资源描述
九院小区三期室外管网施工组织设计
目 录
1、施工组织设计···················································· 2
1.1编制依据·························· 2
1.2工程概况及施工条件··········································3
1.3施工目标····················································4
1.4主要施工方法简介············································4
1.5施工程序····················································5
1.6主要分部分项施工方法···················· 6
1.6.1 施工测量···············································6
1.6.2 施工开挖注意···········································5
1.6.3 给水、消防管线施工······································7
1.6.4 污水管线施工··········································12
1.6.5 雨水管线施工··········································16
1.6.6 热力管线施工··········································19
2. 项目班子机构及劳动力安排·······································35
2.1 项目班子机构:·············································37
2.2劳动力安排················································41
3.质量保证体系和保证措施··········································24
3.1建立完善、全面的质量管理体系································24
3.2建立健全完善的质量保证体系································24
3.3建立严格的工地质量管理制度·································24
3.4建立严格的材料进场管理制度································24
3.5建立完善质量检测体系·······································25
3.6建立完善的施工试验及送检制度 ······························25
3.7质量保证措施···············································26
3.8施工技术交底···············································30
3.9质保资料的整理、存档······································31
4.安全保证体系和保证措施··········································31
1、施工组织设计
1.1编制依据
本工程施工组织设计按照建设单位招标及答疑文件等的要求和现场周边环境进行编制,未提之处均按照施工图纸设计、国家现行技术规范、规程、质量评定标准以及有关文件等要求的具体规定进行施工。编制依据如下:
(1)《室外给水设计规范》〈GB50013-2006〉;
(2)《建筑给水排水设计规范》〈GB50015-2003〉(2009年版);
(3)《建筑设计防火规范》〈GB50016-2006〉;
(4)《建筑给水排水及采暖工程施工质量验收规范》〈GB50242-2002〉;
(5)《给水排水管道工程施工及验收规范》〈GB50268-2008〉;
