1.A manufacturing ptoject has a schedule performance index (SPI) of 0.89 and a cost performance index (CPI) of 0.91.Generally,what is the BEST explanation for why this occurred?
A) The scope was changed.
B) A supplier went out of business and a new one needed to be found.
C) Additional equipment needed to be purchased.
D) A critical path activity took longer and needed more labor hours to complete.
某个制造项目标进度绩效指数 (SPI) 是0.89;成本绩效指数 (CPI) 是0.91。一般而言,对这种情况出现的最佳的释是?
A) 范围变更。
B) 供应商歇业,需要找新的。
C) 额外的设备需要采购。
D) 核心途径的活动太长,需要更多劳动力时间来完成。
2.During the completion of work packages,the sponsor asks the project manager to report on how the project is going.In order to prepare the report,the project manager asks all the team members what percent complete their work is.There is one team member who has been hard to manage from the beginning.In response to being asked what percent complete he is,the team member asks,“Percent complete of what?”Being tired of such comments,the project manager reports to the team member’s boss that the team member is not cooperating.Which of the following is likely to be the real problem?
A) The project manager did not get buy-in from the manager for the resources on the project.
B) The project manager did not create an adequate reward system for team members to improve their cooperation.
C) The project manager should have had a meeting with the team member’s boss the first time the team member caused trouble.
D) The project manager does not have work packages.
在完成工作包期间,出资人要求项目经理报告项目进展。为了准备报告,项目经理要求所有的团体组员阐明工作完成的百分比。有个团体组员从开始就极难管理,当问到他工作完成百分比时,他说:“什么是完成百分比?”因为厌倦此类对话,项目经理向团体组员的老板报告说这个组员不合作。下列哪个更像真正的问题?
A) 项目经理没有从资源管理者那里真正为项目取得资源。
B) 项目经理没有创建适宜的奖励系统来改进团体组员的合作。
C) 项目经理应当和团体组员的老板开个会,在团体组员第一次惹麻烦时。
D) 项目经理没有工作包。
3.Which is not a goal in both project management and quality management?
A) Prevention over inspection. B) Customer satisfaction.
C) Management responsibility. D) Triple constraint.
下列哪个不是项目管理和质量管理的共同目标?
A) 预防胜于检查。 B) 客户满意。 C) 管理层责任。 D) 三角形约束。
4.Which of the following BEST describes the verify scope process?
A) It provides assurances that the deliverable meets the specifications,is an input to the project management plan.and is an output of perform quality control.
B) It ensures that the deliverable is completed on time and gets customer acceptance,and shows that the deliverable meets specifications.
C) It ensures customer acceptance,shows that the deliverable meets specifications,and provides a chance for differences of opinion to come to light.
D) It is an output of perform quality control,occurs before define scope,and ensures customer acceptance.
下列哪项最佳地描述了核算范围过程?
A) 它提供成果符合规格的确保,是项目管理计划的输入,是执行质量控制的输出。
B) 它确保成果及时完成并得到客户接收,表白成果符合规格要求。
C) 它确保客户接收,显示成果符合规格要求,提供机会及时发觉存在的问题。
D) 它是执行质量控制的输出,在定义范围之前出现,确保客户接收。
5.A project has the following earned value data assessed:AC= $4,000,000;CV= $-500,000;SPI=l.12;BAC= $9,650,000.What is the earned value of the project?
A) $3,000,000. B) $3,500,000.C) $4,480,000. D) $5,650,000.
项目实现值数据如下:AC=4,000,000美元;CV=-500,000美元;SPI=1.12;BAC=9,650,000美元。则EV= 。
A) 3,000,000美元 B) 3,500,000美元 C) 4,480,000美元 D) 5,650,000美元
6.At the beginning of project execution,you notice different opinions between team members relating to project work and deliverables and to the level of overall complexity.What should you do right now?
A) Give your team members some time to develop a common understanding of the project scope and product scope.Upcoming interface problems may be resolved later.
B) Use the risk management processes to identify and assess risks caused by misunderstandings and develop a plan with measures in order to respond to them.
