德之馨(上海)有限公司新建研发 实验楼项目桩基工程Piling foundation project for Symrise(Shanghai)Co.,Ltd new lab
施工方案Construction scheme
编制人Prepare the peoele:汤春强
审核人The reviewer:朱连忠
技术负责人Technical director:汤春强
总包单位General contractor:江苏南通二建集团有限公司Jiangsu Nantong NO.2 Construction Engineering Group Co.,Ltd
施工单位Construction unit:上海极基建设工程有限公司Shanghai Jiji Construction Engineering Co.,Ltd
编制日期Date:20 Oct. 2016 2016年10月20日
Index目 录
Chapter 1 Project overview第一章 工程总体概述
一、Basis编制依据
Chapter2 Construction organization & responsibility第二章 施工管理组织机构及职责
一、Construction organization施工管理组织机构
Chapter3 Construction deployment第三章施工部署
一、Preparation施工前准备工作
二、Site plan施工现场总平面图
Chapter 4 Construction schedule & guarantee measures of project duration 第四章 施工计划及工期保证措施
一、Construction machinery arrangement schedule施工机械配置计划表
二、Manpower plan劳动力安排
三、Construction progress schedule施工总进度计划表
Chapter5 Construction scheme第五章施工技术方案
一、Construction process flow施工工序流程
二、Transportation, hoisting, storage of PHC pile PHC管桩运输及吊装、堆放
三、Construction technology of PHC pile PHC管桩的施工技术
Chapter6 Main measures for project quality assurance第六章保证工程质量的主要措施
一、Project quality goal工程质量目标
二、Project organization项目组织机构体系
三、Detailed measures for project quality assurance保证工程质量的具体措施
Chapter7 HSE control measures第七章安全、环境与健康(HSE)管理措施
一、HSE guidelines, goals HSE方针、目标
二、HSE system HSE管理体系
三、Contigency plan for construction emergency施工紧急情况下应急预案
四、JSA危险性分析报告
Chapter 8 As-built documentation submittal第八章提交竣工资料
Appendix附表一:JSA危险性分析报告
Chapter 1 Project overview第一章 工程概述
一、Project profile工程概况
1.Project name工程名称:Piling foundation project for Symrise(Shanghai)Co.,Ltd new lab德之馨(上海)有限公司新建研发实验楼项目桩基工程
2.Project location工程地点:No.30, Lonqiao Road, Pudong District,Shanghai上海市浦东新区陇桥路30号
3、Client建设单位:德之馨(上海)有限公司
4、Design unit设计单位:The IT Electronics Eleventh Design & research Institute Science and Technology Engineering Co., Ltd信息产业电子第十一设计研究院科技工程股份有限公司
5、Jianli监理单位:上海创众工程监理有限公司
6、General contractor总包单位:Jiangsu Nantong NO.2 Construction Engineering Group Co.,Ltd
江苏南通二建集团有限公司
7、Construction unit施工单位:Shanghai Jiji Construction Engineering Co.,Ltd上海极基建设工程有限公司
8、Overview工程基本情况:Proposed location is within Symrise(Shanghai)Co.,Ltd, which is grassland. Project ±0.000 is relatively to 4.4000m of Wusong elevation. This project adopts static-press piling, which is pre-tensioning method, pile model is PHC 500(100)AB-C80-15,15, total no. of piles is 89, album no. is 10G409 拟建场地位于德之馨(上海)有限公司厂区内,该场地原为绿化草坪。本工程±0.000相对于吴淞高程4.400m,本工程采用静力压桩,采用先张法预应力混凝土管桩,管桩型号为PHC 500(100)AB-C80-15,15,总桩数为89根,图集号:《10G409》。
二、Basis编制依据
1、Bidding documents and drawings依据提供工程招标文件及招标图纸;
2、Technical code for building pile foundation《建筑桩基技术规范》(JGJ94-2008);
3、Technical code for testing of building foundation piles 《建筑基桩检测技术规范》(JGJ106-2014);
4、Code for design of building foundation《建筑地基基础设计规范》(DGJ-11-2010);
5、Code for acceptance of construction quality of building foundation《建筑地基基础工程施工质量验收规范》(GB50202-2016);
6、Pretensioned spun concrete piles 《先张法预应力混凝土管桩》(DBJT08-92-2000);
7、 Code for engineering surveying《工程测量规范》(GB50026-2007)
8、Unified standard for construction quality acceptance of building engineering《建筑工程施工质量验收统一标准》(GB50300-2013);
9、Code for construction project document filing and arrangement《建设工程文件归档整理规范》(GB50328-2001);
10、 Specification for welding and acceptance of reinforcing steel bars《钢筋焊接及验收规范》(JGJ18-2012);
11、Technical code for safety of temporary electrification on construction site《施工现场临时用电安全技术规范》(JGJ46-2005);
12、Standard of construction safety inspection《建筑施工安全检查标准》(JGJ59-2011);
13、Technical code for safety of aerial work on construction site《建筑施工高处作业安全技术规范》(JGJ80-91);
