资源描述
目 录
1、编制依据:···············································1
2、工程概况:···············································1
3、施工部署:···············································1
3.1施工组织管理机构·····································2
3.2人员部署·············································2
3.3施工队人员部署·······································2
3.4周转材料存放·········································3
4、施工前期准备············································3
4.1技术准备·············································3
4.2人员培训·············································3
4.3材料及施工工具准备···································3
5、结构脚手架施工··········································4
5.1结构外架设计·········································4
5.2施工工艺·············································8
5.3脚手架受力计算·······································14
5.4质量标准·············································26
5.5施工中应注意的问题···································28
6、安全措施················································29
6.1外架安全·············································29
6.2安全平网搭设·········································31
6.3脚手架拆卸···········································31
7、环保措施················································31
1、编制依据
1.1 施工图纸及现场概况:
1.2 《建筑施工质量管理标准》(DBJ14—033—2023):
1.3 《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130—2023):
1.4 《建筑施工安全技术手册》:
1.5 《建筑施工计算手册》:
1.6 《建筑施工手册》第四版(缩印本);
1.7 《建筑结构荷载规范》(GB5009—2023):
2、工程概况
序号
项目
内容
1
建设单位
河南财政税务高等专科学校
2
监理单位
郑州中兴工程监理有限公司
3
施工单位
河南建隆建筑安装装饰工程有限公司
4
建筑面积
31353.92㎡
5
建筑层数
地下
1层
地上
12层
6
建筑层高
地下室
3m
标准层
3.5m
机房层
2.93m
7
结构形式
基础形式
筏型基础
结构形式
框架结构
8
建筑高度
地上部分檐高
43.20m
3、施工部署
3.1施工组织管理机构
3.2人员部署
序号
职务
姓名
负责内容
1
项目经理
徐贺卿
对项目部管理人员进行明确分工,各司其职
2
技术负责人
王俊杰
负责分项施工方案的总体框架的拟定,审核技术方案
3
材料主任
贺高举
负责各种外架材料的进场与现场管理
