1、(完整word)研究生外文文献翻译-中英完整版Discussion about the application of the anchor bar on the slope constructionFu Ming Fu , Zhang TianAbstract: There are some advantages in strengthening slope with the anchor bar, such as low project cost, convenient for construction and so on。 It not only meets the requirement
2、 of the reliability of the construction, but also is economic and reasonable for the construction.Key words: anchor bar; slope; strengthening1. Introduction Anchor technique uses strata geotechnicals shear strength around bolt to deliver structures pulling force or keep strata of the excavation own
3、stability. Due to the use of the anchor rod, Anchor strata produce compressive zone and have reinforcement effect to strata, can enhance the strength of strata, improve mechanical properties of strata, make structure and stratum together formed a kind of work together complex. Anchor system can effe
4、ctively sustain tension and shear, improve shear strength of the potential sliding surface, so it can effectively prevent slope to produce sliding damage. Fig 1 after excavation of the slope2. Project profile The length of a slope is about 60m, the most slope height is about 23m,the angle up to 50 7
5、5, a five-layer frame structure buildings is far from about 1.5 to 4m at its base edge, its foundation is artificial bored pile and its bearing stratum is in weathered phyllite。 Due to the strong weathering of rocks, it was chunky, loosely structured, multimuddy filling。 It has residual slope deposi
6、ts of silty clay overlying and local folder with a pulpy, low strength。 Slope had collapsed at various locations, it is vary dangerous to the building, so we need to reinforce the slope, and we use stone concrete retaining wall and bolt to support it。3. Bolt retaining and protecting design3.1 Bolt d
7、esign(1)all formation of anchor use whole length bond-type, the binder materials are ordinary cement mortar, the mortar strength grade is M30, the anchor length L is 10 meters, the slope height h is 9 meters. Anchoring section length is 5m。(2)According to the construction condition and the needs of
8、the process, the layout form of anchor use quincunx, and in order to make the anchoring force in the role of surface rock surface with uniform, the two adjacent line bolts should be staggered arrangement.(3)The anchors number according to h/3.24 per meter to calculation, the anchor length is L, a to
9、lal of 252。 The diameter of drilling holes is 90,the number of drill according to (L0。1)m per hole to calculation, M30 grout number according to average 0。052m3 per hole to calculation。(4)The two adjacent rows vertical spacing of anchor take 2.55m, horizontal spacing take 2。55m。 The dip angle of anc
10、hor: with the angle of horizontal line is 20, and drilling down with this Angle.(5)Anchor use the steel bar, which is HRB400 level, 28mm diameter。3.2 Anchor calculation (1)The calculation of lateral geotechnical pressure12When the supporting structure to leave in rock and earth mass direction migrat