14、Company's existing equipment, construction condition, technology in previous years for such project construction experience and achievement of the quality, safety, civilization, standardized management regulations, system and the enterprise standard我公司现有设备、施工技术力量状况,往年对此类工程的施工经验及创造成果,有关质量、安全、文明、标准化管理的条例、制度及各项企业标准。
Chapter2 Construction organization & responsibility第二章 施工管理组织机构及职责
PM项目经理
Lianzhon Zhu朱连忠
一、Construction organization施工管理组织机构
HSE specialist专职安全员
马跃军
Project engineer项目工程师
汤春强
Construction manager施工经理
汤春强
Technology team技术组
Document team资料组
Surveying team测量组
Quality team质检组
Material team材料组
Equipment team设备组
Engineering team工程组
All construction teams各施工班组
二、Main construction staff’s responsibilities主要施工管理人员职责
1、Project manager项目经理
© to carry out the relevant state laws and regulations, decrees, entrusted by the general manager, the implementation of company general manager to set up the quality policy, policy, target, the contract within the scope of the project quality, time, cost, and will be entirely responsible for HSE management.贯彻执行国家有关的法规、法令,受公司总经理委托,执行公司总经理制定的质量方针、政策、目标,对合同范围内的工程质量、工期、成本及HSE管理全面负责。
© The composition of organization planning programs, establish and improve the quality assurance system, and guarantee the effective operation.组织策划项目机构的组成、建立健全质保体系,并保证有效进行运转。
© control project cost.控制项目成本。
© project manager is the first head of project HSE work during project construction, to organize the formulation of the HSE plan, the implementation of the HSE management, pays special attention to the HSE management work.项目经理是工程施工期间项目HSE工作的第一负责人,组织编制HSE计划,落实HSE管理人员,抓好HSE各项管理工作。
© approval to carry out the project construction organization design, make sure to ensure the engineering quality, finish on time to complete the company issued the economic and technical indexes.批准落实项目的施工组织设计,确保工程保质、保量如期完成,按时完成公司下达的各项经济技术指标。
© organization commissioning acceptance of completion of the project (including middle).组织交工验收(含中间交工工程)。
2、Construction manager施工经理
Under the leadership of project manager在项目经理领导下:
© responsible for the construction of converting, director of the construction team and total project coordination.负责施工方面的实物量,主管各施工班组和项目总协调。
© unified command production and coordination of each construction team responsible for the management of the cooperative unit.统一指挥各施工班组的生产和协调工作,负责对协作单位的管理。
© responsible for organizing the formulation of the project construction plan and the implementation of production plan.负责组织编制项目的施工计划并实施生产计划。
© according to production plan organization and implementation of labor, to play equipment check, ensure the equipment in good condition.按生产计划组织劳动力并实施,对进场设备组织检查,确保设备处于良好状态。
© implement the project HSE plan and the implementation of project HSE measures.贯彻项目HSE计划,实施项目HSE的各项措施。
© responsible for the progress and quality of construction projects.对工程的施工进度和质量负责。
© labor induction forensics and safety education work for the assigned project.负责项目劳动力上岗培训取证及安全教育工作。
© responsible for the completion of project review and follow-up services.负责竣工项目回访和善后服务工作。
3、Project engineer项目工程师
在项目经理的领导下:
© fully responsible for project construction technology and quality management and HSE related technical work.全面负责项目施工的技术和质量管理工作以及HSE的有关技术工作。
© to carry out national technical regulations, standards, procedures, etc.贯彻执行国家技术法规、标准规程等。
© to organize the formulation of technical solutions, quality planning and review, cooperate with the production plan in related technical work.组织编制技术方案、质量策划并进行审核,配合生产计划进行相关的技术工作。
© decided not to conform to the treatment scheme of the project.决定不符合项目的处理方案。
© quality work conference, and make technical decisions on important issues.参加有关质量工作会议,并对重要问题作出技术决策。