4
技术员
刘亚辉
负责外架施工的技术指导及现场巡视
5
质检员
王振乾
负责外架施工的质量检查
6
栋号长
王堪
负责外架安装及施工现场进度和现场安全巡视
7
测量负责
张廷剑
全面负责项目测量工作及相关内业资料
8
安全负责
乔文杰
全面负责项目安全工作及相关内业资料
3.3施工队人员部署
由于本工程工期紧,质量规定高,为保证工程如期竣工,主体施工期间,各施工队必须配备足够的架子工穿插作业,每个施工队要配备架子工不少于20人,每班设班长一名,所有架子工必须经培训,具有有效期内架子工上岗证。
3.4周转材料存放
根据《施工组织设计》结构施工阶段现场平面布置图设计规定,外脚手架的周转材料使用前及拆除后集中码放在现场指定场地,保持现场整洁、干净。
4、施工前期准备
4.1技术准备
4.1.1 本工程结构外架按照悬挑架进行设计。
4.1.2 根据工程进度情况,编制各种材料的备料计划、计划进场时间安排,保证脚手架及时搭设使用。
4.2 人员培训
4.2.1 对架子工进行上岗培训。
4.2.2 对工人进行安全教育,提高施工人员安全意识。
4.3 材料及施工工具准备
4.3.1 材料准备:
(1)钢管:钢管采用《直缝电焊钢管》(GB/T12793)中规定外经48mm,壁厚3.5mm的3号普通钢管,其化学成份与机械性能符合国家标准《碳素结构钢》(GB/T700)中Q235—A级的规定。脚手架采用的钢管,在螺栓拧紧力矩达成65N.m时,不得发生破坏。
(2)扣件:扣件应符合《钢管脚手架扣件》(GB15831-2023)的规定。采用可铸铁制作的钢管。扣件不能有裂纹、气孔、疏松、砂眼等铸造缺陷。扣件与钢管的贴合面要接触良好,扣件夹紧钢管时,开口处的最小距离要小于5mm。扣件拧紧时,使螺栓方向朝上,防止由于下雨导致扣件滑落松动。
(3)脚手板:采用楠竹制作的竹串片。长度3.0m,厚度45~50mm,宽度28~30cm。
(4)连墙件:连墙件的材质应符合《碳素结构钢》(GB/T700)中Q235—A级钢的规定。
(5)密目安全网:密目网要四证齐全,要有阻燃性能,其续燃、阻燃时间均不得大于4s。要符合GB16909的规定。每10cm×10cm=100cm2的面积上有2023个以上网目。安全网必须做耐贯穿实验,将网与地面成30°夹角拉平,在其中心上方3m,用5Kg重的钢管(管径48-51mm)垂直自由落下,不穿透即为合格产品。用系绳将密目网绑扎至立杆或大横杆上,使网与架体牢固的连接在一起。系绳的材质应符合GB16909的规定。
(6)钢丝绳:采用15.5mm钢丝绳,断面面积89.49mm2,重量169.14kg/m。应满足《一般用途钢丝绳》(GB/T20238—2023)的规定。
4.3.2 施工工具准备:在施工中,需要准备的施工机具有:水准仪、经纬仪、安全帽、安全带、扳手等。
5、结构脚手架施工
5.1 结构外架设计
本工程施工至地上结构时基坑回填土和地下室外墙防水施工,而地上结构外墙施工必须要有脚手架,假如考虑采用落地脚手架,周转材料用量太大,而基坑回填土工程还没有开始,地基条件不能满足规定,考虑从2层以上使用挑架(下面2层施工时采用双排落地脚手架),出挑材料采用18#工字钢,立杆和横杆材料采用48×3.5mm钢管。5层一挑,在2层、7层设立出挑工字钢,每挑搭设总高度为17.5米,具体参数如下:
工字钢横向间距 1.5m
立杆纵距 1.5m 立杆(立杆采用4m和、6m钢管在同步内错开布置、保证钢管接头不在同一平面内)、大横杆(大横杆接头位置错开,错开距离不小于1m)的钢管长度为4~6m,横向水平杆(小横杆)为1.2m。钢管应涂防锈漆。在挑架顶部钢管使用对接连接,使立杆顶端在同一平面上,保证整体效果美观。并在顶部位置设立一道锁口大横杆。
立杆横距 0.9m(立杆全高度垂直度偏差不大于50mm)
大横杆步距 1.8m(外排间距900mm,间距误差及两端水平标高误差不大于20mm)
内排立杆距结构距离 0.30m
小横杆端距结构距离 0.10m