C) Organize meetings to identify and resolve mlsunderstandings between team members in order to early avoid interface problems,disintegration and costly rework.
D) Use interviews in private with each individual team member to inform them of your expectations and your requirements in an atmosphere of confidence.
在项目执行早期,你注意到项目团体组员对项目工作和成果的复杂程度有不一样的见解。你目前应当做什么?
A) 给团体组员些时间,以建立对项目范围和产品范围的共同了解,即将出现的接口问题稍后也许会处理。
B) 使用风险管理过程来识别和评定因为误解引起的风险,编写个计划来衡量并回应它们。
C) 组织会议来识别、处理团体组员之间的误解,以便尽早防止接口问题,减少返工成本。
D) 私下会见每个团体组员,在相互信任的气氛下告诉他们你的期望和你的要求。
7.Being the project manager in a software project which is currently initiated,you want to assess high level risks.What should you do?
A) Develop a preliminary scope statement and document initially identified risks in this document.
B) Identify and analyze risk events using qualitative and quantitative techniques.
C) Develop contingency plans and fallback plans in case the original plan proves wrong.
D) Discuss the risks documented in your risk register with the project key stakeholders.
你是个项目经理,刚才开启一个软件项目,你想评定最高层次的风险,你应当做什么?
A) 编写初步范围阐明书,统计下来最初识别的风险。
B) 使用定性和定量技术识别和分析风险事件。
C) 编写应急计划和后备计划以防本来的计划出现错误。
D) 和项目重要干系人对你风险登记册中的风险进行讨论。
8.What is not a reason for companies to organize lessons learned?
A) Lessons learned databases are an essential element of the organizational process assets.
B) Lessons learned should focus on identifying those accountable for errors and failures.
C) Lessons learned sessions should bring about recommendations to improve future performance on projects.
D) Phase end lessons learned sessions provide a good team building exercise for project staff members.
下列哪一项不是企业组织经验总结的原因?
A) 经验总结数据库是组织过程资产的重要元素。
B) 经验总结必须集中于识别错误和缺陷的责任。
C) 经验总结会议应当提出提议以提升项目将来的绩效。
D) 阶段经验总结会为项目组员提供了很好的团体建设练习。
9.How should change management be planned for?
A) Changes are generally not predictable,therefore planning for change management cannot be sensible.
B) Planning for change management should be done while the various change control processes are being applied.
C) Change management can be planned in a set of management plans or a specific change management plan.
D) Changes are a sign of bad planning.One should avoid changes during a project thus eliminating the need to manage them.
变更管理该怎样计划?
A) 变更一般是不可预测的,因此规划变更管理不明智。
B) 当有不一样的变更控制过程被应用时,必须要规划变更管理。
C) 变更管理能够伴随一系列管理计划而规划,也能够单独进行规划。
D) 变更是规划作得不好的信号,应当在项目执行中防止变更,也就消除了管理它们的需要。
10.Which of the following documents is not used as input for product acceptance?
A) The project scope statement,it describes the acceptance criteria.
B) The project scope management plan,it describes the acceptance process.
C) The work breakdown structure (WBS) ,it describes the deliverables for acceptance.
D) The RACI matrix,it describes accountabllities in case of product rejection.
下列哪个文档不是产品接收的输入?
A) 项目范围阐明书,描述了接收标准。
B) 项目范围管理计划,描述了接收过程。
C) 工作分解结构,描述了可接收的成果。
D) RACI矩阵,描述了产品拒绝时的责任。
11.When should lessons learned be organized?
A) During the project life cycle and at the end.
B) At the end of the project during closing.
C) After the end of the project at a project post-mortem meeting.
D) Lessons learned can be organized when there is time available.
经验总结应当在什么时候被组织?
A) 在项目生命期内以及最后。 B) 在项目收尾最后。 C) 在项目结束后的总结会上。 D) 当有时间的时候随时组织。
12.Understanding of characteristics of people is not part of understanding the cultural and social environment.