© solve various technical problems occurred in field construction.解决现场施工中出现的各类技术问题。
© responsible for the management of the interface with the design institute.负责与设计院的接口管理。
© build project quality assurance system, make its normal operation.建立项目部质保体系,使其正常运转。
© responsible for organize the formulation of quality planning, and to carry out the implementation.负责组织编制质量策划,并落实实施。
© responsible for interface management and supervision company.负责与监理公司的接口管理。
© above shall have the right to report to quality assurance, quality inspection, maintenance and ensure the normal operation of quality control, and seriously endanger the quality problem有权越级报告质保、质检工作,维护和保证质控工作的正常运转,制止严重危及质量的问题。
© collect, sort out band data, quality evaluation system.收集、整理交工资料,完成质量评定工作。
© for completed project quality review and follow-up service work.参加竣工项目质量回访和善后服务工作。
4、HSE specialist专职安全员职责
© familiar with and master safety production dynamic, collection and the dyke construction site HSE information, timely report to the HSE manager.熟悉和掌握安全生产动态,收集和反溃施工现场HSE信息,及时向HSE经理汇报。
© check construction personnel at the scene at any time is properly carried out safety operation procedures and to observe the safety rules and regulations, to prevent illegal behavior随时在现场检查施工人员是否正确执行了安全操作规程和遵守安全规章制度的情况,制止违章行为。
© check and maintain the good scene safety facilities, to ensure the reliability of the site safety facilities.检查和维护好现场的安全设施,确保现场安全设施的可靠性。
© shall have the right to stop does not comply with the safety rules of construction personnel and mechanical equipment.有权制止不符合安全规定的施工人员和机械设备上岗。
© organization staff post production safety education and shift safety activities.组织员工的岗位安全生产教育及班组安全活动。
If any accident, rescue the wounded, protect the scene and immediately report, assist the accident investigation and analysis.发生事故,抢救伤员,保护现场并立即报告,协助事故调查分析。
Chapter3 Construction deployment 第三章 施工部署
一、Preparation施工前的准备工作
1、All procedures to be done per requirements按施工要求办理各种施工手续
Positively related to construction, the total package units to deal with the construction procedures, such as construction personnel safety education, ensure the legitimacy of the construction, make the project smoothly.积极与建设、总包单位办理有关的施工手续,如施工人员安全教育等,保证施工的合法性,使工程顺利开工。
2、Tech. preparation认真做好技术准备工作
(1) under the organization of the project manager, familiar with drawings carefully and deeply understand the design intent and design requirements, questions and Suggestions to the design drawings, and in conjunction with the owner, supervision and design institutes, the blue prints.the design so as to guide the construction.在项目经理的组织下,认真熟悉图纸,深刻理解设计意图及设计要求,提出对设计图纸的疑问和建议,并会同业主、监理和设计院进行图纸会审,从而指导施工。
(2) according to the requirements of construction actively equipped with all kinds of management information, technical data, construction specifications, acceptance criteria, under the organization of the project manager for the relevant construction technical clarificaiton work按施工要求积极配备各类管理资料、技术资料、施工规范、验收标准,在项目经理的组织下进行各有关施工技术交底工作。
(3) Carry out all tech. requirements贯彻施工方案的各项技术要求。
3、Equipments & material preparation认真做好设备、材料的供应工作
Do a good job, the supply of equipment, material is the basis to ensure the project completed on time.According to the project schedule, project department, plan well component product and material approach as planned by the materials department prepares materials procurement, the project according to the request of the construction unit choose inspection qualified pipe pile factory products, to provide qualified products on time with good quality.做好设备、材料的供应工作,是确保工程项目按时完成的基础。根据工程进度要求,项目部做好构件产品和材料的进场计划,由材料部门按计划进行备料采购,本工程根据建设单位要求选用考察合格的管桩厂产品,保质保量按时提供合格产品。