每一立杆与纵向水平杆相交处均设立小横杆,距主节点位置小于15cm,用直角扣件扣紧在纵向水平杆上。小横杆间距与立杆纵距相同,上下层小横杆在立杆处错开布置。为保证外立面统一美观,小横杆伸出外排大横杆边沿距离保证10cm(伸出长度必须保证一致),靠结构一端距结构面10cm,保证模板操作工人可以进行外墙模板的安装、加固及拆除作业。
连墙杆布置: 横距3.0m(每层均设,梅花状布置,刚性连接,连墙件靠近主接点,偏离主节点的距离小于30cm。在梁浇筑前预留短钢管)
剪刀撑:剪刀撑每4跨设立一组,剪刀撑与大横杆夹角为60°,在脚手架外侧立面的整个长度和高度上连续设立。剪刀撑斜杆采用搭接接长,其搭接长度不小于1m,至少采用3个旋转扣件固定,端部扣件距杆端大于10cm,所有固定点距主接点不大于15cm。
脚手板铺设层数 2层
踢脚板 200mm高,三层布置一道
操作层数 2层
施工均匀荷载 2KN/㎡
单立杆高度 :17.4m (10步)
普通18#工字钢 :
截面高度:H=180mm
截面宽度:B=92mm
翼缘厚度:tf=10.7mm
腹板厚度:tw=6.5mm
截面面积:A=3074mm²
惯性距:ix=16990000mm4 截面模量:wx=185400mm³
脚手架立面图
5.2施工工艺
5.2.1施工流程:
在2层、7层楼板砼施工前在结构边埋设钢筋地锚(地锚留设尺寸见上图),悬挑工字钢→摆放扫地杆(贴近工字钢的大横杆)→逐根树立杆,随即与扫地杆扣紧→装扫地小横杆并与立杆或扫地杆扣紧→安装第一步大横杆(与各立杆扣紧)→安装第一步小横杆→第二步大横杆→第二步小横杆→加设临时斜撑(上端与第二道大横杆扣紧,在装设两道连接杆后可拆除)。安装每一步大横杆须水准仪找平。立杆用经纬仪检查垂直度。
5.2.2 每层架子与结构设立点连接,连接点间距为3.0m,每层均设。连接点直接采用短钢管将架子连接在结构楼板上,楼板在浇筑前必须预留连接钢管,具体做法见下图:
5.2.3 作业层的外侧面用1.8m×6m的安全网竖向完全封闭。在架高方向每隔二层设一道水平安全网。安全网的固定和连接必须采用安全网系绳,安全网应从端头、卸料平台、施工电梯洞口处开始布置(具体见外架洞口防护措施)。
5.2.4 脚手架外侧面设剪刀撑,每四跨搭设一道,剪刀撑的斜杆与水平面的交角为60度。
5.2.5 脚手架左右相邻立杆和上下相邻大横杆的接头应互相错开并设立不同的构架框格,且间距大于1000mm。
5.2.6 小横杆设于双立杆之间,搭于大横杆之上,保证每根小横杆距结构边0.1m并用直角扣件扣紧。
5.2.7 大横杆与双立杆中的两根立杆都必须用直角扣件扣紧。
5.2.8 脚手架应从一个角部开始,并向两边交圈搭设。
5.2.9 外架阳角搭设:为了保证脚手架的整体美观,对脚手架阳角处型钢外部立杆设立双立杆,外部立杆为脚手架立杆,内部立杆(在工字钢上焊接25钢筋,立杆套在钢筋上)固定安全网使用。阳角悬挑型钢应避开柱子钢筋预留悬挑洞口,严禁伤害柱子钢筋设立预留洞。
5.2.10洞口防护搭设:
(1)、电梯井道防护做法:主体施工阶段各层电梯井道周边均要设立防护栏杆,第一道距楼面400mm,第二道距楼面1200mm,在防护栏四周满挂安全网,设立安全标示牌。在电梯井处每隔三层设立一道水平大眼网。进入装修阶段电梯井口必须设立不低于1500mm高的金属防护门,井内首层和以上每隔两层(不低于10m)设立一道水平安全网,网边与井道边间隙不得大于200mm,安全网封闭严密。电梯井不得做垂直通道和垃圾通道。通道附近的各类洞口,除设立防护和安全标示牌的同时,夜间须设立红灯警示。布置见下图:
电梯井防护平面图
(2)、本工程凡小于50cm的洞口,须加设盖板。盖板须能保持四周的平衡,并固定。边长50以上的洞口,除加上盖板外,还须在洞口下方设一道水平安全网,洞口四周除设立防护栏杆。
(3)、楼梯两侧须加设两道牢固的防护栏杆,护栏上杆距踏步面1.2m,下杆距踏步面0.6m,护栏两侧挂上安全标语。见下图:
楼梯临边防护图(1)
楼梯平面防护图(2)