(6)《城镇给水排水技术规范》〈GB50788-2012〉;
(7)《湿陷性黄土地区建筑规范》〈GB50025-2004〉;
(8)《湿陷性黄土地区室外给水排水管道工程构筑物》〈S531-1~5〉;
(9)《室外排水设计规范》〈GB50014-2011〉;
(10)《给水排水构筑物工程施工及验收规范》〈GB50141-2008〉;
(11)《城镇供热管网设计规范》 <CJJ34-2010>
(12)《城市供热管网工程施工及验收规范》<GJJ28-2004>
(13)《城镇直埋供热管道工程技术规程》<CJJ/T81-98>
(14)《直埋供热管道工程设计》
(15)《室外排水设计规范》〈GB50014-2011〉
(16)《埋地聚乙烯排水管道技术规程》〈CECS164:2004〉;
(17)《城镇给水排水技术规范》〈GB50788-2012〉;
(18)九院小区三期工程及室外管线综合图设计.
(19)太原市气象资料
(20)本工程管线综合规划图、竖向规划设计图及单体建筑给排水专业施工图;
(21)甲方委托的设计任务合同书;
(22)现行的其它有关规范及规程。
1.2工程概况及施工条件
本工程为太原市九院小区三期室外工程施工图设计。本工程位于山西省太原市万柏林区,九院小区三期西邻开城路,南邻纬二路,东临西山北外环路,整个地块东西长约370.0m,南北长约130.0m。地势西高东低,南高北低,场地坡度较为陡峭。本工程总建筑面积约为170047.0m2,总户数约1930户(3.5人/户)。
地质情况:本工程拟建场地为自重湿陷性场地,湿陷等级为Ⅲ级。勘察期间,本场地在勘察深度范围内,未揭露地下水。
施工条件:2014年由于室外地下管线、挡土墙、庭院与主楼裙楼、独立商铺、办公楼同时施工,为了互不影响施工,最先进行2#楼消防水池方涵及各化粪池施工。
1#、2#楼主楼北边东西走向管线和1#楼西边管线以及3#、4#楼北边东西走向管线受主楼施工影响,不能进行施工,待主体结构封顶后进行施工。
10米小路上地下管线计划通长施工,为保证1#楼主楼施工材料及运输,须在10米小路开成路口处开门。
施工经二路两侧所有地下管线施工时,需要封堵纬二路西边大门。
为保证不影响4#楼主楼以及管线施工,保证材料运输,须在4#楼南边围墙处开门。
3#、4#楼主楼南侧管线在纬二路上,为了不影响主楼施工(材料运输、浇筑主楼混凝土纬二路上需支泵车及罐车运输),则纬二路路面及树木不能进行破坏。纬二路上管线须在3#、4#楼主楼施工完毕后进行破路面及拆除马路牙和迁移树木后,方可进行施工。
1.3施工目标
(1)进度目标:室外工程计划于2014年3月20日开工,2015年9月1日竣工。
(2)质量目标:工程质量达到“合格”标准,争创“市优”。
(3)安全目标:杜绝死亡、重伤事故,轻伤事故频率控制在2‰以内。
(4)文明施工目标:文明现场达标,创太原市文明施工样板工地。
(5)环境保护目标:降低施工噪音,减少大气污染,控制污水排放,保持环境整洁。
1.4工程的重点和难点
2014年九院工程可分为三个主要目标及管理重点:第一个是商铺主体及内装饰安装工程,第二个是室外管网道路及配套工程,第三个是主体及二次结构装饰安装工程。三个目标即独立又相互交叉,室外工程影响商铺的竣工,主体工程影响室外工程衔接。在不便于施工的条件下,努力创造施工条件,对室外管网进行划分区段进行施工,在保证不影响主体结构施工的情况下,同时开展室外管网的施工。
1.5施工程序
由于室外地下管线、挡土墙、庭院与主楼裙楼、独立商铺、办公楼同时施工,为互不影响,室外管网施工初步计划分两段进行施工,第一段施工不影响主体结构施工的各管线,待各楼主体施工完毕后,进行第二段其余管线施工。
第一段室外管网施工计划2014年3月份中旬开始,首先进行施工的室外管网部位和时间如下:
①、3月20日开始进行2#楼消防水池处方涵及管沟施工。
②、4月20日开始进行10米小路上所有管线施工(从东边六建围墙处至经二路交叉口),为保证室外管网施工,不受主体施工影响,拟定分段施工,为保证分段施工的可操作性,10米小路计划通长施工,在10米小路开成路口处开门,以保证1#楼主体施工材料的进场。;
③、4月20日开始进行1#楼、2#楼化粪池施工。
④、5月20日开始进行1#楼裙楼、2#楼裙楼南边所有管线施工;