A) economic B) individual C) educational D) ethnic and religious
了解人们的 特点不是了解文化和社会环境的一部分。
A) 经济 B) 个人 C) 教育 D) 种族和宗教
13.The concept of the states that changes related to one requirement- scope,time or cost-will at least influence one other element.
A) three point estimation B) triple constraint C) three wise men D) three needs theory
的概念提到,当范围、进度、成本其中一个原因发生变化的时候,将最少影响到其他一个原因。
A) 三点估算 B) 三角形约束 C) 三个聪明人 D) 三个需要理论
14.What is the purpose of a project charter?
A) To address and document the characteristics and houndarjes of the project and its associated products and services.
B) To formally authorize the project and provide th。project manager with the authority to apply organizational resources.
C) To link th。project,whictl is going to be planned,executed,and monitored/controlled to the ongoing work of the organization.
D) To break down the scope of the project into smailer,better manageabie components for further planning and estimating.
项目章程的目标是什么?
A) 识别并统计项目标边界和特点以及有关的产品和服务。
B) 正式授权项目,为项目经理提供权限来使用组织资源。
C) 把将要计划、执行、监控的项目连接到组织的连续运行工作上。
D) 将项目范围分解成更小的、更易管理的部分,用于将来的规划和估算。
15.At the end of the closing process group, .
A) it is verified that the defined processes are completed within all the process groups to close the project phase
B) it is determined that the product of the project is completed satisfactorily
C) project management plan is written off by the project sponsor
D) new change requests are initiated as required
在项目收尾过程组的最后, .
A) 应核算定义的所有过程组的过程已完成,来结束项目阶段
B) 应确定项目标产品被满意地完成
C) 项目管理计划被项目出资人取消
D) 新的变更祈求被开启
16.You have recently appointed a project manager to handle a critical prolect in your organization.You want to provide the project manager with authority to apply organizational resources to project activities.Which document should you use?
A) Resouree authorization document. B) Work breakdown structure.
C) project charter. D) Project scope statement.
你最近指定了某个项目经理负责你组织的核心项目,你想给项目经理权限去应用组织资源到项目活动上。你应当使用哪个文档?
A) 资源授权文档。 B) 工作分解结构。 C) 项目章程。 D) 项目范围阐明书。
17.You are the project manager of a new project,which will construct a bridge on the River Nile in Egypt.Before initiating the project,you should .
A) create a scope management plan to document how the project scope will be defined,verified and controlled
B) develop a project management plan
C) determine specific activities that need to be performed to produce the various project deliverables
D) facilitate the formal authorization to start a new project
你是新项目标项目经理,在埃及尼罗河上建设-座桥梁。在项目开启之前,你应当——。
A) 创建范围管理计划来统计项目标范围怎样被定义、核算和控制
B) 开发项目管理计划
C) 确定详细的活动用来执行产生不一样的项目成果
D) 推进正式授权,开启新项目
18.As a project manager,project plan development is an important element of managing projects.Which phase of the project management Life cycle does project plan development belong to?
A) Initiation process. B) Planning process. C) Execution process. D) Controlling process.
作为项目经理,项目计划开发是管理项目非常重要的元素,下列哪个项目管理生命期阶段包括项目计划编制?
A) 开启过程组。 B) 规划过程组。 C) 执行过程组。 D) 控制过程组。
19.A customer informed you that it is preferable to change a certain aspect of the project.What should you do first?
A) Talk with team members to understand implications of the change.
B) Communicate the change to the management to get their inputs.
C) Open up a change control.
D) Do sizing for the change and communicate to the customer.
客户告诉你最佳变更项目某个方面。你首先应当做什么?
A) 和团体组员交流了解这个变更的影响。
B) 就这个变更和管理层沟通得到他们的输入。
C) 开始变更控制。
D) 分析变更大小,和客户进行交流。
20.In your project,you want to monitor and control project processes associated with initiating,planning,executing and closing.This will help you take corrective or preventive action to control project performance.In this context,what should you do first?
A) Review all project forecasts.