(4)、施工电梯外架搭设及防护:由于本工程楼层较高,为了材料的垂直运送,须安装施工电梯。外架立杆、横杆双排设立,防止安装施工电梯导致对脚手架的影响。本工程按照双笼施工电梯考虑,须在每层楼面以上开1500mm×1800mm洞口,洞口周边脚手架采用增长钢管连接以及连墙杆连接加固外架。见下图:
(5)卸料平台:由于主体周转材料量大,为了便于施工,方便材料的周转,须在外架外部搭设卸料平台,卸料平台设立处,外架相应变动:洞口两侧立杆设立双立杆,大横杆设立双排,间距为1/2大横杆间距。挂安全网时,应从端头、卸料平台、施工电梯洞口处开始布置,保证端头处两侧整齐。断头处安全网竖向边与立杆绑扎间距不得超过400mm,绑扎牢固。
(6)临时安全通道防护:
安全通道正立面图
安全通道侧立面图
5.3脚手架受力计算
本工程脚手架为双排脚手架,搭设高度按18m计算,立杆采用单立杆。搭设尺寸:立杆纵距1.50m,立杆横距0.90m,立杆步距1.8m。 采用的钢管为租赁钢管,型号按4.8cm×3.0mm考虑。连墙杆采用层层均设,梅花布置,横距3.0m。施工均匀荷载为2.5KN/㎡,同时施工2层,脚手板共铺设2层。
悬挑型钢为18#工字钢,其中建筑外悬挑长度为1.20m,建筑物内长度为2.80m。悬挑水平钢梁采用钢丝绳与建筑物拉结。
1、大横杆的计算
大横杆按照三跨连续梁进行强度和挠度计算,大横杆在小横杆的上面。按照大横杆上面的脚手板和活荷载作为均匀荷载计算大横杆最大弯矩和变形。
(1)、均布荷载值计算
大横杆的自重标准值 P1=0.038KN/m
脚手板的荷载标准值 P2=0.150×0.90/3=0.045kN/m
活荷载标准值 Q=2.5×0.9/3=0.75kN/m
静荷载计算值 q1=1.2×0.038+1.2×0.045=0.0996kN/m
活荷载计算值 q2=1.4×0. 75=1.05kN/m
(2)、抗弯强度计算
最大弯矩考虑为三跨连续梁均布荷载作用下得弯矩
跨中最大弯矩计算公式如下:
M1max=0.08q1l2+0.10q2l2
跨中最大弯矩为
M1=(0.08×0.0996 +0.10×1.05)×1.22=0.163kN.m
支座最大弯矩计算公式如下:
M2max= -0.10q1l2—0.117q2l2
支座最大弯矩为
M2= -(0.10×0.0996+0.117×1.05)×1.22=-0.13281kN.m
选择支座弯矩和跨中弯矩的最大值进行强度验算:
=0.13281×106/4491.0=29.573N/mm2
大横杆的计算强度小于205.0N/mm2,满足规定!
(3)、挠度计算
最大挠度考虑为三跨梁均布荷载作用下得挠度
计算公式如下:
Vmax=0.677q1l4/100El+0.990q2l4/100El
静荷载标准值q1=0.038+0.045=0.083kN/m
活荷载标准值q2=0. 75kN/m
三跨连梁均步荷载作用下的最大挠度
V=(0.677×0.083+0.090×0.75)×12023/(100×2.06×105×107780)=2.82mm
大横杆的最大挠度小于1200/150与10mm,满足规定!
2、小横杆计算
小横杆按照简支梁进行强度和挠度计算,大横杆在小横杆的上面。用大横杆支座的最大反力计算值,在最不利荷载布置下计算小横杆的最大弯矩和变形。
(1)、荷载值计算
大横杆的自重标准值 P1=0.038×1.200=0.0456kN/m
脚手板的荷载标准值 P2=0.150×0.90×1.200/3=0.054kN/m
活荷载标准值 Q=2.500×0.90×1.200/3=0.90kN/m
荷载的计算值 P=1.2×0.0456+1.2×0.054+1.4×0.90=1.26kN/m
小横杆计算简图
(2)抗弯强度计算
最大弯矩考虑为小横杆自重均布荷载与荷载的计算值最不利分派的弯矩和均布荷载最大弯矩计算公式如下:
集中荷载最大弯矩计算公式如下:
M=(1.2×0.038)×0.902/8+2.001×0.90/3=0.707kN.m
=0.707×106/4491.0=157.369N/mm2
小横杆的计算强度小于205.0N/mm2,满足规定!