Equipment maintenance and inspection by the regulation, check it again for main equipment before entry to ensure the performance of play equipment is in good condition.设备按规定维修、检验,进场前对主要设备再次检查确认,以保证进场设备处于良好的性能状态。
4、Construction electricity preparation认真做好施工用电准备工作
The project plans to input 1 YZY - 300 type pile machine, total power consumption of not less than 120 kw.本工程计划投入1台YZY-300型桩机,总用电量不少于120kw。
Construction units to provide the total power in construction planning red line within the scope of my project department from the total package units to provide construction distribution box, and then supply power to piling area construction power cable will be used for access to the site to establish distribution box, with a cable from the construction of electricity, electricity box to set up a good grounding device and the leakage switch, prevent to get an electric shock.建设单位提供总电源位于施工规划红线范围内,我项目部从总包单位提供的施工配电箱引出,然后向打桩区域供电,采用电缆将施工用电接入到现场增设的配电箱,再用电缆接到各施工用电点,电箱要设置良好的接地装置及漏电开关,防止触电。
Site construction electricity lines and distribution box set adopts three-phase five wire system, construction of electricity power box location layout.现场施工用电线路及配电箱设置均采用三相五线制,施工用电的电源箱位置见平面布置图。
5、Surveying preparation测量放样的准备工作
According to the level of the construction unit to provide the coordinates of control points and control points, in strict accordance with the design and construction drawings, axis control point positioning in J2 theodolite.根据建设单位提供的座标控制点和水准控制点,严格按设计施工图纸,用J2经纬仪进行轴线控制点定位。
Axis to the axis of the piles with solid protection, then every axis of each axis arranged according to the axis of the pile pile, with J2 theodolite measuring out the pile engineering samples, requirements have to be lofting Φ 6 round steel, the error shall not be greater than 1 cm.对现场轴线的各个轴线桩进行稳固保护,再根据轴线桩布设各条轴线的各分轴线桩,用J2经纬仪测放出各工程样桩,要求要Φ6圆钢进行放样,其误差不得大于1cm。
Axis positioning also completes the review work, each time to review the measurement data should be archived for future reference, and please build supervision and owner unit check, and make the book visa face to face.轴线定位还做好复核工作,每次复核测量数据应存档备查,并请建监理及业主单位核验,并做好书面签证。
6、Site preparation场地准备
(1)Construction site must be flat topography, venue is not flatness should be < 1%, construction areas around open drain, field with blind ditch, asking for a flat, the rain stopped not water施工现场地势必须平坦,场地不平整度应<1% ,施工区域四周开设排水沟,场内设盲沟,要求达到雨停场平,不积水。
二、Site plan施工现场总平面布置示意图
1、in accordance with the total package units construction layout plan, ready to live life, construction of temporary facilities.按照总包单位施工平面布置规划,做好现场生活、施工的临时设施。
2、considering of the need to transport goods pile, the construction site to north and south road, the goods can transport to the whole construction area.Road turning radius shall meet the operation of the truck.考虑到商品桩运输的需要,在施工现场道路要南北向贯通,使商品桩能运输到整个施工区域。道路的转弯半径应满足载重车的运行。
Chapter 4 Construction schedule & guarantee measures of project duration 第四章、施工计划及工期保证措施
一、 Construction machinery arrangement schedule施工机械配置计划表
SEQ序号
NAME名称
MODEL型号
UNIT单位
QTY数量
COMMENT备注
1
Piling machine打桩机
YZY-300
台
1
For piling打桩主机
2
Truck crane汽车吊
50T
辆
1
Load & unload piling machine装、卸桩机
3
Welding machine焊机
NBC-400
台
2
Pile following接桩
4
Theodolite经纬仪
J2
台
2
Setting out放样、校正垂直度
5
Level水准仪
S3
台
1
Control elevation控制标高
6
Tool box工具箱
个
1
Store tools储放桩机配件工具
7
Tape50m卷尺
把
1
Measuring丈量
8
Distribution box配电箱
只
1
Matched cable电缆配套
9
Pile follower送桩杆
φ500
根
1
1 spare usage送桩备用1根
(1)Piling machine arrangement桩机安排:a 300T static pressure machine will be adopted for construction, equipped with pile follower本工程安排一台300吨静压桩机进行施工,配置相应的送桩杆。
(2)Construction progress plan施工进度计划:commence date is set on 25 Oct,2016 for time being, details