⑤、5月20日开始进行4#楼北边的所有管线施工,确保在6月底完成。然后将4#楼原钢筋棚移至4#楼东北角,进行原钢筋棚处的管线施工(在4#楼东南角开门,作为施工通道)。
⑥、6月份开始经二路两侧所有管线施工,7月底结束(封堵纬二路西边大门)。
⑦、6-8月份,进行4#楼原钢筋北区所有管线施工。
⑧、确保8月10日完成所有主体结构施工,9月份开始进行主楼南侧以及其余室外管网施工。同时,10月中旬开始进行现场庭院、造型以及护坡等施工。
第二段室外管网施工:待主体结构施工完毕后,进行第二段室外管网其余管线施工。
1.6主要分部分项施工方法
1.6.1 施工测量
1)、进入现场后,先探明地下各类管线,若遇重要管线,应及时通知甲方,进行保护。
2)、进入施工现场后,根据设计资料和建设单位交付的控制点,认真校核各控制点高程及坐标,若与现状不符,应及时与设计单位和甲方联系。
3)、导线复测采用全站仪,原有导线点不能满足施工要求时,应进行加密。
4)、施工过程中,测量人员对平面和水准测量应准确及时,并应及时向施工人员提供测量数据并现场交桩,测量标志应坚固稳定,施工人员对测量标志应认真保护。
5)、编制详细的施工测量方案,严格执行测量复测制度,并对所有的测量成果进行记录整理。
6)、技术负责人应会同设计或勘测部门现场交接中线控制桩和设计水准点,并设置护桩,临设水准点应与设计水准点复测闭合。
1.6.2 施工开挖注意
1)、施工前,应对开槽范围内的地上地下障碍物进行现场核查,逐项查清障碍物构造情况,以及与工程的相对位置关系。建议采取物探、坑探等方法查明地下管线和设施以防对其他地下管线和设施造成破坏,并在开挖过程中采取措施加以保护。当开挖管沟发现发现文物时,应采取措施保护并及时通知文物管理部门。
2)、土方开挖中发现事先未查到的地下障碍物时应停止施工。应采取措施并经有关单位同意后,再进行施工。
1.6.3 给水、消防管线施工
本工程的水源除换热站由九院二期供给外,其它水源均为本小区南侧市政路纬二路上的市政供水管线供给,市政入口压力为0.4MPa,其水质必须符合国家现行生活饮用水卫生标准的要求。
1.6.3.1、管线布置:室外给水工程从本小区南侧纬二路接入市政给水管线后分两路供水,一路JS管线供给各个商铺,一路J1管线直供给各楼座低区生活用水、泵房中的无负压设备和消防水池;各楼座中、高区生活用水由J1管道直接接至泵房无负压设备,经叠压加压后分别供给各楼座(1#、2#、3#、4#号楼所共用的无负压设备与廉租房所使用的无负压设备相互独立);消防用水由消防水池经吸水管吸至消防泵加压后沿管道(其管道出泵房绕本小区外围成环敷设)分别供给个楼座,以满足各楼座室内外消防用水量需求。
1.6.3.2、管材及接口:消防给水管采用内外壁热浸镀锌钢管,其接口采用法兰连接;生活给水管和商铺给水管采用钢丝网骨架塑料(聚乙烯)复合管,其接口形式为热容连接。
1.6.3.3、管道敷设、基础及回填;管道敷设:本小区北侧部分管线由于场地局限,管线敷设方式采用管沟敷设;本小区东侧、南侧和西侧部分管线由于不满足三级湿陷性黄土地区建筑物对管道防护距离的要求,管线敷设方式为检漏沟敷设;其余管线均采用直埋敷设。其中管沟做法见室外热力管道施工图;检漏沟做法参见图集04S531.
管道基础及回填土:根据单体提供,本工程地质情况为:1#、1#裙楼、3#、4#及3#和4#间的裙楼为Ⅲ级自重湿陷性黄土,2#、廉租房为Ⅱ级自重湿陷性黄土;给水管线不满足对湿陷性黄土地区防护距离要求的(在Ⅲ级自重湿陷性场地,甲类建筑的防护距离为8.0~9.0m,丙类建筑的防护距离为6.0~7.0m;在Ⅱ级自重湿陷性,甲类建筑的防护距离无要求,丙类建筑的防护距离为5.0m),应做检漏沟(选用C型H×B:1200X1800和C型H×B:600X600,具体做法见国标04S531)或消除全部湿陷量(全部换3:7灰土);满足防护距离的管道基础应原土夯实后做50cm厚3:7灰土垫层,再铺10cm中粗砂垫层,沟槽回填土时,管道管腔至管顶部分及管顶以上0.5米范围内回填土均应采用中粗砂回填,管顶0.5米(0.5米~1.0米)以上范围内回填土采用原土回填。