(3)、挠度计算
最大挠度考虑为小横杆自重均布荷载与荷载的计算值最不利分派的挠度和
均布荷载最大挠度计算公式如下:
集中荷载最大挠度计算公式如下:
小横杆自重均布荷载引起的最大挠度
V1=5.0×0.0456×0.90.004/(384×2.060×105×107780.000)=0.03mm
集中荷载标准值 P=0.0456+0.054+1.313=1.243kN
集中荷载标准值最不利分派引起的最大挠度
V2=1448.850×900×(3×902-4×9002/9)/(72×2.06×105×107780.0)=2.143mm
最大挠度和
V=V1+V2=2.173mm
小横杆的最大挠度小于900.0/150与10mm,满足规定!
3、扣件抗滑力的计算:
纵向或横向水平杆与立杆连接时,扣件的抗滑承载力按照下式计算:
R ≤ Rc
其中 Rc —— 扣件抗滑承载力设计值,取8.0kN;
R —— 纵向或横向水平杆传给立杆的竖向作用力设计值;
荷载值计算
横杆的自重标准值 P1=0.038×0.9=0.0342kN
脚手板的荷载标准值 P2=0.150×0.9×1.500/2=0.101kN
活荷载标准值 Q=2.500×0.9×1.500/2=1.688kN
荷载的计算值 R=1.2×0.0342+1.2×0.101+1.4×1.688=2.546kN
单扣件抗滑承载力的设计计算满足规定!
4、脚手架荷载标准值:
作用于脚手架的荷载涉及静荷载、活荷载和风荷载。
静荷载标准值涉及以下内容:
(1)每米立杆承受的结构自重标准值(kN/m) :本工程为0.1248
NG1 = 0.125×17.40=2.170kN
(2)脚手板的自重标准值(kN/m2);本例采用竹笆片脚手板,标准值为0.15
NG2 = 0.150×4×1.200×(0.90+0.250)/2=0.485kN
(3)栏杆与挡脚手板自重标准值(kN/m);本例采用栏杆、竹串片脚手板挡板,标准值为0.15
NG3 = 0.150×1.200×4/2=0.450kN
(4)吊挂的安全设施荷载,涉及安全网(kN/m2);0.005
NG4 = 0.005×1.200×17.400=0.135kN
经计算得到,静荷载标准值:
NG = NG1+NG2+NG3+NG4 = 3.416kN
活荷载为施工荷载标准值产生的轴向力总和,内、外立杆按一纵距内施工荷载总和的1/2取值。
经计算得到,活荷载标准值:
NQ = 2.500×2×1.200×0.900/2=3.937kN
风荷载标准值应按照以下公式计算:
其中 W0 —基本风压(kN/m2),按照《建筑结构荷载规范》(GB50009-2023)的规定采用:W0 = 0.450
Uz —风荷载高度变化系数,按照《建筑结构荷载规范》(GB50009-2023)的规定采用:Uz = 1.250
Us —风荷载体型系数:Us = 1.560
经计算得到,风荷载标准值
Wk = 0.7×0.450×1.250×1.560 = 0.614kN/m2
考虑风荷载时,立杆的轴向压力设计值计算公式:
N = 1.2NG + 0.85×1.4NQ
风荷载设计值产生的立杆段弯矩MW计算公式:
MW = 0.85×1.4Wklah2/10
其中 Wk — 风荷载基本风压标准值(kN/m2)
la —立杆的纵距 (m)
h —立杆的步距 (m)
5、立杆的稳定性计算:
(1)不考虑风荷载时,立杆的稳定性计算
其中 N —立杆的轴心压力设计值,N=9.61kN;
—轴心受压立杆的稳定系数,由长细比 l0/i 的结果查表得到0.19;
i —计算立杆的截面回转半径,i=1.60cm;
l0 —计算长度 (m),由公式 l0 = kuh 拟定,l0=3.12m;
k —计算长度附加系数,取1.155;
u —计算长度系数,由脚手架的高度拟定,u=1.50;
A —立杆净截面面积,A=4.24cm2;
W —立杆净截面模量(抵抗矩),W=4.49cm3;
—钢管立杆受压强度计算值 (N/mm2);经计算得到 = 119.63
[f] —— 钢管立杆抗压强度设计值,[f] = 205.00N/mm2;
不考虑风荷载时,立杆的稳定性计算 < [f],满足规定!