11、ion until to the limit equilibrium state, the geotechnical pressure which is role in supporting structure called active geotechnical pressure。 Its calculation method is as follows:For the slope which has no flare structure surface, generally speaking, failure is controled by rock mass strength, the
12、calculation formula is same to the active soil pressure, but cohesive force C take zero, internal friction angle use (rock mass equivalent internal friction angle) instead of, according to the standard to selection; rupture angle is 45+/2(is rock mass internal friction angle, is estimationed by hair
13、cut at the standard of rock mass internal friction angle, reduction factor according to the standard to selection)。According to the engineering survey, active rock pressure can calculation as follows:(2)the calculation of anchor tension design value (1) (2)In the formula: is anchor tension design va
14、lue; is anchor tension standard value; is partial load factor, take 1。3; is the horizontal tension standard value of anchor; is the dip angle of anchor。Through the calculation, =112.3kN =145。99kN(3)the calculation of anchor steel section area (3)In the formula: is the steel section area of anchor; i
15、s slope engineering importance coefficient(the slope engineering importance coefficient of this project is level 1, take 1.1); is the tensile working conditions coefficient of anchor bar ( permanent anchor take 0.69, temporary anchor take 0。92); is the tensile strength design value of anchor bar(sta
16、ndard value=400, design value=360)。According to the calculation, 0。588,choose level 3 steel of 128mm, =0.615。(4)The calculation of anchorage body and rock mass anchoring lengthanchoring length should not only meet the requirements which the bond force of formation on mortar and the bond stress of mo
17、rtar on steel, but also meet the requirements that the Structure design codes the Minimum anchoring length. (4)In the formula: is the anchoring length; D is the diameter of anchorage body; is the bond strength eigenvalue of layer and anchorage body, through the experiment or local experience sure, o
18、r according to the standard to selection ( this engineerings rock mass uniaxial compressive strength is 7。46, belong to soft rock, rock mass structural plane development, take 300);is the bond working conditions coefficient of anchorage body and layer (permanent anchor take 1.00). According to the c
19、alculation, 4.3m, take=5。0m.(5)The anchoring length between anchor steel and anchor mortar (5)In the formula: is the anchoring length between steel and mortar; d is the diameter of anchor bar; n is the number of steel; is the bond strength design value between steel and anchor mortar, through the ex