1.6.3.4、直埋管道回填土压实度:管道管腔至管顶以上0.5米范围内,管顶部分回填土压实系数为0.85;管道两侧管底至管顶部分回填土压实系数不应小于0.95;管顶至管顶以上0.5米范围内,管道两侧压实系数不应小于0.90;管外顶0.5米以上(0.5米~1.0米)范围内,管顶及管道两侧压实系数不应小于0.90。
1.6.3.5、管道埋深及管道防腐:给水主干管及支管埋深1.2m以下。生活给水管线与其它市政管线有交叉的遵循有压管让无压管、可弯曲管让不易弯曲管、分支管让主干管、小管让大管的原则避让。
直埋热镀锌钢管防腐采用加强级管道防腐层,防腐层厚度不小于6mm(金属表面—冷底子油—沥青涂层—加强保护层—沥青涂层—外保护层)。
1.6.3.6、标准图集选用:
1)阀门井选用矩形钢筋混凝土阀门井(做法详见国标04S531);
2)水表井选用钢筋混凝土矩形水表井(井做法参见国标05S502);
3)室外消火栓:室外消火栓井做法参见国标04S531,消火栓安装做法参见国标01S201(SA100/65型,室外地下式消火栓安装(支管深装式);
各种给水附属构筑物均采用Φ700铸铁井盖及支座,井盖过汽车者采用重型井盖及井盖支座,不过汽车者采用轻型井盖及井盖支座。井内踏步采用铸铁踏步。铸铁井盖顶面中间空白处应标识给水,以示区别。
1.6.3.7、管道试压:
1)管道安装完毕后按验收规范规定对管道系统进行强度及严密性试验,以检查管道系统及各连接部件的产品及安装质量。
2)各种承压管道系统和设备应做水压试验,其中生活给水管道中,低区给水管的设计工作压力为0.40MPa,试验压力为0.80MPa;中区给水管道的设计工作压力为1.01MPa,试验压力为1.52MPa;高区给水管的设计工作压力为1.26MPa,试验压力为1.89MPa。其中消防给水管道中,室内消防室外管线低区的设计工作压力为1.06MPa,试验压力为1.56MPa;室内消防室外管线高区的设计工作压力为1.60MPa,试验压力为2.10MPa;室外消防管道的设计工作压力为0.40MPa,试验压力为0.90MPa;自动喷淋管道的设计工作压力为0.80MPa,试验压力为1.40MPa。试压按《给水排水管道工程施工及验收规范》〈GB50268-2008〉第9.2.10条规定进行管道水压试验。
1.6.3.8、管道冲洗消毒:给水管道在竣工后,必须对管道进行冲洗,饮用水管道还要在冲洗后进行消毒,并经有关部门取样检验,符合国家《生活饮用水标准》方可使用。检验方法:观察冲洗水的浊度,查看有关部门提供的检验报告。
1.6.3.9、生活用水及消防用水量
生活用水量(根据单体提供):
1)1#楼生活用水量:1区商铺部分最高日用水量为20.70m³/d,最高日最大时用水量为2.42m³/h;1区住宅部分最高日生活用水量为32.76m³/d,最高日最大时用水量为3.41m³/h;2区最高日生活用水量为114.66m³/d,最高日最大时用水量为11.94m³/h;3区最高日生活用水量为98.28m³/d,最高日最大时用水量为10.24m³/h。
2)2#楼生活用水量:1区商铺部分最高日用水量为25.92m³/d,最高日最大时用水量为3.03m³/h;1区住宅部分最高日生活用水量为31.50m³/d,最高日最大时用水量为3.29m³/h;2区最高日生活用水量为88.20m³/d,最高日最大时用水量为9.19m³/h;3区最高日生活用水量为69.30m³/d,最高日最大时用水量为7.22m³/h。
3) 3#楼生活用水量:1区商铺部分最高日用水量为23.54m³/d,最高日最大时用水量为2.75m³/h;1区住宅部分最高日生活用水量为44.10m³/d,最高日最大时用水量为4.59m³/h;2区最高日生活用水量为88.20m³/d,最高日最大时用水量为9.19m³/h;3区最高日生活用水量为50.4m³/d,最高日最大时用水量为5.25m³/h。
4) 4#楼生活用水量:1区商铺部分最高日用水量为12.59m³/d,最高日最大时用水量为1.47m³/h;1区住宅部分最高日生活用水量为50.4m³/d,最高日最大时用水量为5.25m³/h;2区最高日生活用水量为88.20m³/d,最高日最大时用水量为9.19m³/h;3区最高日生活用水量为44.10m³/d,最高日最大时用水量为4.59m³/h。
消防用水量 (根据水单体提供):