(2)、考虑风荷载时,立杆的稳定性计算
其中 N —立杆的轴心压力设计值,N=8.79kN;
—— 轴心受压立杆的稳定系数,由长细比 l0/i 的结果查表得到0.19;
i —— 计算立杆的截面回转半径,i=1.60cm;
l0 —— 计算长度 (m),由公式 l0 = kuh 拟定,l0=3.12m;
k —— 计算长度附加系数,取1.155;
u —— 计算长度系数,由脚手架的高度拟定;u = 1.50
A —— 立杆净截面面积,A=4.24cm2;
W —— 立杆净截面模量(抵抗矩),W=4.49cm3;
MW —— 计算立杆段由风荷载设计值产生的弯矩,MW = 0.355kN.m;
—— 钢管立杆受压强度计算值 (N/mm2);经计算得到 = 188.44
[f] —— 钢管立杆抗压强度设计值,[f] = 205.00N/mm2;
考虑风荷载时,立杆的稳定性计算 < [f],满足规定!
6、连墙件的计算:
连墙件的轴向力计算值应按照下式计算:
Nl = Nlw + No
其中 Nlw —— 风荷载产生的连墙件轴向力设计值(kN),应按照下式计算:
Nlw = 1.4 × wk × Aw
wk —风荷载基本风压标准值,wk = 0.614kN/m2;
Aw—每个连墙件的覆盖面积内脚手架外侧的迎风面积,Aw = 3.60×4.50 = 16.200m2;
No —连墙件约束脚手架平面外变形所产生的轴向力(kN);No = 5.000
经计算得到 Nlw = 13.931kN,连墙件轴向力计算值 Nl = 18.931kN
连墙件轴向力设计值 Nf = A[f]
其中 —— 轴心受压立杆的稳定系数,由长细比 l/i=25.00/1.60的结果查表得到=0.96;
A = 4.24cm2;[f] = 205.00N/mm2
通过计算得到 Nf = 83.433kN
Nf>Nl,连墙件的设计计算满足规定!
7、悬挑梁的受力计算:
悬挑脚手架的水平钢梁按照带悬臂的连续梁计算。
悬臂部分脚手架荷载N的作用,里端B为与楼板的锚固点,A为墙支点。
本工程中,脚手架排距为900mm,内侧脚手架距离墙体300mm,支拉斜杆的支点距离墙体 = 1300mm,
水平支撑梁的截面惯性矩I=16990000mm4,截面模量W=185400mm³,截面积A = 3074mm²
受脚手架集中荷载 P=9.61kN
水平钢梁自重荷载 q=1.5×26.10×0.0001×7.85×10=0.35kN/m
悬挑脚手架示意图
悬挑脚手架计算简图
通过连续梁的计算得到
悬挑脚手架支撑梁剪力图(kN)
悬挑脚手架支撑梁弯矩图(kN.m)
悬挑脚手架支撑梁变形图(mm)
各支座对支撑梁的支撑反力由左至右分别为
R1=11.001kN,R2=9.360kN,R3=-0.399kN
最大弯矩 Mmax=1.266kN.m
抗弯计算强度 f=M/1.05W+N/A=1.266×106/(1.05×185400)+4.469×1000/3074=15.262N/mm2
水平支撑梁的抗弯计算强度小于215.0N/mm2,满足规定!
