泥砂浆抹面 ㎡ 11.8 16.56 (7) M7.5水泥砂浆砌砖 m³ 1.7 1.68 (8) 钢筋制安 kg 0.06 36.24 (9) 碎石垫层 m³ 1.2 1.15
26、 8 C15埋石混凝土边墙 m³ 64 55.06 9 C15埋石混凝土底板(30cm厚) m³ 11 10.80 10 10mm厚M10水泥砂浆抹面 ㎡ 61 11 钢管固定扣件 个 3 12 Φ16钢筋爬梯 t 0.1 13 C20钢筋混凝土顶板(12cm) m³ 5 4.32 14 手动葫芦(2t) 个 1 15 C15砼踏步 m³ 8 0.98 16 10cm厚碎石垫层 m³ 3 12.93 17 M7.5
27、浆砌石衬砌 m³ 8 18 防渗土工布 ㎡ 40 19 C15砼支墩(50cm厚) m³ 2 15.62 20 C20砼镇墩 m³ 3 47.61 21 安全标示牌 个 3 22 DN50镀锌钢管围栏 m 100 23 DN25镀锌钢管围栏 m 100 24 钢筋制安 t 0.48 0.46 25 模板 ㎡ 202 195.38 (二) 泵房工程 1 泵房工程 ㎡ 14.4 14.39
28、 (三) 1.5M宽水泥路(240m长) 1 土方开挖 m³ 196 2 石方开挖 m³ 49 3 弃渣回填 m³ 40 4 10cm厚C15砼路面 m³ 38 5 10cm厚碎石垫层 m³ 38 6 20cm厚块石垫层 ㎡ 75 7 M7.5浆砌石路沿 m³ 93 (四) 提水管工程(880m) 1 土方开挖 m³ 755 1065.63 2 石方开挖 m³ 190 1
29、6.02 3 土石回填 m³ 835 965.95 4 砂垫层 m³ 55 5.08 5 镇墩C15混凝土 m³ 55 6 M7.5浆砌石边墙 m³ 19 9.45 7 C30钢筋砼盖板(30cm厚) m³ 5 3.98 8 C15外包砼 m³ 25 6.86 9 C15混凝土路面(20cm厚) m³ 98 10.89 10 钢筋制安 t 3.9 1.41 11 干砌块石 m³ 32 12 砌体拆除 m³ 6
30、 13 闸阀井 ㎡ 24 5.50 14 模板 ㎡ 250 153.95 (五) 高位水池(600m³) 1 土方开挖 m³ 114 23.59 2 石方开挖 m³ 172 212.34 3 石渣回填 m³ 297 25.72 4 C15混凝土垫层(10cm) m³ 20 57.31 5 C25混凝土顶板(18cm) m³ 37 30.82 6 C25钢筋混凝土池壁(25cm) m³ 49 50.70 7 C25混
31、凝土底板(20cm) m³ 41 25.26 8 C25钢筋混凝土柱(30cm*30cm) m³ 14 10.49 9 模板(梁板柱) ㎡ 363 245.35 10 曲面钢模板 ㎡ 420 404.52 11 钢筋 t 9.8 10.712 12 Φ20钢筋爬梯 t 0.1 0.04 三 管理房工程 (一) 管理房 1 管理房主体结构 ㎡ 399.57 317.93 2 15cmC15砼底板(地坪) m³ 1
32、10 73.81 3 碎石垫层 m³ 55 72.08 4 地坪围栏 m 150 (二) 3.5m宽水泥路(150m长) 1 土方开挖 m³ 221 584.20 2 石方开挖 m³ 55 3 弃渣回填 m³ 25 4 10cm厚C15砼路面 m³ 54 5 10cm厚碎石垫层 m³ 54 92.85 6 20cm厚块石垫层 m³ 108 185.71 7 M7.5浆砌石路沿 m³ 62 72.2