1)、消防用水量1#、2#、3#,其室内消火栓系统的用水量为20L/S ,火灾持续时间为2小时;室外消火栓系统的用水量15L/S ,火灾持续时间为2小时;自动喷淋系统的用水量为23L/S,火灾持续时间为1小时。
2)、消防用水量4#楼,其室内消火栓系统的用水量为40L/S ,火灾持续时间为3小时;室外消火栓系统的用水量30L/S ,火灾持续时间为3小时;自动喷淋系统的用水量为23L/S,火灾持续时间为1小时。
消防用水量:Q/XH1=40×3.6×3+30×3.6×3+23×3.6×1=838.8m³,故火灾发生一次所需的最大消防用水量:Q消=838.8m³。考虑到消防灭火时两个消防水池进水管的补水量(根据甲方提供给水为24小时不间断供水),故在室外设两个400m³的消防水池。
1.6.3.0 给水消防管道施工注意事项:
1)、给水管道必须采用与管材相适应的管件。
2)、施工过程中应严格遵守《城镇给水排水技术规范》〈GB50788-2012〉中3.1.2条,城镇给水中生活饮用水的水质必须符合国家现行生活饮用水卫生标准的要求。
3)、当给水管道与污水管道交叉时,给水管道敷设在污水管线下面且交叉点间距小于0.4m时,应在给水管上加设钢套管,套管伸出交叉管的长度每边不得小于3米,套管两端应采用防水材料封闭。
4)、施工前应校测接管点高程,确定无误后方可施工。
1.6.4 污水管线施工
1.6.4.1污水管线主要工程量:
DN300 HDPE双壁波纹管:990m
Ø1000mm钢筋混凝土污水检漏井:51座
Ø1000mm钢筋混凝土污水检查井:74座
1400×1100mm矩形钢筋混凝土污水检查井:1座
Ø1250mm竖管式钢筋混凝土跌水井:1座
1#(3.75m³)钢筋混凝土化粪池:1座;
3#(12.5m³)钢筋混凝土化粪池:1座
5#(30m³)钢筋混凝土化粪池:1座
10#(100m³)钢筋混凝土化粪池:5座1.6.4.2污水管线设计:
1.6.4.2 污水量计算
污水量按照给水量的85%计,约为1033.5m³/d。
1.6.4.3 平面施工要求
本工程小区内采用雨水与污水完全分流体系。
室外污水管线按照九院小区三期室外管线综合规划给出的管线位置进行布设,污废水经建筑物楼前DN300污水管收集,经化粪池处理后排入小区周边市政现状污水管网。
1.6.4.4 纵断施工要求
污水管管径为DN300;设计坡度采用0.003~0.054。
1.6.4.5 结构施工要求
1)、管材及接口:污水管道采用埋地高密度聚乙烯(HDPE)双壁波纹管;接口采用承插橡胶圈接口,采用环刚度S2级(8KN/㎡ )。
2)、管道基础: 本项目地质情况为:1#、1#裙楼、3#、4#、3#和4#间的裙楼按Ⅲ级自重湿陷性黄土考虑,2#、廉租房按Ⅱ级自重湿陷性黄土考虑(根据结构单体提供);甲类建筑(Ⅲ级自重湿陷性)污水支线和主线距离建筑物不满足防护距离(8.0~9.0m)的及丙类建筑(Ⅲ级自重湿陷性)污水支线和主线距离建筑物不满足防护距离(6.0~7.0m)的,应消除全部湿陷量(全部换3:7灰土)或做检漏沟(选用C型600X600具体做法见国标04S531-2-P7页);甲类建筑(Ⅱ级自重湿陷性)污水支线和主线距离建筑物无防护距离要求;丙类建筑(Ⅱ级自重湿陷性)污水支线和主线距离建筑物不满足防护距离(5.0m)的,应消除全部湿陷量(全部换3:7灰土)或做检漏沟(选用C型600X600具体做法见国标04S531-2 P7页);满足防护距离的管道基础应原土夯实后铺50cm3:7灰土垫层,再铺10cm中粗砂垫层;沟槽回填土时,距离管顶0.5m以上的回填土内允许有少量直径不大于0.1m的石块和冻土,其数量不得超过填土总体积的15%。距离管顶0.5m以内的回填土内不得含有碎石、砖块、垃圾等杂物,不得用冻土回填 。
3)、污水检查井:污水支线和主线距离建筑物不满足防护距离的,采用Ø1000mm钢筋混凝土污水检漏井(具体做法见国标图集04S531-3)。污水支线和主线距离建筑物满足防护距离的,采用Ø1000mm钢筋混凝土污水检查井(具体做法见国标图集04S531-5)。Wh9污水检查井采用1400×1100mm矩形钢筋混凝土污水检查井(具体做法见国标图集04S531-5)。
4)、跌水井:Wh10污水检查井采用Ø1250mm竖管式钢筋混凝土跌水井(具体做法见国标图集04S531-5)。