8、悬挑梁的整体稳定性计算:
水平钢梁采用18号工字钢,计算公式如下
其中 b —— 均匀弯曲的受弯构件整体稳定系数,查表《钢结构设计规范》(GB50017-2023)附录B得到:
b=2.00
由于b大于0.6,按照《钢结构设计规范》(GB50017-2023)附录B其值用b'查表得到其值为0.929
通过计算得到强度 =1.27×106/(0.929×185400)=10.64N/mm2;
水平钢梁的稳定性计算 < [f],满足规定!
9、拉杆的受力计算:
水平钢梁的轴力RAH和拉钢绳的轴力RUi按照下面计算
其中RUicosi为钢绳的拉力对水平杆产生的轴压力。
各支点的支撑力
RCi=RUisini
按照以上公式计算得到由左至右各钢绳拉力分别为
RU1=11.874kN
10、拉杆的强度计算:
拉绳或拉杆的轴力RU我们均取最大值进行计算,为RU=11.874kN
拉杆的强度计算:
上面拉杆以钢管100.0×10.0mm计算,斜拉杆的允许压力按照下式计算:
=N/A < [f]
其中 N —— 斜拉杆的轴心压力设计值,N = 11.87kN;
A —— 斜拉杆净截面面积,A =29.85cm2;
—— 斜拉杆受拉强度计算值,经计算得到结果是 3.98 N/mm2;
[f] —— 斜拉杆抗拉强度设计值,f = 215N/mm2;
受拉斜杆的稳定性计算 < [f],满足规定!
斜撑杆的焊缝计算:
斜撑杆采用焊接方式与墙体预埋件连接,对接焊缝强度计算公式如下
其中 N为斜撑杆的轴向力,N=11.874kN;
lwt为焊接面积,取3184.52mm2;
ft或fc为对接焊缝的抗拉或抗压强度,取185.0N/mm2;
通过计算得到焊缝抗拉强度 = 11873.87/2984.52 = 3.98N/mm2。
对接焊缝的抗拉或抗压强度计算满足规定!
11、锚固段与楼板连接的计算:
1.水平钢梁与楼板压点假如采用钢筋拉环,拉环强度计算如下:
水平钢梁与楼板压点的拉环受力R=9.360kN
水平钢梁与楼板压点的拉环强度计算公式为
其中[f]为拉环钢筋抗拉强度,每个拉环按照两个截面计算,按照《混凝土结构设计规范》10.9.8[f] = 50N/mm2;
所需要的水平钢梁与楼板压点的拉环最小直径 D=[9360×4/(3.1416×50×2)]1/2=11mm
水平钢梁与楼板压点的拉环一定要压在楼板下层钢筋下面,并要保证两侧30cm以上搭接长度。
2.水平钢梁与楼板压点假如采用螺栓,螺栓粘结力锚固强度计算如下:
锚固深度计算公式
其中 N —— 锚固力,即作用于楼板螺栓的轴向拉力,N = 9.36kN;
d —— 楼板螺栓的直径,d = 20mm;
[fb] —— 楼板螺栓与混凝土的允许粘接强度,计算中取1.5N/mm2;
h —— 楼板螺栓在混凝土楼板内的锚固深度,通过计算得到 h 要大于9359.82/(3.1416×20×1.2)=99.3mm。
3.水平钢梁与楼板压点假如采用螺栓,混凝土局部承压计算如下:
混凝土局部承压的螺栓拉力要满足公式
其中 N —— 锚固力,即作用于楼板螺栓的轴向拉力,N = 9.36kN;
d —— 楼板螺栓的直径,d =20mm;
b —— 楼板内的螺栓锚板边长,b=5d=100mm;
fcc —— 混凝土的局部挤压强度设计值,计算中取0.95fc=13.59N/mm2;
通过计算得到公式右边等于131.6kN
楼板混凝土局部承压计算满足规定!