33、9 四 观景台至管理房引水管(550m) 1 沟槽土方开挖 m³ 332 133.06 2 沟槽石方开挖 m³ 38 3 土石回填 m³ 320 133.06 4 砂垫层 m³ 18 5 15cm厚C15砼外包 m³ 8 6 C15砼镇墩 m³ 6 7 模板 ㎡ 24 9 钢筋 t 0.36 五 排洪渠工程 (一) 渠道工程(380m) 1 土方
34、开挖 m³ 1803 2134.02 2 石方开挖 m³ 200 65.52 3 弃渣回填 m³ 739 841.65 4 M7.5浆砌石边墙 m³ 1199 1008.29 5 3cm厚M10水泥砂浆抹面 ㎡ 1240 1172.30 6 砂石反滤包 m³ 40 8.04 7 10cm厚C15混凝土压顶 m³ 2 33.97 8 不良地质处理(块石垫层) m³ 38 (二) 交通桥工程 1 C20钢筋混凝土桥墩帽 m³
35、 3 2 C25钢筋混凝土桥面板 m³ 4 3 钢筋 t 0.9 第六部分 协议内新增工程 一 将军岩提水泵站工程 (一) 集水池及提水管工程 1 土方开挖 m³ 3.50 2 C15砼 m³ 12.93 3 C20砼 m³ 6.27 4 M7.5水泥砂浆砌砖 m³ 15.85 5 M10水泥砂浆抹面 ㎡ 71.09 6 Φ325螺旋钢管(壁厚6
36、mm)刷防锈漆 ㎡ 967.93 7 不锈钢窗 ㎡ 42.54 8 不锈钢门 ㎡ 9.71 9 青石板 ㎡ 105.49 10 玻璃钢棚 ㎡ 107.60 11 等径三通管(DN325) 个 2.00 12 模板 ㎡ 51.04 13 锚杆 m 180.00 14 水利管道混凝土桩 个 9.00 15 清淤 m³ 5.10 16 C15埋石砼侧墙 m³ 6.28
37、 17 碎石垫层 m³ 0.23 18 C15砼底板 m³ 0.23 21 C20钢筋砼盖板 m³ 0.63 22 钢筋制安 t 0.13 (二) 泵房工程 1 C15埋石砼基础 m³ 5.57 (三) 高位水池 1 C15埋石砼回填 m³ 79.28 2 M7.5浆砌石边墙 m³ 9.61 3 10cmC15混凝土压顶 m³ 0.53 4 C15砼底板(地坪
38、 m³ 9.53 5 碎石垫层 m³ 9.53 二 管理房工程 (一) 管理房 1 管理房水电安装 ㎡ 317.93 2 进户电力电缆17米 m 17.00 3 6套方形吸顶灯(LED,25W,三色) 套 6.00 4 PVC扣板吊顶 ㎡ 22.97 5 石膏板吊顶 ㎡ 50.54 6 外墙文化石 ㎡ 172.38 7 U形木板包柱 m 60.20
39、 8 门补差价 元 9 窗补差价 元 (二) 管理房室外工程 1 土方开挖 m³ 281.31 2 土石回填 m³ 37.54 3 C20砼底板 m³ 3.08 4 M10/M7.5水泥砂浆砌砖 m³ 24.91 5 M10水泥砂浆抹面 ㎡ 34.73 6 C20钢筋砼顶板 m³ 2.65 7 钢筋制安 t 0.59 8 模板 ㎡ 11.64
40、 9 φ700混凝土井盖(加重型) 套 2.00 10 青石板 ㎡ 30.89 11 青石板砖(30*60) ㎡ 529.77 12 DN300 HDPE双壁波纹管 m 8.50 第四章·关键工程施工方法 4.1土石方明挖工程施工 4.1.1 工程情况 本工程土石方明挖工程总量为:土石方开挖:4806.85m³。 4.1.2土方开挖施工 4.1.3土方开挖施工程序 表土、砂砾石、岩石,和小于或等于0.5m3孤石或岩块等直接使用机械开挖。土方工程开挖施工程序见下框图。 测量放样 植被、表土