5)、化粪池:采用省标图集1#(3.75m³)、3#(12.5m³)、5#(30m³)、10#(100m³)钢筋混凝土化粪池,清掏周期为180天,污水停留时间为12h。(具体做法参见省标集图05S7)。
在车行道上及停车场上的所有检查井的井盖均采用重型铸铁井盖。在路面上的井盖,上表面应同路面相平、绿化带内井盖应高出室外设计标高50mm,并应在井口周围以0.02的坡度向外做护坡。铸铁井盖顶面中间空白处应填铸“污水”字样,作为区别于其它井室的标注。
1.6.4.6施工注意事项
1)、本项目地质情况为Ⅲ级自重湿陷性黄土,在施工过程中须严格按照湿陷性黄土地区相关规范施工。
2)、污水出户管做法详见单体水施工图。
3)、本项目因现场场地条件有限,污水管道距建筑外墙的距离不能满足相关技术要求,需做混泥土外包处理以增强其抗压力(W19-W23)。
4)、管道施工前必须校测管线终点现状高程,必须从下游开始施工。
5)、楼前接户井位置如与出户管位置不符,应依据出户管位置作相应调整;污水井面高程如与设计道路高程不符,以设计道路高程为准。
6)、排水管道转弯和交汇处检查井内流槽内应保证水流转角等于和大于90°,但当管径小于300mm时,且跌水高度大于0.30m时,可不受此限。
7)、开挖沟槽,应严格控制基底高程,不得扰动基底原状土层基底设计标高以上0.2-0.3m的原状土,应在铺管前人工清理至设计标高。如遇局部超挖或发生扰动,不得回填泥土,可换填最大粒径10-15mm的天然级配砂石料或最大粒径小于40mm的碎石,并整平夯实。槽底如有坚硬物体必须清除,用砂石回填处理。
8)、闭水试验:污水管道回填前,应对污水管道进行全线闭水试验,合格后方可回填,回填时土方土质应严格按照规范规定进行。不合格的应返修或加固,重做实验,直至合格为止。
9)、钢筋混凝土检漏井或检查井应采用内外防水,防水做法采用合成高分子防水涂膜防水层,具体做法为10mm厚1:2水泥砂浆找平,1.5~2.0mm厚合成高分子防水涂膜,20mm厚1:2水泥砂浆保护层。管道接口处应采取防水措施,防止管道接口处渗漏影响建筑物基础。
1.6.5 雨水管线施工
1.6.5.1雨水管线主要施工量:(HDPE)双壁波纹管:DN300mm雨水管线设计管长1100m,DN400mm雨水管线设计管长20米。雨水口的连接管管径为DN200,坡度为0.01,设计管长230米。
雨水口:58个 雨水检查井:85座
1.6.5.2雨水管线设计参数
雨水流量:Q=ψqF
q=1446.22(1+0.867LgT )/(t+5)
q----暴雨强度(升/秒·公顷)
F----汇水面积(平方米)
T----设计重现期(年)T=1年
ψ----综合径流系数ψ=0.65
t----降雨历时(分)t1=10分钟
雨水管线采用暗管,折减系数m=2
1.6.5.2平面施工要求
本工程室外采用雨水与污水完全分流体系,室外雨水管线严格按照市政管线综合规划给出的管线位置进行布设,九院小区三期雨水总汇水面积为3.5ha,雨水最大流量为85.4L/S,雨水经楼前井及雨水口收集后排入雨水干管,最终排入小区周边市政现状雨水管线。
1.6.5.3纵断施工要求:雨水管线设计坡度为0.003~0.055。
1.6.5.4结构施工要求
1)管材及接口:雨水管道采用DN300mm和DN400mm高密度聚乙烯(HDPE)双壁波纹管,环刚度S2级(8KN/㎡ ),采用承插橡胶圈接口。
2)管道基础: 本项目地质情况为:1#、1#裙楼、3#、4#、3#和4#间的裙楼按Ⅲ级自重湿陷性黄土考虑,2#、廉租房按Ⅱ级自重湿陷性黄土考虑(根据结构单体提供);甲类建筑(Ⅲ级自重湿陷性)雨水支线和主线距离建筑物不满足防护距离(8.0~9.0m)的及丙类建筑(Ⅲ级自重湿陷性)雨水支线和主线距离建筑物不满足防护距离(6.0~7.0m)的,应消除全部湿陷量(全部换3:7灰土)或做检漏沟(选用C型600X600具体做法见国标04S531-2-P7页);甲类建筑(Ⅱ级自重湿陷性)雨水支线和主线距离建筑物无防护距离要求;丙类建筑(Ⅱ级自重湿陷性)雨水支线和主线距离建筑物不满足防护距离(5.0m)的,应消除全部湿陷量(全部换3:7灰土)或做检漏沟(选用C型600X600具体做法见国标04S531-2 P7页);满足防护距离的管道基础应原土夯实后铺50cm3:7灰土垫层,再铺10cm中粗砂垫层;沟槽回填土时,距离管顶0.5m以上的回填土内允许有少量直径不大于0.1m的石块和冻土,其数量不得超过填土总体积的15%。距离管顶0.5m以内的回填土内不得含有碎石、砖块、垃圾等杂物,不得用冻土回填 。