5.4 质量标准
5.4.1 对进场的钢管、扣件进行专项检查,对于严重锈蚀、变形、出现裂纹及其他不符合标准情况的不得在承重脚手架工程上使用,符合规定的钢管使用时应涂刷防锈漆。
5.4.2 程使用的钢管、扣件,实行“谁使用,谁负责”的制度,项目劳务队要与生产或租赁单位签订质量担保协议,查验和保存生产许可证、产品合格证、检测报告等有关资料,加强对钢管、扣件的进场验收。质量合格资料不全和未按照标准规定铸有商标的产品不得验收进场。结点连接可靠,扣件的拧紧限度应控制在扭力矩达成40-60N/m。
5.4.3 脚手架搭设稳固,扣件紧固力矩达成设计规定。安全网与架体连接牢固,无漏掉部位。架子地基解决符合设计规定,架子底部垫有脚手板。脚手板用8#铅丝固定牢固,杜绝大于200mm的探头板出现。
5.4.4 脚手架构架搭设步距、横距、排距、连墙件布置等符合设计尺寸,内侧立杆距墙300mm。
5.4.5 钢管探头统一为10cm,允许偏差2cm。扣件的使用不得缺少,不得有松动和有裂痕的等不合格扣件以免影响结构安全。
5.4.6 密目安全网悬挂整齐、美观、牢固。密目安全网用配套的绳子绑在大横杆上。并且将密目网拉紧、拉直、平整。钢管涂刷的油漆颜色均匀、美观。水平杆、立杆为黄色,剪刀撑为红白色。
5.4.7 脚手架的平常检查按以下规定进行,检查合格后,方允许继续使用。
(1)、定期检查悬挑件是否松动;立杆是否悬空;扣件螺栓是否松动;立杆的沉降与垂直度是否符合规范规定;安全防护措施是否符合规定。
(2)、对检查出得不合格的材料及安全隐患应及时整改;
(3)、建立三级巡查制度:1、班组自检;2、标段复查;3、项目部抽查。并做好记录,逐项限时贯彻整改。
(4)、不定期组织在楼上作业的班组进行交底,明确成品保护(立杆、横杆、安全网的保护)及安全操作意识,以保证搭设完好的脚手架不受二次破坏。
5.4.8 脚手架搭设及验收质量标准:
项目
技术规定
允许偏差
检查方法
地基基础
表面
坚实平整
/
观测
排水
无积水
垫板
不滑动
底座
沉降
-10mm
立 杆 垂 直 度
验收垂直度偏差
H/800
±100mm
经纬仪、吊线和卷尺
搭设中检查
不等高的允许值
H=2m
±5mm
H=5m
±8mm
H=10m
±13mm
H=15m
±20mm
H=17.4m
±40mm
间距
步距
±20mm
钢尺
柱距
±50mm
排距
±20mm
5.5 施工中应注意的问题
5.5.1 扣件安装注意开口方向,用于连接大横杆的对接扣件,开口应朝架子内侧螺栓向上,避免开口朝上,以防雨水进入。
5.5.2 安全网设立在立杆与大横杆内侧,立杆及大横杆用4m~6m长黄色钢管搭接,剪刀撑用6m长红白相间钢管搭设,严格控制立杆的垂直度,水平杆的水平度,保证搭设的架子牢固耐用、美观整齐。
5.5.3 现场应修建安全网清洗池(2m×3m),清洗池高0.4m,安全网定期清洗。
6、安全措施
6.1 外架安全
6.1.1 架子使用的材料扣件必须进行检查。
6.1.2 维护用的扣件必须100%检查,是否有裂纹、砂眼等质量缺陷,有缺陷的一律弃用。
6.1.3 严格按照规定的构造尺寸进行搭设,立杆的垂直度偏差不大于50mm和横杆的水平偏差不大于20mm,并保证节点连接达成规定。
6.1.4 脚手板要铺满、铺平并固定,不得有探头板。
6.1.5 架子外挂安全网,挡脚板高20cm,架子上不允许堆放物品,只作为人行通道。
6.1.6 搭设过程中要及时设立连墙杆(每层均设,水平间距3.0m)、斜撑
展开阅读全文