41、清理 开挖运 输2-20输 弃渣平整 4.1.4土方开挖施工方法 依据土方开挖施工程序框图,土方开挖各项目施工方法以下: ⑴、测量放样:工程施工前,测量人员依据设计提供测量控制网进行施工控制网加密,施工测量控制网设置采取全站仪进行。控制测量放样结果交监理工程师复核确定后方可作为施工测量依据。土方施工前测量人员会同监理工程师依据设计开挖范围进行工程原始地形断面测量,测量结果交监理工程师审核确定后方可进行土方开挖。土方工程开挖结束后立即会同监理工程师进行完工断面测量确定,为工程计量提供依据。 ⑵、植被、表土清理:土方工程施工前,采取机械配合人工对开挖工程区域内全部树根
42、杂草、垃圾、废碴和工程师指明其它有碍物进行清理。清理范围为开挖边界线或建筑物基础外侧3~6m水平距离。凡属无价值可燃物,采取就地焚烧,在焚烧期间,必需采取必需防火方法。如无法烧尽或严重影响环境清除物,必需按工程师指定地域进行掩埋,不得妨碍自然排水或污染河川。清除有机土壤按工程师指定位置堆放,并采取有效方法,预防土壤被冲刷流失,后期利用于工程环境保护。砍伐成材或清理取得含有商业价值材料按监理工程师指定位置进行堆放。 ⑶、土方开挖运输: 土方明挖关键采取0.3m3反铲开挖, 5t自卸汽车运输至指定位置堆放。土方边坡经反铲开挖后留一定修整余量再采取人工修整以满足设计图纸要求坡度和平整度。 4
43、1.5施工安全方法 依据以往经验,经过有经验人员对工地定时进行巡视检验,巡视内容包含施工现场相关信息,和施工质量事故情况,立即发觉,采取有效处理方法。 4.1.6质量检验和验收 在施工中严格根据设计要求及施工规范作业,开挖误差符合DL/T5099-1999条要求。并对开挖边坡进行安全清理后立即会同监理、业主、质检进行立即验收回填。 4.2浆砌石工程施工 4.2.1工程简述 本工程浆砌石关键为小濛弄排洪渠侧墙及路沿。 4.2.2工程材料材质要求 砌石材料应材质坚硬新鲜,无风化剥落或裂纹;石材表面无污垢、水锈等杂质;用于表面石材应色泽均匀;石料物理力学指标应符合施工图纸要求。本工
44、程所用石料起源有两条:外购及原砌体拆除余料,满足材质要求。 砂浆采取砂料:要求粒径为0.15~5mm,细度模数为2.5~3.0,工程用砂采购自白石岩砂场材料合格。 水泥:砌筑工程采取水泥品种为PC32.5安顺平坝台泥水泥,到货水泥应按品种、标号、出厂日期分别堆存,受潮湿结块水泥严禁使用。 水: 直接到河内抽水。 4.2.3砌体工程施工 4.2.4浆砌石砌筑施工满足以下要求 砌石体采取铺浆法砌筑,砂浆稠度应为30~50mm,依据气温改变时做合适调整。 采取浆砌法砌筑砌石体转角处和交接处同时砌筑,对不能同时砌筑面,留置临时间断处,并应砌成斜槎。 砌石体尺寸和位置许可偏差,不应超出G
45、B50203—98表6.1.6中要求。 4.2.5浆砌块石砌体 浆砌块石施工按以下要求:齿槽按设计开挖后,清洗洁净;满足设计及规范要求,经过检验验收合格并经监理工程师签证后,进行砌筑施工。 ⑴、选材及冲洗:选择合格石料,进入施工面前全部冲洗洁净;砂和水泥是经检验合格产品(安顺西南水泥)。 ⑵、砂浆拌制及运输 本工程浆砌石用砂浆依据设计要求,配合比由试验确定,砂浆采取0.35m3拌和机拌制,砂浆搅拌时间不少于2min(若因特殊情况进行人工拌和, “三干三湿”拌和后使用)。运输采取搭梭槽及胶轮车运至工作面,施工用砂浆随拌随用,严禁在使用过程中随意加水,施工间歇时间符合规范要求。 ⑶、砌