3)、雨水检查井:雨水主线和支线距离建筑物不满足防护距离的,采用∅1000mm钢筋混凝土雨水检漏井,(具体做法见国标图集04S531-3);雨水支线和主线距离建筑物满足防护距离的,采用∅1000mm钢筋混凝土雨水检查井(具体做法见国标图集04S531-5)。
在车行道上及停车场上的所有检查井的井盖均采用重型铸铁井盖。在路面上的井盖,上表面应同路面相平、绿化带内井盖应高出室外设计标高50mm,并应在井口周围以0.02的坡度向外做护坡。铸铁井盖顶面中间空白处应填铸“雨水”字样,作为区别于其它井室的标注。
1.6.5.5 施工注意事项
1)、本项目地质情况为Ⅲ级非自重湿陷性黄土,在施工过程中须严格按照本地区相关规程施工。
2)、管道施工前必须校测管线终点现状高程,必须从下游开始施工。雨水出户管做法详见单体水施工图。
3)、本项目因现场场地条件有限,雨水管道距建筑外墙的距离不能满足相关技术要求,需做混泥土外包处理以增强其抗压力(Y1-Y9)。
4)、楼前接户井位置如与出户管位置不符,应依据出户管位置作相应调整;雨水井面高程如与设计道路高程不符,以设计道路高为准;
5)、开挖沟槽,应严格控制基底高程,不得扰动基底原状土层基底设计标高以上0.2-0.3m的原状土,应在铺管前人工清理至设计标高。如遇局部超挖或发生扰动,不得回填泥土,可换填最大粒径10-15mm的天然级配砂石料或最大粒径小于40mm的碎石,并整平夯实。槽底如有坚硬物体必须清除,用砂石回填处理。
6)、钢筋混凝土检漏井或检查井应采用内外防水,防水做法采用合成高分子防水涂膜防水层,具体做法10mm厚1:2水泥砂浆找平,1.5~2.0mm厚合成高分子防水涂膜,20mm厚1:2水泥砂浆保护层。管道接口处应采取防水措施,防止管道接口处渗漏影响建筑物基础。
7)、排水管道转弯和交汇处检查井内流槽内应保证水流转角等于和大于90°,但当管径小于300mm时,且跌水高度大于0.30m时,可不受此限。
8)、闭水试验:全线做闭水试验,必须经严密性试验合格后方可投入使用。不合格的应返修或加固,重做实验,直至合格为止。
1.6.6 热力管线施工
1.6.6.1热负荷:根据单体设计提供商铺采暖设计平均热指标为58w/m2.商铺采暖热负荷为965KW,住宅采暖设计平均热指标为30w/m2,系统总热负荷为4386.2KW,其中低区为2137.8KW,高区为2248.4KW。考虑到安全系数,所以总的低区采暖热负荷为3102.8KW×1.1=3413.08KW,高区为2248.4KW×1.1=2473.24KW。
1.6.6.2 施工设计参数 :
(1)工作压力:高区P=1.3MPa,低区P=0.8MPa.
(2)设计压力:高区P=1.6MPa,低区P=1.0MPa.
(3)供水温度Tg=50°C,回水温度Th=40°C.
1.6.6.3 敷设补偿方式 :
(1)供热管道采用直埋敷设及地沟敷设。
(2)管道热补偿采用自然补偿,管沟内设固定支架,直埋敷设无补偿器,无固定墩。
(3)管网最不利环路总阻力: 高区19.62KPa 低区20.66KPa.
1.6.6.4主要管件及材料的选用 :
(1)供热管道材料:采用预制直埋保温管.DN≥200时采用螺旋焊接钢管,DN<200时采用焊接钢管。管道及钢制管件的的钢材钢号不应低于相关规定,本工程设计参数P≤1.0MPa,t≤95℃时,钢号为Q235AF,钢板厚度≤8mm;P≤1.6MPat≤150℃时,钢号为Q235A,钢板厚度≤16mm,管道和钢材的规格及质量应符合国家现行相关标准的规定。管道保温厚度应符合《居住建筑节能设计标准》DBJ04-242-2012的规定。
(2)供热管道分段阀,分支阀均采用双密封蝶阀,焊接连接.
(3)补偿器.弯头,三通及异径管均采用工厂化产品.
(4)小室内90°弯头及分支上翻弯头均采用压制弯头(R=1.5D) .其余采用预制保温弯头(R=3D).弯头壁厚大于同径管道2-3毫米.