20、periment sure, or according to the standard take 2.40; is the working conditions coefficient of steel and mortar bond strength(permanent anchor take 0。60). According to the calculation, 2.1m,take =5。0m。3.3 The construction technology and key points of anchor The anchors construction technology is as
21、 follows: build-up scaffold-excavate and clear up the slope surface-measures to fix positiondrill holewashing holebolt put in a certain placegrout-colligation the end of the anchorflushing the slope surface-pouring frame space-Spray seed(1)This slope belong to rocky slope, after excavate the slope 1
22、0 cm to the underside of the frame space, set bolt and pouring frame space, then spray grass or seeds after borrowed soil 20 cm in the frame space.(2)the slope should be payed attention to clean up, when construction。 The anchor should be placed after wash hole, then put pressure (0.4MPa) and grout。
23、 After the mortar fully solidification, colligation steel, castinplace reinforced concrete frame space, bend the end of the anchor and bind point by point with the skeleton steel。(3)Before drilling, the hole should be measured to fix position and then do mark。 Pitch deviation is less than 150mm, hol
24、e depth error is less than 50mm. Try not remold the surrounding rock, when drill。 Before Put the anchor, it should be attentioned that blow wash clean the water of the hole and rock powder and so on, and rust removal the body of rod。 When grouting, builders should attention the grouting pressure and
25、 mortar ratio. Fig 2 anchor field construction drawing4. ConclusionIt is economical to reinforcement slope with bolt, and use the normal equipment, It is not only achieve safe and also economy and rational.(1) Today bolt technology is widely used in the project. It is an effective reinforcement meas
26、ures to constraints sliding soil with the combining of bolt and concrete slope protection.(2) We must be sure to do geological exploration work of the slope to find out the nature of the rock and hydrogeological situation before reinforcing slope by grouting bolt. (3) Due to the factors of engineeri
27、ng geological conditions, grouting pressure and construction technology, we should be given adequate attention to the quality of construction. Reference1Technical code for building slope engineering (JGJ 120-99)。 The Peoples Republic national standards. Beijing: China Architecture Building PRESS.2 Y
28、ing-Ren Zheng, ZuYu Chen etc. Engineering Treatment of Slope & Landslide M. Beijing:China Communications Press,20073 LuoZhenHai。 Talk shallowly the application of the anchor at the slope reinforcementJ。 Fujian Construction Science Technology,2010,06:15-16浅谈锚杆技术在边坡工程中的应用1.引言锚杆技术是利用锚杆周围地层岩土的抗剪强度来传递结构物
29、的拉力或保持地层开挖面的自身稳定。由于锚杆的使用,使锚固地层产生压应力区并对地层起到加筋作用,来增强地层的强度,改善地层的力学性能,使结构与地层一起形成一种共同工作的复合体。锚杆体系其能有效地承受拉力和剪力,能提高潜在滑移面上的抗剪强度,有效地阻止坡体产生滑动破坏. 2。工程概况某边坡长约60m,最大坡高约23m,坡度达5075,为岩质边坡。距坡底边缘约1.54m处有1栋5层框架结构建筑物, 人工挖孔灌注桩基础,建筑物以中风化千枚岩为持力层。因岩石风化强烈,呈碎块状,结构松散,多为泥质充填.上覆残坡积粉质粘土,局部夹有泥状,强度较低。边坡坡体多处位置曾发生崩塌,对建筑物存在威胁,所以需对边坡进