46、筑 工程全部砌体严格根据浆砌石施工规范进行砌筑,均满足设计要求。 4.2.6砌体工程验收 ⑴、砌体工程砌筑前进行砌筑体测量放样结果检验和基础面开挖清理质量检验和验收。 ⑵、在砌体工程砌筑过程中按规范要求对砌体工程各项材料和砌体砌筑质量进行检验和验收 ⑶、完工验收:每项砌体工程完工后,按本协议要求申请完工验收,并提供相关完工验收资料。 4.3 混凝土工程施工 4.3.1混凝土拌制程序及说明 混凝土拌和可用1台0.35 m3拌和机,部署在大坝及溢洪道周围,混凝土运输用胶轮车运输。 ⑴、原料准备 A、水泥:采取安顺西南水泥; B、砂:周围砂场购置; C、碎石:石子粒径、级配及
47、加工料场符合混凝土配合比通知单要求,在周围砂场购置。 D、水:从河道抽水,其水质符合《混凝土拌和用水标准》 JGJ63—89要求。 ⑵、拌和过程及说明 多种配料计量: ①砂、石计量:砂、石料采取体积计量; ②水泥计量:搅拌时采取袋装水泥,以袋为计量单位; ③水计量:水必需正确计量,其许可偏差应≤±2%。 ⑶、上料及拌和:将计量好原料先汇于料斗内,进行拌和,其上料 次序为:石子 水泥 砂 掺合料 水 外加剂。混凝土拌和按相关程序进行。 ⑷、出料及拌制混凝土质量检验 ① 质量员应检验拌制混凝土所用原料品种、规格和用量,
48、每一个工作班最少检验两次。 ②检验混凝土坍落度及和易性,每一工作班最少两次,混凝土拌和物应搅拌均匀,颜色一致,含有良好流动性、粘聚性和保水性,不泌水,不离析。不符合要求应查找原因,立即调整。 ③混凝土搅拌和时间及程序按规范实施。 ④拌制混凝土应留试块作试验检验。 4.3.2混凝土拌和工艺步骤图 混凝土拌和工艺步骤图见图4.4-1 搅 拌 和易性检验 出 料 制 作 试 块 试 验 运 输 坍 落 度 检 查 质 量 检 查 制 作 试 块 试 验 运 输 4.3.3混凝土浇筑程序、施工方法及说明 ⑴
49、混凝土浇筑工艺步骤图: 测量放样 建基面清洗洁净并打毛 立模、清理模板 钢筋混凝土挷扎钢筋 混凝土 拌 制 混凝土入仓浇筑 振 捣 养 护 拆 模 ⑵、浇筑混凝土前建基面清理在地基或需要浇筑基础面上,需将淤泥、杂物等清理洁净,并设有防水和排水方法。对于干燥面用水浇润,但表面不得留有积水。 ⑶、模板工程:采取模板标准木模。使用模板前先清理校正模板,安装好后,应吊线进行尺寸复核,使检验支撑是否可靠,检验需要预留孔及固定埋件是否到位,并清理洁净模板内杂物,对于木模,在浇筑前还要用清水浇湿。 模板拆除:
50、待混凝土强度达成要求后,方可拆除,拆除模板按指定地方堆放,并立即清洗洁净,待下次反复使用。 模板拆除次序和方法,应遵照先支后拆,先拆非承重部位后拆承重部位和自上而下标准进行。拆模时,严禁用大锤和撬棍硬砸硬撬,在注意保护混凝土表面及棱角不受损坏。 (4)钢筋制作安装 1)在钢筋使用前,遵照相关施工规范,对钢筋进行常规性检验,合格才能用于工程施工。结构钢筋依据钢筋配料表所列钢筋型号、种类、数量等加工成型, 自卸车运至施工现场,吊车或反铲吊运入仓。 2)作业队现场施工技术人员依据设计图纸并对照钢筋配料表指导熟练施工人员进行钢筋安装,直径在25mm以下钢筋采取绑扎或焊接;直径在25mm及以上钢