(5)放气,泄水阀门应采用进口球阀.
1.6.6.5支架及盖板的施工要求:
热力网管道支架支墩见国标图集<<03R411-1>>,安装时,管道的接头焊缝不应布置在支座上,焊缝距支座边缘距离不小于100mm。
1.6.6.6施工注意事项
1)、主管道覆土深度不小于1.0米.支管道覆土深度不小于0.9米 ;管道应有不小于0.002的坡度.且在管道高处放气.低处泄水.
2)、穿越交通道路时.砂槽上应加设保护盖板,做法详见05R410-52,53页
3)、放气(管)阀设于放气小室内,做法详见05R410-67页
4)、检查室中设置的泄水接管座和放气阀参见05R410-66页
5)、各分支三通,泄水三通均需补强,做法详见05R410-80~86页.
6)、供热管道自然转弯处应做软回填,做法详见本设计图,以保护弯头.
7)、所有大于1.5°的平面及竖向折点均不得直接对焊,应采用弯头连接.
8)、水平分支管做法详见05R410-72页,水力平衡通过单体内设置的平衡阀进行平衡.
1.6.6.7施工及验收说明
1)、所有的施工及验收应严格按照<<城镇供热管网工程施工及验收规范>>(CJJ28-2004 J372-2004)进行,并应符合<<城镇直埋供热管道工程技术规程>>(CJJ/T81-98)的规定.沟槽开挖到设计高度后,如地基软硬不一致时,应与设计单位联系处理.
2)、管道安装 :
(1)管道安装前应进行清洗.
(2)管道对接采用电焊,焊条采用E4303型.
(3)管道焊接后要按规范规定数量进行无损探伤.
3)、防腐.保温:
(1)小室外管道接口、管件保温均采用聚氨脂发泡保温,现场做高密度聚乙烯外护.
(2)小室内管道接口、管件、放气装置和泄水装置阀门以内部分保温均采用聚氨脂发泡保温,外护采用环氧树脂型玻璃钢.
4)、冲洗.试压:
管道安装完毕,在接口保温前必须进行水压试验,具体要求按照 <<城市供热管网工程施工及验收规范GJJ-28-2004>>中有关规定执行
(1)试压必须在管道的泄水 、放气 、除污装置安装完毕后进行.
(2)管网应进行强度试验和严密性试验。强度试验压力应为设计压力的1.5倍,为2.4MPa,严密性试验压力应为设计压力的1.25倍,为2.0MPa。
(3)冲洗使用普通清水,管内流速不小于1.5m/s,要求出水清澈为合格。
2. 项目班子机构及劳动力安排
2.1 项目班子机构:本工程按项目组织施工,项目经理选派承担过同类型工程项目管理,并具备丰富施工管理经验项目经理担任;项目经理部对本项目的人、财、物按照项目法施工管理的要求实行统一组织,统一布置,统一计划,统一协调,统一管理,室外工程安排主管一名、技术员一名、测量员一名、安全员一名。室外工程主管选派具有较高技术业务素质和技术管理水平、并有创优管理经验的工程技术人员担任。
2.2劳动力安排
施工队人员配备:施工作业层人员的是项目的具体执行者和操作者,按照以人为本、专业合理的原则进行施工作业层人员的配备,工程涉及道路土方、给水、雨水、污水、热力管道等多个专业,施工人员不仅要求具备较强的专业能力,更要求一专多能。配备时既要充分发挥专业特点,又要注意其工序之间的互联性,做到专业水平高、知识面广。为确保专业人员的操作水平和能力,抽派专业人员对参加施工的人员进行理论知识和实际操作能力的培训和考核,不合格人员坚决不允许进场。
各施工队人员配备见下表:
施工队人员配备表
序 号
工种
数 量
备 注
1
管理人员
5
2
测量工
2
4
机械、司机、起重工
5
5
电工、机修工
4
6
瓦 工
6
7
木 工
15
8
混凝土工
10
9
钢筋工
12
10
普 工
30
11
管道工
24
12
焊工
8
3.质量保证体系和保证措施
3.1建立完善、全面的质量管理体系
本着"质量第一"的原则进行质量目标管理,并导入ISO9001 质量认证体系,以“强化科学管理,优化整体质量,持续改进提高,满足甲方要求。”
3.2建立健全完善的质量保证体系
展开阅读全文