30、行加固,采用的是块石混凝土挡墙+锚杆进行支护。3。锚杆支护设计3。1 锚杆的设计(1)采用全长黏结式锚杆,黏结材料为普通水泥砂浆,砂浆强度等级为M30,锚杆长度L为10米,防护边坡高度h为9米。锚杆锚固段长度为5m。(2)锚杆的布置形式根据施工条件及工艺的需求采用梅花行布置,且为了使锚杆的锚固力均匀作用于岩体表面,应采用相邻两行的锚杆错开布置。(3)锚杆数量按每延米h/3。24根计,锚杆长度为L,共计252根。钻孔直径为90,钻孔数按(L0。1)m/孔计, M30注浆数量平均按0。052m3/孔计.(4)锚杆的上、下排垂直间距取2。55m,水平间距2.55m。锚杆倾角:与水平线成20角度向下成
31、孔。(5)锚杆杆体选用直径为28mm的HRB400级钢筋。3。2 锚杆计算(1)侧向岩土压力的计算12当支护结构向离开岩土体方向偏移至岩土体达到极限平衡状态时,作用在支护结构上的岩土压力称为主动岩土压力.其计算方法如下:对于无外倾结构面的边坡,一般发生由岩体强度控制的破坏,计算公式按主动土压力计算,但粘聚力C取零,内摩擦角用(岩体等效内摩擦角)代替,按表取值;破裂角按45+/2(为岩体内摩擦角,由岩块内摩擦角标准值折减确定,折减系数按表取值)确定。根据地勘报告可知,边坡岩体类型为类,取等效内摩擦角为40,计算可得主动岩石压力 (31)其中:为20kN/;H为9m;= =0。217通过计算可得=
32、175。77 kN/m.(2)锚杆轴向拉力设计值的计算 (32) (33)其中:为锚杆轴向拉力设计值;为锚杆轴向拉力标准值;为荷载分项系数,取1。3;为锚杆所受水平拉力标准值;为锚杆倾角。通过计算可得=112.3kN =145.99kN(3)锚杆钢筋截面面积的计算 (34)其中:为锚杆钢筋截面面积;为边坡工程重要性系数(本工程边坡工程安全等级为一级,取1。1);为锚筋抗拉工作条件系数(永久性锚杆取0。69,临时性锚杆取0。92);为锚筋抗拉强度设计值(标准值=400,设计值=360)。根据计算可得0.588 ,选用128mm的三级钢,=0。615.(4)锚杆锚固体与岩土体锚固长度的计算锚杆锚固
33、段长度除应同时满足地层对砂浆的粘结力和砂浆对钢筋的握裹力要求外,还应满足构造设计规定的最少锚杆锚固长度的要求。 (35)式中: 为锚固段长度;D为锚固体直径;为地层与锚固体粘结强度特征值,通过实验或当地经验确定,也可按表选取(本工程岩体单轴抗压强度为7.46,属软岩,岩体结构面发育,取为300);为锚固体与地层粘结工作条件系数(永久性锚杆取1.00)。通过计算可得4.3m,实际取=5。0m。(5)锚杆钢筋与锚固砂浆间锚固长度的计算 (36)式中: 为锚筋与砂浆间的锚固长度;d为锚筋直径;n为钢筋根数;为钢筋与锚固砂浆间的粘结强度设计值,由试验确定,也可按表取为2。40;为钢筋与砂浆粘结强度工作
34、条件系数(永久性锚杆取0.60)。由公式计算可知2。1m,实际取=5.0m。3.3 锚杆施工工艺与要点锚杆施工的工艺流程为:搭设脚手架坡面开挖整修测量定位钻孔-清孔锚杆安放-注浆-锚杆端部绑扎冲洗坡面浇框格喷草籽(1)本边坡为石质边坡,坡面开挖10cm至框格底面后设锚杆、浇框格,再在框格内客土20cm后喷播草、灌籽。(2)施工时应注重边坡清理,锚杆孔清孔后方可放置锚杆并加压(0。4MPa)注浆,在孔内砂浆充分凝固后扎筋,现浇钢筋砼框格,锚杆端部弯折并与纵横骨架筋间逐点绑扎。(3)钻孔前需测量定位,做好标记,孔距偏差小于150mm,孔深误差小于50mm。钻孔时尽量不扰动周围岩层,安放锚杆前注意将
35、孔内积水和岩粉等吹洗干净且杆体应除锈。注浆时注意注浆压力及砂浆配比.图3.7锚杆现场施工图4.结论边坡工程采用锚杆进行边坡加固,工程造价较低,对施工器械要求不高,在达到安全可靠的同时兼顾了工程施工的经济性和合理性。(1)当今锚杆技术在工程中被广泛应用。将锚杆和混凝土护坡相结合,约束滑动土体。是一种有效的加固措施。(2)在利用灌浆锚杆加固边坡前,一定要做好边坡的地质勘探工作.摸清各岩层的性质和水文地质情况。(3)由于工程地质条件、灌浆压力、施工技术等因素影响,加固施工质量应给与足够的重视。参考文献1建筑边坡工程技术规范(JGJ 12099).中华人民共和国国家标准.北京:中国建筑工业出版社.2郑
36、颖人、陈祖煜等. 边坡与滑坡工程治理 M。北京:人民交通出版社,20073罗贞海。 浅谈锚杆在边坡加固中的应用J. 福建建设科技,2010,06:15-16荆轲,一个四处为家的刺客,他的心犹如浮云,心如飘蓬,是没有根的,然而高渐离的筑声,却成了他愿意停留在燕国这片土地上的原由。虽是初见,却如故人。也许所有的遇见,早已经是前世的注定,没有早晚,刚好在合适的时间遇见你,就是最美的相识.他曾经游历过多少地方,自己已经数不清,但是没有一处可以挽留他行走的脚步,唯有今日高渐离的筑声,让他怎么也舍不得离开。从此二人心性相投,在燕国集市上,载歌击筑,把盏言欢,欢喜处。嬉笑开颜,忧伤处,潸然泪下,即便这些神经
37、质的状态,被集市上的人哗然,可是对知己而言,又如何呢?人生难得一知己,悲欢喜悦与何人相干呢?我们各自欢喜就好.生为乱世,能够遇到如此懂得自己的人,是一件多么难得的幸福事情啊!然而,这快意的知己日子,总归逃不过那个时代的残酷,千不该,万不该,荆轲不该是一位刺客,若不如此,又如何会被愚蠢的太子丹派去刺杀秦王,一去不复返。倘若荆轲不是刺客,也就更不可能身如飘蓬,居无定所,也许不可能遇见高渐离,所有一切都是冥冥之中的注定吧!“风萧萧兮,易水寒,壮士一去兮,不复还。知己的离去,让高渐离心如刀割,整日独自击筑高歌,在痛苦中浑噩度日,这样疏懒的生活,无人懂他,对他来说已经倦怠了,他厌倦了这种孤独和苟且的日子
38、.他本可以大隐于野,疏远于喧嚣处,可是他同样选择了一条不归路.去咸阳宫为上宾演奏,最终被人认出,他并不害怕,倒是坦然自若。因为他心里清楚这里就是染过他知己荆轲的鲜血的宫殿,若能在这里死去,也算是一种缘分。然而事与愿违,秦王并没杀了他,给他一个痛快,而是熏瞎了他的双目,让他生不如死。在一次次的心伤中,他在筑中灌满了铅,仿效荆轲,想与秦王同归于尽,只是他心里非常清楚,他根本伤及不了秦王毫发.他之所以如此,以卵击石,无非就是想痛快死去,是一种求死的方式罢了。千百年以后,后人深记那易水的水有多寒冷,那易水的风有多刺骨.那句“风萧萧兮,易水寒,壮士一去兮,不复还里融入了多少痛苦和无奈?几千年之后,易水的水,易水的风,易水的雪,一年复一年,而那个凄美的故事,也这样经久不衰的传颂着.不由让我又想起伯牙绝弦的故事来,因为知己子期的离世,伯牙绝弦谢知音.人世间有一种高山流水的知己,叫伯牙和子期,也有一种侠义知己,叫荆轲与高渐离。古语曰:“士为知己者死。”这可能是世间最高的知己情意了吧!人生漫漫,朋友易得,知己难求。知己情,是我们需要用生命去珍惜和呵护的情意。然而这个时代,情意似乎越来越廉价,从深交到陌生.若你遇到知己情,别忘了好好珍惜。