B) Detail all the activities of project team members involved in executing administrative closure for the project.
C) Review the project management plan and work performance information for your project.
D) Manage project risks.
在你的项目中,你想监控项目开启、规划、执行、收尾等过程,这将协助你采取纠正措施或预防措施来控制项目绩效。在这种情况下,你首先应当做什么?
A) 回忆所有项目预测。
B) 在执行管理收尾时详细所有项目团体的活动。
C) 回忆项目管理计划和项目标工作绩效信息。
D) 管理项目风险。
21.You recently joined as the project manager of ABC Company.The outgoing project manager mentioned that of late,she had been facing several issues with new change requests.The customers were located in the same office and they interacted directly with the project team and,at times,informally asked for some changes in the project’s product.If the changes were small,the project team members usually agreed to do the changes.The project manager found it difficult to prioritize activities and ensure that tasks are done as per schedule. The project had 50 team members and there was some discontent amongst them about the work they were supposed to do.What should be your first priority in this project?
A) Create a detailed project scope statement.
B) Align the project objectives with the organizational goals.
C) Ensure proper project scope control.
D) Call a meeting of all the project stakeholders to determine and resolve any outstanding issues.
你最近加入到ABC企业做项目经理。即将离职的项目经理提到,最近公布了几个新的变更祈求。客户处在同样的办公室,能够直接和项目团体进行交互,有时会非正式地提出产品的新变更。假如变更比较小,项目团体组员一般同意这些变更。项目经剪发觉这么极难确定活动的优先级,确保每个进度表的任务被完成。这个项目有50个团体组员,有些对自己的工作不满。你首先应当做什么?
A) 创建详细的项目范围阐明书。
B) 使项目目标和组织目标一致。
C) 确保适宜的项目范围控制。
D) 召开所有干系人会议来确定和处理最明显的问题。
22.In a recent job interview,you were asked to define the most important characteristic of a project manager.Which of the following will be your best answer?
A) Subject matter expert. B) Integrator. C) Creative person. D) Risk minimizer.
最近面试工作,你被要求定义项目经理最重要的特性,下列哪个是你最佳的答案?
A) 行业教授。 B) 整合者。 C) 创造者。 D) 风险低估者。
23.Which of the following is not a project management knowledge area?
A) Project integration management. B) Project procurement management.
C) Project configuration management. D) Project communications management.
下列哪项不是项目管理知识领域?
A) 项目整体管理。 B) 项目采购管理。 C) 项目配备管理。 D) 项目沟通管理。
24.When deciding which project to select. .
A) select the project with higher life cycle cost B) select the project with lower life cycle cost
C) select the project with higher sunk cost D) select the project with lower sunk cost
当决议选择项目时, 。
A) 选择高生命期成本的项目 B) 选择低生命期成本的项目
C) 选择具备高淹没成本的项目 D) 选择具备低淹没成本的项目
25.While doing quality inspection,few defects were identified in the product.After rectifying the defects,the repaired items were reinspected and accepted.Subsequently,a notification was issued,which can also be referred to as .
A) validated defect repair B) product acceptance C) quality audit D) approved change request
当作质量检查时,产品的少数缺陷被识别。在修复这些缺陷后,修复项被重新检查和接收。随即,一个通知被公布,这个通知被称为 。
A) 缺陷修复确认 B) 产品接收 C) 质量审计 D) 同意的变更祈求
26.Project integration management includes the proeesses and activities needed to identify,define,combine,unify and coordinate the various processes and project management activities.For successful project integration management, you should definitely have (select the best option) .
A) a strong matrix organizational structure in your company
B) a good communication management Dlan
C) good project selection techniques
D) positive stakeholders who support the project
项目整体管理包括某些过程和活动,用来识别、定义、整合、协调不一样过程和项目管理活动。为了成功地完成项目整体管理,你应当具备 (选择最佳的选项) 。
A) 强矩阵组织结构 B) 良好的沟通管理计划 C) 良好的项目选择技术 D) 正面支持项目标干系人
27.You have been given a high priority task that needs to be completed within a shor